Resolved
RESOLVED /- 1. To n ote the implementation of the asset management plan and key engineering projects update and presentation.
Greater Manchester Waste & Recycling Committee decided this item on Wednesday 23 March 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED /- 1. To n ote the implementation of the asset management plan and key engineering projects update and presentation.
Performance of the contracts and associated risks are captured in the GMCA corporate risk register.
Legal Considerations
Activities set out in this report are in accordance with the terms of the WRMS and HWRCMS contracts.
Financial Consequences – Revenue
Activities set out in this report are in accordance with the Waste revenue budget.
Financial Consequences – Capital
Activities set out in this report are in accordance with the Waste capital budget.
Number of attachments to the report:
Appendix A - Asset Management Plan – Action List Update Q3 2021
Comments/recommendations from Overview & Scrutiny Committee
N/A
Background Papers N/A Tracking/ Process Does this report relate to a major strategic decision, as set out in the GMCA Constitution
No
Exemption from call in Are there any aspects in this report which means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency? N/A
GM Transport Committee
N/A 1. Introduction
This report provides Members with updates relating to the Waste and Resources team asset portfolio. Updates are provided for key projects focusing on progress at quarter 3 in 2021. Assets within Waste and Resources are managed by the Engineering team and fall into the following categories:
(A) - Operational Waste Facilities WRMS Contract Facilities - Lot1 28 waste processing and reception facilities across 11 locations. WRMS Contract – Lot 2 11 Household Waste Recycling Centres (B) - Buildings and Land Includes vacant land and building premises at 8 locations (C) - Closed Landfill Sites 4 Closed landfill sites managed by GMCA 18 Closed landfill sites managed by POS Landcare
2. 2021-22 Quarter (3) Update
The following information provides individual updates against selected projects across the Waste and Resources Asset categories.
2.1Category (A) Updates – Operational Waste Facilities
1 Reliance Street Mechanical Treatment and Reception Facility
Update - Q3 2021
The new MTR facility at Reliance Street is now fully operational following successful commissioning of the main plant and equipment. The plant is running at higher-than- expected daily tonnages providing essential capacity while our Longley Lane MTR is offline and undergoing refurbishment. The odour control system (OCS) is currently undergoing further testing against the contractual test criteria. This is an ongoing snagging defect which is being reviewed by the technology provider and main contractor. GMCA and Suez are in dialogue on this matter and provisional options are being reviewed. Suez are continuing to monitor the situation and operate the plant and rectification measures for the OCS will be reviewed and actioned in the coming months.
2 Chichester Street Transfer Loading Station - Floor Replacement Background
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
ASSET MANAGEMENT PLAN UPDATEReport | 554 KB | DownloadRead as text |
PDF |
Asset Management Plan Action ListAppendix A | 35 KB | Download |
Follow Greater Manchester Waste & Recycling Committee at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Mar 2026 | ApologiesTo note the apologies for absence received from Councillor Sue Maitland (Trafford) Subs: Gina Reynolds (Salford) Apol... | Noted | Open |
| 11 Mar 2026 | Chairs Announcements and Urgent BusinessThat the Committee notes the sad loss of Councillor David Lancaster MBE and acknowledges the significant contribution... | Decided | Open |
| 11 Mar 2026 | Declarations of InterestThere were no declarations of interest reported. | Decided | Open |
| 11 Mar 2026 | Greater Manchester Waste & Recycling Committee Minutes 21 January 2026That the minutes of the meeting held on 21 January 2026 be approved as a correct record. | Approved | Open |
| 11 Mar 2026 | Contracts UpdateThat the performance of the Waste and Resource Management contracts be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.