Proposal: Battery Energy Storage System (BESS) to be located at Thames Way, Northfleet

Agreed Executive 3 papers

Cabinet agreed this item on Monday 24 February 2025. Below is the council's own wording, with the papers it was decided on.

Item93

Resolved

Cabinet support the Council entering into a two-year option and subsequent 37-year lease with Speedgreen for 1.25ha of land at Thames Road, Northfleet, upon the terms negotiated. Cabinet grant delegated authority to the Director (Communities & Inclusive Growth) in consultation with the Leader, the Director (Corporate Services) (in the role of S151 officer) and the Deputy Monitoring Officer teams to take all necessary practical, financial and legal actions required, including entering into the relevant formal legal agreements required
Word for word from the decision Gravesham published for this meeting. Source: democracy.gravesham.gov.uk

Follow this further

Built from Gravesham's papers

What the report saysPro

Report to Cabinet

Background

Battery Energy Storage Systems (BESS)

1.1In October 2021, the UK Government committed within its Net Zero Strategy to fully decarbonise the UK’s power system by 2035, a critical component to achieving the overall statutory target of making the UK carbon net zero by 2050 and tackling global warming/climate change.

1.2BESS are vital components in the UK electricity grid to facilitate this decarbonisation. BESS enable the electricity transmission network to be resilient and stable as it transitions from being heavily dependent on centralised fossil fuel power stations to large scale renewable energy sources, matching intermittent weather dependent wind and solar energy generation with continuously fluctuating consumer demand.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
BESS Cabinet Report: Appendix AAppendix 297 KB Download
PDF
BESS Cabinet Report- Appendix BAppendix 367 KB Download
PDF
Proposal: Battery Energy Storage System (BESS) to be located at Thames Way, NorthfleetReport 288 KB DownloadRead as text

At this meeting

Whole meeting

More from Gravesham Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Refuse Vehicle ProcurementTo procure three refuse collection vehicles (one new vehicle and two new chassis with replacement body vehicles) to s... Refused Open
28 Sep 2026 Change to Order of BusinessIt was agreed that the order of business, during the meeting, be amended accordingly. Agreed Open
28 Sep 2026 Cygnet Leisure Centre - Wet Side ImprovementsDecision, outlining the intention to part fund the refurbishment, was published on 14 July 2026 GCLL had provided a p... Noted Open
28 Sep 2026 Gravesham Borough Council's response to 'The Shift'· The Council will work with the Shift Committee & young people to explore, design & develop an interim community spa... Decided Open
28 Sep 2026 LGA Corporate Peer Challenge - Progress Review Follow-up· That the content of the LGA Corporate Peer Challenge Progress Review report be noted · That the process for publish... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies