BUDGET AND LEVY 2021/22 AND MEDIUM-TERM FINANCIAL PLAN TO 2024/25
NotedCommittee1 paper
Greater Manchester Waste & Recycling Committee noted this item on Wednesday 23 March 2022. Below is the council's own wording, with the papers it was decided on.
RESOLVED /- 1. To note the forecast outturn for 2021/22. 2. To note the proposed 2023/24 trade waste rate of £118.30 to allow forward planning by districts. 3. To note the capital programme for 2022/23 as set out in Appendix A. 4. To note the budget and levy for 2022/23 of £164.8m (1.5% increase). 5. To note the risk position set out in the balances strategy and reserves.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
Report to Greater Manchester Waste & Recycling Committee
Purpose of report
The purpose of the report is to seek comment on the budget and levy for 2021/22 and on the Medium-Term Financial Plan (MTFP) to 2024/25. Those plans are delivered by:
1. A total levy requirement for 2022/23 of £164.8m, which represents a 1.5% average increase over 2021/22. At a District level the levy changes range from -2.2% to 4.3%; and
2. The MTFP then proposes levy charges of £170.5m in 2023/24 and £174.7m in 2024/25.
Recommendations: Members of the Committee are recommended to:
1. Note the forecast outturn for 2021/22; 2. Note the proposed 2023/24 Trade Waste rate of £118.30 to allow forward planning by Districts; 3. Note the capital programme for 2022/23 as set out in Appendix A; 4. Note the budget and levy for 2022/23 of £164.8m (1.5% increase); and 5. Note the risk position set out in the Balances Strategy and Reserves. Contact Officers
Lindsey Keech, Head of Finance – Capital and Treasury Management [email protected]
Report authors must identify which paragraph relating to the following issues: Equalities Impact, Carbon and Sustainability Assessment: Equalities Impact, Carbon and Sustainability Assessment: Results of the Sustainability Decision Support Tool to be included here:
A training video is available on how to use the tool.
Risk management
Under Section 25 of the Local Government Act 2003, the Authority’s Chief Financial Officer (the Treasurer) is required to report on the robustness of the estimates made for the purposes of the budget and levy calculations and the adequacy of the proposed reserves. This information enables a longer-term view of the overall financial position to be taken.
In accordance with these requirements a review has been undertaken of the risks that the GMCA may face from Waste & Resources activities which would require the allocation of resources over and above those already included in the MTFP budgets. That review broadly supports the proposed Revenue and Balances Strategy.
This report sets out the proposed Revenue budget for waste disposal in 2022/23.
Financial Consequences – Capital
This report sets out the proposed capital budget for waste disposal in 2022/23.
Number of attachments to the report: 2
1 - Appendix A - Capital Programme
2 - Appendix B – Forecast Levy Increases per District
Comments/recommendations from Overview & Scrutiny Committee
N/A
Background Papers N/A
Tracking/ Process Does this report relate to a major strategic decision, as set out in the GMCA Constitution
No
Exemption from call in Are there any aspects in this report which means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency? N/A
GM Transport Committee
N/A
Overview and Scrutiny Committee
N/A 1. Introduction/Background 1.1 The base budget for 2022/23 has been compiled and updated based upon:
a) District final tonnage information, as supplied in their November 2021 submissions; and b) Actual inflation (as measured using the CPI September 2021 index) for the Waste and Resource Management Services (WRMS) and Household Waste Recycling Centre Management Services Contracts (HWRCMS).
1.2This report is structured to cover the following matters: a) Expected Outturn 2021/22; b) Original Estimate 2022/23; c) MTFP for two further years to 2024/25; d) Balances and Reserves Strategy; e) Budget Engagement; and f) Risk Assessment.
2. Expected Outturn 2021/22
2.1The budget for 2021/22 was set by the GMCA at £162.402m in February 2021. The forecast outturn for 2021/22 is shown below.
Budget Forecast Variance
2021/22 2021/22 2021/22
£m £m £m
Operational Costs 105.023 94.342 (10.681)
Operational Financing 48.830 47.446 (1.384)
Office Costs 6.190 4.351 (1.839)
Non-Operational Financing 2.629 2.640 0.011 Total Budget 162.672 148.779 (13.893)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Greater Manchester Waste & Recycling Committee at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Chairs Announcements and Urgent BusinessThat the Committee notes the sad loss of Councillor David Lancaster MBE and acknowledges the significant contribution...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.