Bee Network Committee, Thursday 29 January 2026 at 2.00pm

Transport Infrastructure Pipeline

Noted Committee 1 paper

AI summaryGreater Manchester's Bee Network Committee approves £2m for Rail Integration phase 1 and £0.375m for early studies into a possible tunnelled metro.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedTwo Integrated Settlement (CRSTS) drawdowns approved
Money£2m and £0.375mSeparate drawdowns for Rail Integration and Tunnelled Metro
What happens nextPhase 1 Rail Integration worksCustomer elements to be delivered for December 2026 launch
Who it affectsGreater Manchester transport networkRail commuters, Metrolink users and wider travelling public

What was decided

The Committee approved a £2m drawdown of Integrated Settlement (CRSTS) funding to complete phase 1 customer elements of the Bee Network Rail Integration programme, due to launch in December 2026. Report 2.1, 2.2, 2.3

The Committee approved a £0.375m drawdown from the Rapid Transit Extensions Package for early feasibility and demand studies to inform a Strategic Outline Case for a tunnelled metro. Report 2.4, 2.7

The Committee noted the current position, recent progress and key milestones on the transport infrastructure pipeline, including that around £1.08bn of the £1.27bn allocated has been released to date. Report 1.3

Why

A previous £15.5m drawdown was approved in March 2025; the further £2m is needed to complete phase 1 customer elements such as website and app rail station information, digital information, announcements and station branding. Report 2.1, 2.2, 2.3

The Greater Manchester Rapid Transit Strategy, noted by the Committee in July 2024, includes an action to explore tunnelled options to avoid surface transport infrastructure becoming a constraint on growth. Three main axes have been identified for further investigation. Report 2.4, 2.5, 2.6, P36, P37, P38

Programme risk of not fully expending Government funding will be mitigated by progressing the pipeline of works. Report P15

What happens next

A detailed Delivery Plan for the £2.47bn Transport for City Regions allocation (April 2027 to March 2032) is being developed alongside the new Local Transport Plan, with consultation running from 09 December until 09 March 2026. Report 1.4

TfGM will continue to progress the three phases of Bee Network Rail Integration, aligned to the rollout of pay-as-you-go on eight commuter lines by the end of 2028. Report 2.1

Early feasibility and demand study work on the tunnelled metro will be used to inform a subsequent Strategic Outline Case. Report 2.7

The money

  • £2m Integrated Settlement (CRSTS) drawdown for Bee Network Rail Integration phase 1 customer elements Report 2.3
  • £0.375m Rapid Transit Extensions Package drawdown for early feasibility and demand studies on a tunnelled metro Report 2.7
  • £15.5m Previous Bee Network Rail Integration drawdown approved in March 2025 Report 2.2
  • £34m Overall allocation for Rail Integration and Accessibility activity approved by the Combined Authority in January 2025 Report 2.2
  • £1.08bn Amount of the £1.27bn transport infrastructure pipeline allocation released to date Report 1.3
  • £2.47bn Transport for City Regions funding allocation for April 2027 to March 2032 confirmed in the June 2025 Spending Review Report 1.4

Options considered

  • Chosen: Approve £2m drawdown for Bee Network Rail Integration phase 1. Needed to complete phase 1 works ahead of the December 2026 launch, within the £34m overall allocation. Report 2.2, 2.3
  • Chosen: Approve £0.375m drawdown for tunnelled metro feasibility work. Will fund early feasibility and demand studies to inform a subsequent Strategic Outline Case. Report 2.5, 2.7
  • Rejected: Reject the drawdown requests

Implications

  • Financial: Drawdowns fall within existing Integrated Settlement (CRSTS) allocations; legal and funding agreements will be produced and implemented using template agreements with GMCA. Report P16
  • Risk: Approving the recommendations mitigates the programme risk of not fully expending the funding awarded by Government. Report P15
  • Equalities: Impacts questionnaire records positive Equality and Inclusion, Resilience and Adaptation, and Mobility and Connectivity ratings. Report P9
  • Climate: Carbon Assessment overall score 0.857143, with positive transport and active travel impacts; supports the GM Carbon Neutral 2038 target. Report P12, P13, P10
  • Other: Tunnelled metro work could roughly double Metrolink network capacity by enabling a relief tunnel on the South-West to North-East axis. Report P36

Who and where

  • Rail passengers on Greater Manchester's commuter lines Report 2.1, 2.3
  • Metrolink and future rapid transit users in Greater Manchester Report P36, P37, P38
  • Residents and businesses along the three identified rapid transit axes (South-West to North-East, North-West to South-East, North-South) Report P36, P37, P38
  • TfGM and the Greater Manchester Combined Authority as delivery bodies Report P3, P16

Timeline

  • January 2025: Combined Authority approved £34m overall allocation for Rail Integration and Accessibility activity Report 2.2
  • March 2025: Previous £15.5m Bee Network Rail Integration drawdown approved by Bee Network Committee Report 2.2
  • 29th January 2026: Bee Network Committee considered and approved the drawdown requests in this report Report P1
  • 09 March 2026: Close of consultation on the Delivery Plan and new Local Transport Plan Report 1.4
  • December 2026: Planned launch of phase 1 of the Bee Network Rail Integration programme Report 2.1, 2.2
  • 2027: Phase 2 of Bee Network Rail Integration due to be completed Report 2.1
  • 2028: Phase 3 of Bee Network Rail Integration due to be completed; pay-as-you-go rollout on eight commuter lines complete Report 2.1
  • April 2027 to March 2032: Period covered by the £2.47bn Transport for City Regions funding allocation Report 1.4

Plain English for the jargon

  • Bee Network: Greater Manchester's planned high-quality, affordable and fully integrated public transport and active travel system.
  • CRSTS: City Region Sustainable Transport Settlement, the Government funding stream being drawn down through the Integrated Settlement.
  • Integrated Settlement: Greater Manchester's single funding pot combining several Government transport funding streams, including CRSTS.
  • PAYG: Pay-as-you-go ticketing, being rolled out across the eight commuter rail lines being integrated into the Bee Network by the end of 2028.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

T hat the current position, recent progress and key milestones on the transport infrastructure pipeline be noted; and 2. That approval be given to the drawdown of Integrated Settlement (CRSTS) and associated scheme progression as follows: · Bee Network Rail Integration: £2m; and · Rapid Transit Extensions Package: GM Tunnelled Metro: £0.375m.
Word for word from the decision Greater Manchester Combined Authority published for this meeting. Source: democracy.greatermanchester-ca.gov.uk

Follow this further

Built from Greater Manchester Combined Authority's papers

What the report saysPro

Report to Bee Network Committee

Bee Network Committee Date: Thursday 29th January 2026

Subject: Transport Infrastructure Pipeline

Report of: Chris Barnes, Network Director, TfGM

Purpose of Report This report provides an update on progress delivering a pipeline of transport infrastructure improvements to support the Bee Network: a high -quality, affordable and fully integrated public transport and active travel system which can support sustainable economic growth and the wider GM Integrated Pipeline. The report makes a number of recommendations for members to support the continued development and delivery of the pipeline programme.

Recommendations: The Committee are requested to:

1. Note the current position, recent progress and key milestones on the transport infrastructure pipeline; and 2. Approve the drawdown of Integrated Settlement (CRSTS) and associated scheme progression as follows: • Bee Network Rail Integration: £2m; and • Rapid Transit Extensions Package: GM Tunnelled Metro: £0.375m.

Contact Officers Chris Barnes Network Director, Infrastructure, TfGM [email removed]

Richard Nickson Network Director, Active Travel, TfGM [email removed] Equalities Impact, Carbon and Sustainability Assessment: Recommendation - Key points for decision-makers Insert text

Impacts Questionnaire Impact Indicator Result Justification/Mitigation Equality and Inclusion G Health G Resilience and G Adaptation Housing Economy Mobility and G Connectivity Carbon, Nature and G Environment Consumption and Production

Contribution to achieving the GM Carbon Neutral 2038 target

Further Assessment(s): Equalities Impact Assessment and Carbon Assessment Positive impacts overall, Mix of positive and Mostly negative, with at G whether long or short A negative impacts. Trade- R least one positive aspect. RR Negative impacts overall. term. offs to consider. Trade-offs to consider.

Carbon Assessment Overall Score 0.857143

Buildings Result Justification/Mitigation New Build residential N/A Residential building(s) N/A renovation/maintenance New build non- residential (including N/A public) buildings Transport Active travel and public 1 transport Roads, Parking and N/A Vehicle Access Access to amenities 1 Vehicle procurement N/A Land Use Land use 0.5

High standard in Mostly best practice Partially meets best Not best practice No associated terms of practice with a good level of practice/ awareness, and/ or insufficient carbon impacts and awareness on awareness on significant room to awareness of carbon expected. carbon. carbon. improve. impacts.

Risk Management The recommendations of this report will enable the continued development and delivery of the Bee Network infrastructure pipeline and prioritised infrastructure expenditure. This will mitigate the programme risk of not fully expending the funding awarded by Government. A programme risk register is maintained and updated regularly by TfGM.

Legal Considerations There is a significant contract workstream supporting the delivery of the Capital Programme which is being supported and delivered by both internal and external legal teams. The Legal Delivery/Funding Agreements in respect of the allocation of MCF, Active Travel and CRSTS funding will be produced and implemented for full scheme and development costs approvals as appropriate using the template agreements agreed with GMCA. Financial Consequences – Revenue Referenced throughout the report.

Financial Consequences – Capital Referenced throughout the report.

Number of attachments to the report: 0

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Transport Infrastructure PipelineReport 322 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 18 attended
GM
GM Mayor Andy BurnhamChair, expected
EO
Councillor Eamonn O'BrienVice-Chair, expected
HK
Councillor Hamid KhurramCommittee Member, expected
AQ
Councillor Alan QuinnCommittee Member, expected
TR
Councillor Tracey RawlinsCommittee Member, expected
JC
Councillor Josh ChartersCommittee Member, expected
PB
Councillor Phil BurkeCommittee Member, expected
CM
City Mayor Paul DennettCommittee Member, expected
GB
Councillor Grace BaynhamCommittee Member, expected
SH
Councillor Stephen HomerCommittee Member, expected
AW
Councillor Aidan WilliamsCommittee Member, expected
PP
Councillor Paul PrescottCommittee Member, expected

All 18 on the meeting page

On this subject at Greater Manchester Combined Authority

Search all
  1. Transport Infrastructure PipelineThis decision
  2. Transport Infrastructure PipelineNoted
  3. Transport Infrastructure PipelineNoted
  4. Transport Infrastructure PipelineNoted
  5. Transport Infrastructure PipelineApproved
  6. Transport Infrastructure PipelineNoted

More from Greater Manchester Combined Authority Bee Network Committee

All decisions
MeetingDecisionOutcome
24 Sep 2026 ApologiesApologies were received and noted from Cllr Nazia Rehman (Wigan), City Mayor Paul Dennett (Salford), Cllr Stephen Hom... Noted Open
24 Sep 2026 Appointment UpdatesThat the update on the appointments made at the June meeting of the GMCA be noted. 2. That the appointments of the Ma... Noted Open
24 Sep 2026 Appointments to Outside BodiesThat the appointment of Cllr Barry Winstanley, Cllr Grace Baynham & Cllr Michael Welton to the Greater Manchester Acc... Noted Open
24 Sep 2026 Terms of Reference & Rules of ProcedureThat the terms of reference and rules of procedure be noted. Noted Open
24 Sep 2026 Declarations of InterestThere were none. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies