Resolved that authority be delegated to the Director (Planning and Development) in consultation with the Leader of the Executive and the Section 151 Officer, to award a build contract to Westridge Construction Limited following a selection process via the South East Consortium for 7 x 1 bed bungalows and associated parking, landscaping and improvements to the wider green space on land at Constable Road/Rembrandt Drive.
Word for word from the decision Gravesham published for this meeting.Source: democracy.gravesham.gov.uk
Reporting officer: Director (Planning and Development)
Subject: Development on Land at Constable Road/Rembrandt Drive
Purpose and summary of report: To seek authority to award a build contract for the development of 7 new Council homes on land at Constable Road/Rembrandt Drive. Recommendations: 1. That authority be delegated to the Director (Planning and Development) in consultation with the Leader of the Executive and the Section 151 Officer, to award a build contract to Westridge Construction Limited following a selection process via the South East Consortium for 7 x 1 bed bungalows and associated parking, landscaping and improvements to the wider green space on land at Constable Road/Rembrandt Drive.
1. Constable Road/Rembrandt Drive
A planning application for the above development was submitted by the Council and presented to the former Regulatory Board (now Planning Committee) in February 2020. The application (reference 20190833) was recommended for permission subject to conditions. Full permission was subsequently granted at that meeting.
2. Tender Process
2.1Potter Raper Limited is appointed as the Council’s Employers Agent. PRP has prepared tender documents based on the drawings submitted to the LPA and the Council’s agreed Employer’s Requirements, and has submitted these to the South East Consortium (SEC) Framework to which the Council has membership.
2.2Potter Raper Limited provided an estimate for the works which was confirmed as being in excess of the Key Decision threshold of £100,000.
2.3Tender documents have been received and Potter Raper Limited, in consultation with officers from the Housing Strategy and Development team, has evaluated the tenders and provided a tender report for the Design and Build of 7 x 1 bed bungalows. 2.4 Following post-tender evaluation, Potter Raper Limited has recommended Westridge Construction Limited be awarded the Design and Build Contract for the scheme. Details of the costs can be found at Appendix 2 which is in the private part of this agenda.
3. Viability
3.1Officers from the Finance Department have assessed the scheme based on an Affordable Rent tenure using current Local Housing Allowance rates which gives a payback period of approximately 38 years.
4. Funding.
4.1As from April 2012, the Department for Communities and Local Government (now MHCLG) announced that it would allow a local housing authority to retain some Right to Buy (RTB) receipts, provided that it could demonstrate that it had spent a sufficient amount on replacement affordable housing. Gravesham Borough Council signed the agreement with CLG in the first quarter of 2012 thereby confirming a commitment to delivering affordable housing.
4.2In return the authority agreed that RTB receipts will not make up more than 30% of total spend on additional stock and to return any unused receipts (after a period of three years from initial receipt) plus interest at 4% above base rate to the Secretary of State.
4.3On 25 February 2020, Full Council approved the Housing Capital Programme for 2020/21 which included £11.575m of capital funding for the council’s New Build/Acquisition Programme. Development of this site will form part of the delivery of this programme.
4.4The construction of the new homes will be met by the most appropriate source of funding such as the HRA reserve or borrowing, with the net increase in homes being funded in part by 30% retained RTB receipts and the remaining 70% being funded from the most appropriate source as part of the Council’s entire borrowing requirement for 20/21 and 21/22.
5. Finance Update
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.