That it be noted that the Mayoral General Budget provisional revenue o utturn position for 2024/25 was breakeven after planned transfer to earmarked reserves. 2. That it be noted that the GMCA General Budget provisional revenue outturn position for 2024/25 was breakeven after planned transfer to earmarked reserves. 3. That it be noted that the Mayoral General – GM Fire & Rescue provisional revenue outturn position for 2024/25 was breakeven after a transfer of revenue funding to capital. 4. That it be noted that the Waste and Resourcing provisional revenue outturn position for 2024/25 was breakeven after a transfer from reserve of £18.7m. 5. That it be noted that the GMCA Transport and TfGM provisional revenue o utturn positions for 2024/25 were breakeven after transfers between earmarked reserves. 6. That it be noted that the final position was subject to the submission of the audited accounts to be reported to the GMCA Audit Committee.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
Report of: Councillor David Molyneux, Portfolio Lead for Resources and Steve Wilson, GMCA Group Chief Finance Officer
Purpose of Report This report is to inform members of the Greater Manchester Combined Authority of the revenue outturn for 2024/2025.
Recommendations: The GMCA is requested to:
1. The Mayoral General Budget provisional revenue outturn position for 2024/25 is breakeven after planned transfer to earmarked reserves. 2. The GMCA General Budget provisional revenue outturn position for 2024/25 is breakeven after planned transfer to earmarked reserves. 3. The Mayoral General – GM Fire & Rescue provisional revenue outturn position for 2024/25 is breakeven after a transfer of revenue funding to capital. 4. The Waste and Resourcing provisional revenue outturn position for 2024/25 is breakeven after a transfer from reserve of £18.7m. 5. The GMCA Transport and TfGM provisional revenue outturn positions for 2024/25 are breakeven after transfers between earmarked reserves. 6. The final position is subject to the submission of the audited accounts to be reported to the GMCA Audit Committee.
Contact Officers Name: Steve Wilson, Group Chief Finance Officer, GMCA
Name: Matt Bull, Director of Finance, Commercial and Corporate Services, Transport for Greater Manchester Telephone: [phone removed]
E-mail: [email removed]
Equalities Impact, Carbon and Sustainability Assessment There are no specific equalities impact, carbon and sustainability issues contained within this report.
Risk Management An assessment of major budget risks faced by the authority are carried out quarterly as part of the reporting process – at the present time a significant proportion of the capital budget is funded through grant. In order to mitigate the risk of monetary claw back the full programme is carefully monitored against the grant conditions and further action would be taken as necessary.
Legal Considerations There are no specific legal implications contained within the report.
Financial Consequences – Revenue There are no specific revenue considerations contained within the report.
Financial Consequences – Capital The report details the actual capital expenditure for 2024/25.
Number of attachments to the report: None
Background Papers GMCA Budget Reports – 9th February 2024 GMCA Revenue Update Quarter 1 - 2023/24 – 27th September 2024 GMCA Revenue Update Quarter 2 – 2023/24 – 29th November 2024 GMCA Revenue and Capital Budget Reports – 7th February 2025 GMCA Revenue Update Quarter 3 – 2024/25 – 28th March 2025
Tracking/ Process Does this report relate to a major strategic decision, as set out in the GMCA Constitution ?
No Exemption from call in
Are there any aspects in this report which means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency?
No
Bee Network Committee
N/A
Overview and Scrutiny Committee
N/A 1. Introduction/Background 1.13 The purpose of this report is to provide the 2024/25 provisional revenue outturn position in relation to the GMCA General, Mayoral, GM Fire and Rescue, Waste and Resources and Transport, including Transport for Greater Manchester (TfGM). 1.14 It should be noted that this report is a draft of the expected outcome of the 2024/25 financial position, ahead of the audit of the Statement of Accounts, however it is not anticipated that there will be any significant changes. The statutory deadline for submission of audited accounts is 30th of June 2025. 1.15 The table below shows the summary of the provisional outturn position for budgets in this report.
Summary 2024/25 Approved Budget Provisional Outturn Variance from Budget Provisional Outturn Exp Income Total Exp Income Total Exp Income Total
Follow Greater Manchester Combined Authority at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.