GMCA Capital Programme 2019/20 - 2022/23 (Key Decision)

Approved Committee 1 paper

Greater Manchester Combined Authority approved this item on Friday 14 February 2020. Below is the council's own wording, with the papers it was decided on.

Item5F

Resolved

That the revisions to the 2019/20 capital forecast, as set out in Appendix A and detailed within the report, be approved. 2. That the capital programme budget for 2020/21 and the forward commitments, as detailed in the report and in Appendix A, be approved. 3. That it be noted that the capital programme was financed from a mixture of grants, external contributions and long term borrowings. 4. That it be noted that provision has been made in the revenue budget for the associated financing costs of borrowing. 5. That expenditure of £0.80 million for the Albert Street, Hollinwood (Oldham) Growth Deal 2 Minor Works scheme, as set out in section 7 of the report and Appendix B, be approved. 6. That it be notedthat the capital programme would continue to be reviewed, with any new schemes which have not yet received specific approval but were included within the programme would be the subject of future reports.
Word for word from the decision Greater Manchester Combined Authority published for this meeting. Source: democracy.greatermanchester-ca.gov.uk

Follow this further

Built from Greater Manchester Combined Authority's papers

What the report saysPro

Report to Greater Manchester Combined Authority

Purpose of report

To present an update in relation to the Greater Manchester Combined Authority capital expenditure programme for Transport and Economic Development and Regeneration functions.

Recommendations

The GMCA is requested to:

1. Approve the revisions to the 2019/20 capital forecast as set out in Appendix A and detailed within the report; 2. Approve the capital programme budget for 2020/21 and the forward commitments as detailed in the report and in Appendix A; 3. Note that the capital programme is financed from a mixture of grants, external contributions and long term borrowings; 4. Note that provision has been made in the revenue budget for the associated financing costs of borrowing; 5. Approve expenditure of £0.80 million for the Albert Street, Hollinwood (Oldham) Growth Deal 2 Minor Works scheme, as set out in section 7 and Appendix B; and 6. Note that the capital programme will continue to be reviewed, with any new schemes which have not yet received specific approval but are included within the programme to be the subject of future reports; CONTACT OFFICERS:

Name: Steve Wilson, Treasurer to GMCA Telephone: 0161 778 7004 E-Mail: [email protected]

Name: Steve Warrener Position: Finance and Corporate Services Director, TfGM Telephone: 0161 244 1025 E-mail: [email protected]

Name: Amanda Fox, Group Finance Lead (AGMA/GMCA) Telephone: 0161 778 7004 E-Mail: [email protected]

Equalities Implications: N/A

Climate Change Impact Assessment and Mitigation Measures: N/A

Risk Management – An assessment of major budget risks faced by the authority are carried out quarterly as part of the reporting process – at the present time a significant proportion of the capital budget is funded through grant. In order to mitigate the risk of monetary claw back the full programme is carefully monitored against the grant conditions and further action would be taken as necessary. Legal Considerations – There are no specific legal implications contained within the report. Financial Consequences – Revenue – There are no specific revenue considerations contained within the report, however, the revenue budget contains resources to meet the capital costs of the authority. Changes in the capital programme can affect the budget to meet these costs. Financial Consequences – Capital – The report sets out the forecast expenditure for 2019/20 and future years.

Number of attachments to the report: 0

Comments/recommendations from Overview & Scrutiny Committee

Background papers

Report to Greater Manchester Combined Authority: ‘Capital Update 2019/20’ 25 October 2019. Report to Greater Manchester Combined Authority: ‘Capital Update 2019/20’ 26 July 2019. Report to Greater Manchester Combined Authority: ‘Capital Programme 2018/19 – 2021/22’ 15 February 2019. TRACKING/PROCESS Does this report relate to a major strategic decision, as set out in the Yes GMCA Constitution

EXEMPTION FROM CALL IN Are there any aspects in this report which means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency? GM Transport Committee Overview & Scrutiny Committee 11 February 2020 1. INTRODUCTION/BACKGROUND

1.1The Greater Manchester Combined Authority (GMCA) approved the 2019/20 Capital Programme at its meeting on 15 February 2019. The latest 2019/20 Capital reforecast was reported to and noted by the GMCA at its meeting on 25 October 2019.

1.2GMCA’s capital programme includes Economic Development and Regeneration programmes, Waste and the continuation of the programme of activity currently being delivered by Transport for Greater Manchester (“TfGM”) and Local Authorities including the following elements:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
GMCA Capital Programme 2019/20: 2022/23 (Key Decision)Decisions 640 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 15 attended
SF
Stefaine FrazerCouncil Staff, expected
GM
GM Mayor Andy BurnhamChair, expected
DG
Councillor David GreenhalghCommittee Member, expected
NK
Nick KershawCouncil Staff, expected
JW
John WrathmellCouncil Staff, expected
DJ
Councillor David JonesCommittee Member, expected
BW
Councillor Brenda WarringtonVice-Chair, expected
RL
Councillor Richard LeeseVice-Chair, expected
SF
Councillor Sean FieldingCommittee Member, expected
AB
Councillor Allen BrettCommittee Member, expected
CM
City Mayor Paul DennettCommittee Member, expected
AW
Councillor Andrew WesternCommittee Member, expected

All 15 on the meeting page

On this subject at Greater Manchester Combined Authority

Search all
  1. GMCA Capital Programme 2019/20 - 2022/23 (Key Decision)This decision
  2. 2026/27 GMCA Capital StrategyApproved
  3. GMCA Revenue and Capital Budgets 2026/27 OverviewNoted
  4. GMCA Capital Programme 2025/26 - 2028/29Noted
  5. GMCA Capital Outturn 2024/25Noted
  6. 2025/26 GMCA Capital StrategyApproved

More from Greater Manchester Combined Authority Greater Manchester Combined Authority

All decisions
MeetingDecisionOutcome
25 Sep 2026 ApologiesThat apologies be received from Councillor Eleanor Wills (Tameside), with Councillor Andrew Mclaren attending as subs... Decided Open
25 Sep 2026 Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities... Decided Open
25 Sep 2026 Declarations of InterestThat it be noted that no declarations of interest were received. Noted Open
25 Sep 2026 GMCA Minutes - 10 July 2026That the minutes of the GMCA meeting held on 10 July 2026 be approved. Approved Open
25 Sep 2026 Bee Network Committee - 25 June 2026That the proceedings of the Bee Network Committee held on 25 June 2026 be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies