Procurement of Build Contract for 46 new homes at St Columba's Close

Agreed Executive

Cabinet agreed this item on Monday 20 March 2023. Below is the council's own wording, with the papers it was decided on.

Item85

Resolved

that: 1. Director (Housing) in consultation with the S.151 Officer and Lead Member be given delegated authority to conduct the procurement process and award a contract for the building of 46 new homes at St Columba’s Close/St Patrick’s Gardens using a procurement framework by way of mini tender or direct award as outlined in the report; and 2. Director (Housing) in consultation with the S.151 Officer and Lead Member be given delegated authority to negotiate and agree on amendments both contractually and budgetary if required as long as the returned tender price and any subsequent amendments, relative to anticipated rental income, continues to demonstrate the scheme can repay the associated borrowing within a period of not more than 30 years.
Word for word from the decision Gravesham published for this meeting. Source: democracy.gravesham.gov.uk

Follow this further

Built from Gravesham's papers

Papers for this item

Kept in our archive, download once signed in

No papers were published with this item. The decision above is the council's full record of it.

At this meeting

Whole meeting

On this subject at Gravesham

Search all
  1. Procurement of Build Contract for 46 new homes at St Columba's CloseThis decision
  2. Procurement of Build Contract for 8 new homes at Worcester Close, Istead RiseAgreed
  3. Procurement of DSO Building Management ContractsDecided

More from Gravesham Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Refuse Vehicle ProcurementTo procure three refuse collection vehicles (one new vehicle and two new chassis with replacement body vehicles) to s... Refused Open
28 Sep 2026 Change to Order of BusinessIt was agreed that the order of business, during the meeting, be amended accordingly. Agreed Open
28 Sep 2026 Cygnet Leisure Centre - Wet Side ImprovementsDecision, outlining the intention to part fund the refurbishment, was published on 14 July 2026 GCLL had provided a p... Noted Open
28 Sep 2026 Gravesham Borough Council's response to 'The Shift'· The Council will work with the Shift Committee & young people to explore, design & develop an interim community spa... Decided Open
28 Sep 2026 LGA Corporate Peer Challenge - Progress Review Follow-up· That the content of the LGA Corporate Peer Challenge Progress Review report be noted · That the process for publish... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies