Transport Infrastructure Pipeline

Noted Committee 1 paper

AI summaryGreater Manchester Bee Network Committee approves transport infrastructure drawdowns totalling in the region of £30m, reallocates £5.3m Oldham underspend, and endorses £1.884m EV pavement channels grant.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNoted16 CRSTS schemes, Oldham reallocation, Bolton Active Travel
MoneyAround £30m drawdowns approvedPlus £1.884m EV pavement channels endorsed
What happens nextSchemes to progress to deliverySeveral FBCs to return to Committee in summer 2026
Who it affectsGreater Manchester Bee Network usersBus, tram, active travel and EV charging schemes

What was decided

Approved drawdown of Integrated Settlement (CRSTS) funding for 16 schemes covering bus pinch points, improving journeys corridors, integrated customer measures, travel hubs, Bury Interchange, Metrolink stop improvements, electric vehicle charging, Wythenshawe active travel and the A56 corridor in Trafford. Report P6

Noted reallocation of £5.3m CRSTS underspend from the withdrawn Oldham Beal Valley Broadbent Moss Greenway Corridor scheme and approved drawdown of a further £0.54m development funding for Park Road/Kings Road, Accessible Oldham Phase 2 (St Mary's Way), and Broadway Canal to Link. Report 3.1, 3.2

Approved drawdown of £2.2m of Active Travel funding and the Full Business Case for the Bolton Doffcocker to Bolton Town Centre Phase 1 scheme, and endorsed the local authority distribution of the £1.884m EV Pavement Channels grant. Report 4.6, 5.3

Why

The pipeline supports the Bee Network, a high quality, affordable and integrated public transport and active travel system, and the wider Greater Manchester Integrated Pipeline, contributing to the Greater Manchester Strategy pledges on a global city region, safe streets and a greener future. Report 1.1, 1.4, P25, P26, P27

Around £1.081bn of the £1.27bn transport infrastructure pipeline allocation has been released to date; further drawdowns mitigate the programme risk of not fully expending government funding. Report 1.3, P10

What happens next

Subject to approval, A56 Cross Street works at Sale West/Altrincham to start at Easter 2026 and complete by summer 2026; Ashton-Stockport package to start in spring 2026 and complete by end of 2026. Report 2.8, 2.12

Further updates and Full Business Case approvals to come to the Committee in summer 2026 for the Wigan-Leigh junctions, Beaumont Road Bolton junction and the Heywood (Bury-Rochdale) scheme. Report 2.16, 2.18

Bolton Doffcocker Phase 1 works to start on site in May 2026, with completion scheduled for early 2027; Phase 2 to Doffcocker received funding through the 2025 CRSTS Reprioritisation. Report 4.6, 4.8

The money

  • £2.75m Bus Pinch Points & Maintenance Report 2.3
  • £0.97m Sale West Altrincham Cross Street (with Full Business Case) Report 2.8
  • £1.9m Improving Journeys: Ashton-Stockport (with Full Business Case) Report 2.12
  • £0.44m Improving Journeys: Wigan-Bolton and Wigan-Leigh Report 2.16
  • £0.27m Improving Journeys: Bury-Rochdale Report 2.18
  • £0.3m Improving Journeys: A62 Oldham Road and A662 Ashton New Road Report 2.22
  • £1.5m Integrated Measures (Customer): Mobile App (with Full Business Case) Report 2.23
  • £0.75m Integrated Measures (Customer): Active Travel Integration Report 2.24
  • £0.85m Metrolink Customer Experience Improvements at Etihad Campus Report 2.25
  • £0.2m Hindley Travel Hub including Park & Ride Report 2.29
  • £7.47m Bury Interchange Report 2.33
  • £0.65m Metrolink Stop Improvements (Heaton Park Phase 1) Report 2.38
  • £0.703m Wigan Electric Vehicle Charging Infrastructure (with Full Business Case) Report 2.42
  • £0.544m Tameside Electric Vehicle Charging Infrastructure (with Full Business Case) Report 2.49
  • £1.55m Manchester Wythenshawe Active Travel Programme Report 2.52
  • £0.5m Trafford A56 Corridor Improvements (with Full Business Case) Report 2.56
  • £5.3m Reallocated from Oldham Beal Valley Broadbent Moss Greenway Corridor Report 3.1
  • £0.54m Development funding drawdown for Park Road/Kings Road, Accessible Oldham Phase 2, Broadway Canal to Link Report 3.2
  • £2.2m Active Travel funding for Bolton Doffcocker to Bolton Town Centre Phase 1 (with Full Business Case) Report 4.6
  • £1.884m EV Pavement Channels grant distribution to 10 GM local authorities (endorsed) Report 5.1, 5.3

Options considered

  • Chosen: Approve the CRSTS and Active Travel drawdowns and the Oldham reallocation as set out in the report. Schemes have demonstrated appropriate strategic case, value for money and deliverability through the local assurance framework. Report 2.8, 2.12, 2.42, 2.49, 2.56, 4.5
  • Rejected: Note the report rather than approve

Implications

  • Financial: Integrated Settlement (CRSTS), Active Travel and EV pavement channels grant funding is drawn down to keep the £1.27bn Bee Network capital programme on track; £1.081bn has already been released. Report 1.3, P10, P13
  • Legal: Legal Delivery and Funding Agreements will be produced for full scheme and development cost approvals using the template agreements agreed with GMCA, supported by internal and external legal teams. Report P11
  • Equalities: Equality and Inclusion assessment rated G, with overall positive impacts and significant room to improve; a small number of positive aspects identified. Report P7, P8, P9
  • Climate: Carbon assessment of the report scored Overall 1, with a Transport Carbon, Nature and Environment rating of G; 78 new zero-emission buses to enter service between April and June 2026 with about 200 more in pipeline. Report P7, P8, P23
  • Risk: Programme risk register maintained by TfGM; the drawdowns mitigate the risk of not fully expending government funding. Report P10
  • Other: Greater Manchester received £2.47bn Transport for City Regions funding for April 2027 to March 2032 in the June 2025 Spending Review, to be part of GM's Integrated Settlement. Report 1.5

Who and where

  • Bus passengers across Greater Manchester, including 470 bus stop accessibility enhancements and bus lane enforcement cameras in Salford Report 2.3, P35, P36
  • Residents and road users in Trafford, particularly on the A56 corridor between Carrington Lane and Washway Road Report 2.53, 2.55, P105
  • Metrolink customers, including users of Heaton Park stop and Etihad Campus Report 2.25, 2.26, 2.34, 2.36
  • Bury town centre users through the Bury Interchange redevelopment (Phase 1 and Phase 2 with residential element) Report 2.31, 2.32, 2.33
  • Bolton residents in Heaton and Doffcocker through new active travel routes to the town centre and Queen's Park Report 4.1, 4.2
  • GM residents without off-street parking who could benefit from EV pavement channels, especially in terraced housing Report 5.2, P175, P181
  • Stockport bus passengers and staff during relocation to a temporary depot ahead of the new EV depot in 2029 Report 2.57, 2.60, 2.61

Timeline

  • Easter 2026: A56 Cross Street works (Sale West/Altrincham) to commence Report 2.8
  • Spring 2026: Ashton-Stockport highway improvement package to commence Report 2.12
  • May 2026: Bolton Doffcocker to Bolton Town Centre Phase 1 to start on site Report 4.6
  • Summer 2026: A56 Cross Street works to complete; A56 Cross Street and Bolton, Wigan-Leigh and Heywood (Bury-Rochdale) FBCs to come to Committee Report 2.8, 2.16, 2.18
  • End 2026: Ashton-Stockport works to complete; further zero-emission buses from Oldham and Hyde Road large franchises to enter service Report 2.12, P23
  • December 2026: Wigan EVCI contract to be in place Report 2.39
  • Early 2027: Bolton Doffcocker Phase 1 completion scheduled; Wythenshawe Active Travel FBCs planned Report 2.52, 4.6
  • Q1 2027: Stockport temporary bus depot to complete and hand over to TfGM and bus operator Report 2.61
  • March 2027: Tameside EVCI delivery aims; Trafford A56 Corridor to be delivered Report 2.46, 2.56
  • Mid-2027: Wigan EVCI delivery to start Report 2.39
  • Summer 2027: Bury Interchange Phase 2 Full Business Case planned Report 2.33
  • 2029: New fully electric Stockport bus depot intended to be ready for operation Report 2.57

Plain English for the jargon

  • Bee Network: Greater Manchester's planned high quality, affordable and fully integrated public transport and active travel system.
  • CRSTS: City Region Sustainable Transport Settlement, the main government capital funding stream for the transport infrastructure pipeline.
  • Integrated Settlement: Greater Manchester's consolidated capital funding arrangement that includes the CRSTS allocation.
  • FBC: Full Business Case, the final assurance stage required before full scheme funding approval.
  • SOBC: Strategic Outline Business Case, the initial business case stage for a scheme.
  • BPP&M: Bus Pinch Points and Maintenance programme of minor bus network interventions.
  • MStIP: Metrolink Stop Improvements Programme, covering accessibility, safety and customer experience at existing Metrolink stops.
  • SWANI: Sale West to Altrincham Network Improvements scheme.
  • EVCI: Electric Vehicle Charging Infrastructure.
  • LEVI: Local Electric Vehicles Infrastructure programme.
  • MCF: Mayors Challenge Funding, used in this report for the Mayors Cycling and Walking Challenge Fund.
  • TCF: Transforming Cities Fund.
  • TCR: Transport for City Regions, the post-2027 government funding stream replacing CRSTS.
  • GMS: Greater Manchester Strategy, the overarching policy framework for the city region.
  • AfA: Access for All, a rail station accessibility improvement programme.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

That the current position, recent progress and key milestones on the transport infrastructure pipeline be noted. 2. That the drawdown of Integrated Settlement (CRSTS) funding and associated scheme progression be approved as follows: · Bus Pinch Points & Maintenance: £2.75m; · Sale West Altrincham Cross Street: £0.97m and Full Business Case; · Improving Journeys: Ashton- Stockport: £1.9m and Full Business Case; · Improving Journeys: Wigan – Bolton and Wigan - Leigh: £0.44m; · Improving Journeys: Bury – Rochdale: £0.27m · Improving Journeys: A62 Oldham Road & A662 Ashton New Road: £0.3m; · Integrated Measures (Customer): Mobile App: £1.5m and Full Business Case; · Integrated Measures (Customer): Active Travel Integration: £0.75m; · Integrated Measures: Metrolink Customer Experience Improvements at Etihad Campus: £0.85m; · Hindley Travel Hub incl. Park & Ride: £0.2m; · Bury Interchange: £7.47m; · Metrolink Stop Improvements: £0.65m; · Wigan: Electric Vehicle Charging Infrastructure: £0.703m and Full Business Case; · Tameside: Electric Vehicle Charging Infrastructure: £0.544m and Full Business Case; · Manchester: Wythenshawe Active Travel Programme: £1.55m; and · Trafford: A56 Corridor Improvements: £0.5m and Full Business Case. 3. That it be noted that reallocation of £5.3m underspend from the Oldham Beal Valley Broadbent Moss – Greenway Corridor scheme and approve the drawdown of the previously approved development funding underspend of £0.54m to the following schemes, approved at the GMCA meeting held on 13 February: · Park Road / Kings Road; · Accessible Oldham - Phase 2 (St Mary's Way); and · Broadway Canal to Link. 4. That the drawdown of £2.2m of Active Travel funding and associated scheme progression to Full Business Case for Bolton: Doffcocker to Bolton Town Centre Phase 1 be approved; and 5. That the funding distribution for the £1.884m Electric Vehicle Pavement channels grant, to help drive uptake by supporting residents without off-street parking to charge at home and benefit from cheaper, domestic tariffs, as set out in Appendix 2 be endorsed.
Word for word from the decision Greater Manchester Combined Authority published for this meeting. Source: democracy.greatermanchester-ca.gov.uk

Follow this further

Built from Greater Manchester Combined Authority's papers

What the report saysPro

Report to Bee Network Committee

Bee Network Committee Date: Thursday 26th March 2026

Subject: Transport Infrastructure Pipeline

Report of: Chris Barnes, Interim Infrastructure Delivery Director, TfGM

Purpose of Report This report provides an update on progress delivering a pipeline of transport infrastructure improvements to support the Bee Network: a high -quality, affordable and fully integrated public transport and active travel system which can support sustainable economic growth and the wider GM Integrated Pipeline. The report makes a number of recommendations for members to support the continued development and delivery of the pipeline programme.

Recommendations: The Committee are requested to:

1. Note the current position, recent progress and key milestones on the transport infrastructure pipeline; and 2. Approve the drawdown of Integrated Settlement (CRSTS) funding and associated scheme progression as follows: • Bus Pinch Points & Maintenance: £2.75m; • Sale West Altrincham Cross Street: £0.97m and Full Business Case; • Improving Journeys: Ashton- Stockport: £1.9m and Full Business Case; • Improving Journeys: Wigan – Bolton and Wigan - Leigh: £0.44m; • Improving Journeys: Bury – Rochdale: £0.27m • Improving Journeys: A62 Oldham Road & A662 Ashton New Road: £0.3m; • Integrated Measures (Customer): Mobile App: £1.5m and Full Business Case; • Integrated Measures (Customer): Active Travel Integration : £0.75m; • Integrated Measures: Metrolink Customer Experience Improvements at Etihad Campus: £0.85m; • Hindley Travel Hub incl. Park & Ride: £0.2m; • Bury Interchange: £7.47m; • Metrolink Stop Improvements: £0.65m; • Wigan: Electric Vehicle Charging Infrastructure: £0.703m and Full Business Case; • Tameside: Electric Vehicle Charging Infrastructure: £0.544m and Full Business Case; • Manchester: Wythenshawe Active Travel Programme: £1.55m; and • Trafford: A56 Corridor Improvements: £0.5m and Full Business Case. 3. Note the reallocation of £5.3m underspend from the Oldham Beal Valley Broadbent Moss – Greenway Corridor scheme, and approve the drawdown of the previously approved development funding underspend of £0.54m to the following schemes, approved at the GMCA meeting held on 13 February; • Park Road / Kings Road; • Accessible Oldham - Phase 2 (St Mary's Way); and • Broadway Canal to Link. 4. Approve the drawdown of £2.2m of Active Travel funding and associated scheme progression to Full Business Case for Bolton: Doffcocker to Bolton Town Centre Phase 1; and 5. Endorse the funding distribution for the £1.884m Electric Vehicle Pavement channels grant, to help drive uptake by supporting residents without off-street parking to charge at home and benefit from cheaper, domestic tariffs, as set out in Appendix 2.

Contact Officers Chris Barnes Interim Infrastructure Delivery [email removed] Director, TfGM Richard Nickson Network Director, Active Travel, TfGM [email removed] Equalities Impact, Carbon and Sustainability Assessment: Recommendation - Key points for decision-makers Carbon Assessment Insert text Overall Score 1

Buildings Result Justification/Mitigation New Build residential N/A Impacts Questionnaire Residential building(s) Impact Indicator Result Justification/Mitigation N/A renovation/maintenance Equality and Inclusion G New build non- Health G Resilience and residential (including N/A G Adaptation public) buildings Housing Transport Economy Active travel and public Mobility and G 1.285714 Connectivity transport Carbon, Nature and G Roads, Parking and Environment N/A Vehicle Access Consumption and Production Access to amenities 1 Vehicle procurement N/A Land Use Contribution to achieving the GM Carbon Neutral 2038 target Land use 0.5

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Transport Infrastructure PipelineReport 974 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 18 attended
GM
GM Mayor Andy BurnhamChair, expected
EO
Councillor Eamonn O'BrienVice-Chair, expected
HK
Councillor Hamid KhurramCommittee Member, expected
AQ
Councillor Alan QuinnCommittee Member, expected
TR
Councillor Tracey RawlinsCommittee Member, expected
JC
Councillor Josh ChartersCommittee Member, expected
PB
Councillor Phil BurkeCommittee Member, expected
CM
City Mayor Paul DennettCommittee Member, expected
GB
Councillor Grace BaynhamCommittee Member, expected
SH
Councillor Stephen HomerCommittee Member, expected
AW
Councillor Aidan WilliamsCommittee Member, expected
PP
Councillor Paul PrescottCommittee Member, expected

All 18 on the meeting page

On this subject at Greater Manchester Combined Authority

Search all
  1. Transport Infrastructure PipelineThis decision
  2. Transport Infrastructure PipelineNoted
  3. Transport Infrastructure PipelineNoted
  4. Transport Infrastructure PipelineApproved
  5. Transport Infrastructure PipelineNoted
  6. Transport Infrastructure PipelineNoted

More from Greater Manchester Combined Authority Bee Network Committee

All decisions
MeetingDecisionOutcome
24 Sep 2026 ApologiesApologies were received and noted from Cllr Nazia Rehman (Wigan), City Mayor Paul Dennett (Salford), Cllr Stephen Hom... Noted Open
24 Sep 2026 Appointment UpdatesThat the update on the appointments made at the June meeting of the GMCA be noted. 2. That the appointments of the Ma... Noted Open
24 Sep 2026 Appointments to Outside BodiesThat the appointment of Cllr Barry Winstanley, Cllr Grace Baynham & Cllr Michael Welton to the Greater Manchester Acc... Noted Open
24 Sep 2026 Terms of Reference & Rules of ProcedureThat the terms of reference and rules of procedure be noted. Noted Open
24 Sep 2026 Declarations of InterestThere were none. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies