That the report and the publication of the ‘ – report on early results, June 2025’ be noted. 2. That it be noted that the National Audit Report will be shared with members of the GMCA. 3. That officers be requested to submit a further update to the GMCA in due course. 4. That endorsement of the network review schedule by the Bee Network Committee be noted. 5. That the GMCA record its thanks to Bee Network officers for the route changes that have been made to date to improve the network.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
Greater Manchester Combined Authority Date: Friday 27th June 2025
Subject: Delivering Better Bus Services for Greater Manchester
Report of: Andy Burnham, Mayor of Greater Manchester, Portfolio Lead for Transport
and Caroline Simpson, Group Chief Executive, GMCA
Purpose of Report This report provides a summary of what Greater Manchester set out to achieve for our bus services through the process of bus reform, activities delivered so far in relation to bus franchising and related bus investments, achievements to date, and some of our ambitions for the future.
Recommendations: The GMCA is requested to:
1. Note the contents of this report and the publication of the attached report.
Contact Officers Martin Lax Transport Strategy Director, TfGM [email removed]
Nick Fairclough Acting Head of Policy, Insight & Public Affairs, TfGM [email removed] Equalities Impact, Carbon and Sustainability Assessment: Not applicable
Risk Management Not applicable
Legal Considerations Not applicable
Financial Consequences – Revenue Not applicable
Financial Consequences – Capital Not applicable
Number of attachments to the report: 1 – “Delivering Better Bus Services for Greater Manchester – report on early results, June 2025”
Comments/recommendations from Overview & Scrutiny Committee Not applicable
Background Papers Not applicable.
Tracking/ Process Does this report relate to a major strategic decision, as set out in the GMCA Constitution ?
No
Exemption from call in
Are there any aspects in this report which means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency?
No
Bee Network Committee
BNC will consider the report at the meeting of 26 June 2025.
Overview and Scrutiny Committee
Not applicable 1. Background
1.1To help deliver Greater Manchester’s vision for a fully integrated transport network, ‘the Bee Network’, the formal decision to take forward bus franchising in Greater Manchester was taken in March 2021. The transition to a publicly controlled bus network was completed in three tranches, on 23 September 2023, 24 March 2024 and 5 January 2025.
1.2Franchising provides a framework for improving the bus network in the city region and the opportunity to improve bus services and reverse the long-term decline in bus use in Greater Manchester.
1.3The report attached sets out the early achievements of the journey to improve the bus network, and our ambitions for the future network. Implementation of bus franchising is only the beginning of transforming our bus network for the people and businesses of Greater Manchester.
2. Delivering Better Bus Services for Greater Manchester - Report on Early Results
2.1The attached report provides an early picture of the positive progress to date in improving the bus network in Greater Manchester, structured around developments in customer experience, service delivery, overall bus usage and financial sustainability.
2.2Changes made to improve the experience against each of our Customer Commitments, service delivery, and early bus use outcomes are highlighted. Without the changes we have made, our bus network would be smaller, less attractive and more expensive to run and use.
2.3After a strong start, we are at the beginning of our journey towards the bus network we want to build. The report also sets out our longer-term ambitions for the bus network, as well as the wider Bee Network as a whole, including local rail integration.
2.4Long-term monitoring of progress in improving the bus network is planned, with results in terms of outcomes, particularly in relation to bus use, to be reported on in future years.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Greater Manchester Combined Authority at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.