Development on Land at Constable Road/Rembrandt Drive

Decided Executive 1 paper

Cabinet decided this item on Monday 4 January 2021. Below is the council's own wording, with the papers it was decided on.

Item60

Resolved

Resolved that authority be delegated to the Director (Planning and Development) in consultation with the Leader of the Executive and the Section 151 Officer, to award a build contract to Westridge Construction Limited following a selection process via the South East Consortium for 7 x 1 bed bungalows and associated parking, landscaping and improvements to the wider green space on land at Constable Road/Rembrandt Drive.
Word for word from the decision Gravesham published for this meeting. Source: democracy.gravesham.gov.uk

Follow this further

Built from Gravesham's papers

What the report saysPro

Report to Cabinet

Classification: Public Key Decision: Yes

Gravesham Borough Council

Report to: Cabinet

Date: 4 January 2021

Reporting officer: Director (Planning and Development)

Subject: Development on Land at Constable Road/Rembrandt Drive

Purpose and summary of report: To seek authority to award a build contract for the development of 7 new Council homes on land at Constable Road/Rembrandt Drive. Recommendations: 1. That authority be delegated to the Director (Planning and Development) in consultation with the Leader of the Executive and the Section 151 Officer, to award a build contract to Westridge Construction Limited following a selection process via the South East Consortium for 7 x 1 bed bungalows and associated parking, landscaping and improvements to the wider green space on land at Constable Road/Rembrandt Drive.

1. Constable Road/Rembrandt Drive

A planning application for the above development was submitted by the Council and presented to the former Regulatory Board (now Planning Committee) in February 2020. The application (reference 20190833) was recommended for permission subject to conditions. Full permission was subsequently granted at that meeting.

2. Tender Process

2.1Potter Raper Limited is appointed as the Council’s Employers Agent. PRP has prepared tender documents based on the drawings submitted to the LPA and the Council’s agreed Employer’s Requirements, and has submitted these to the South East Consortium (SEC) Framework to which the Council has membership.

2.2Potter Raper Limited provided an estimate for the works which was confirmed as being in excess of the Key Decision threshold of £100,000.

2.3Tender documents have been received and Potter Raper Limited, in consultation with officers from the Housing Strategy and Development team, has evaluated the tenders and provided a tender report for the Design and Build of 7 x 1 bed bungalows. 2.4 Following post-tender evaluation, Potter Raper Limited has recommended Westridge Construction Limited be awarded the Design and Build Contract for the scheme. Details of the costs can be found at Appendix 2 which is in the private part of this agenda.

3. Viability

3.1Officers from the Finance Department have assessed the scheme based on an Affordable Rent tenure using current Local Housing Allowance rates which gives a payback period of approximately 38 years.

4. Funding.

4.1As from April 2012, the Department for Communities and Local Government (now MHCLG) announced that it would allow a local housing authority to retain some Right to Buy (RTB) receipts, provided that it could demonstrate that it had spent a sufficient amount on replacement affordable housing. Gravesham Borough Council signed the agreement with CLG in the first quarter of 2012 thereby confirming a commitment to delivering affordable housing.

4.2In return the authority agreed that RTB receipts will not make up more than 30% of total spend on additional stock and to return any unused receipts (after a period of three years from initial receipt) plus interest at 4% above base rate to the Secretary of State.

4.3On 25 February 2020, Full Council approved the Housing Capital Programme for 2020/21 which included £11.575m of capital funding for the council’s New Build/Acquisition Programme. Development of this site will form part of the delivery of this programme.

4.4The construction of the new homes will be met by the most appropriate source of funding such as the HRA reserve or borrowing, with the net increase in homes being funded in part by 30% retained RTB receipts and the remaining 70% being funded from the most appropriate source as part of the Council’s entire borrowing requirement for 20/21 and 21/22.

5. Finance Update

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Development on Land at Constable Road/Rembrandt DriveReport 97 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Gravesham

Search all
  1. Development on Land at Constable Road/Rembrandt DriveThis decision
  2. Development of Land at Milton Place - Part AAgreed
  3. Development on Land at Valley Drive, GravesendDecided
  4. Development on Land at Whitehill and Nansen Road, GravesendRefused
  5. To consider a report in respect of the disposals and acquisition of interests in land belonging to the Council and the redevelopment of land belonging to the Council.Approved
  6. To consider a report in respect of the disposals and acquisition of interests in land belonging to the Council and the redevelopment of land belonging to the Council.Agreed

More from Gravesham Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Refuse Vehicle ProcurementTo procure three refuse collection vehicles (one new vehicle and two new chassis with replacement body vehicles) to s... Refused Open
28 Sep 2026 Change to Order of BusinessIt was agreed that the order of business, during the meeting, be amended accordingly. Agreed Open
28 Sep 2026 Cygnet Leisure Centre - Wet Side ImprovementsDecision, outlining the intention to part fund the refurbishment, was published on 14 July 2026 GCLL had provided a p... Noted Open
28 Sep 2026 Gravesham Borough Council's response to 'The Shift'· The Council will work with the Shift Committee & young people to explore, design & develop an interim community spa... Decided Open
28 Sep 2026 LGA Corporate Peer Challenge - Progress Review Follow-up· That the content of the LGA Corporate Peer Challenge Progress Review report be noted · That the process for publish... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies