Greater Manchester Combined Authority
Bee Network Committee, Thursday 25 June 2026 at 2.00pm

Transport Infrastructure Pipeline

Noted Committee 1 paper

AI summaryBee Network Committee approves transport infrastructure funding drawdowns in the region of £140m, including £25.1m for Bury Interchange, £15.6m Local Highways Maintenance, and £49.7m Core Highways Maintenance for 2026/27.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedIntegrated Settlement, Active Travel, and Highways Maintenance allocations across GM
Moneyapprox £140m total drawdowns requestedper paragraph 1.4; includes £49.7m and £15.6m highways pots
What happens nextSchemes to start on site through 2026/27Some contract awards delegated to Group Chief Executive
Who it affectsAll ten GM local authoritiesBolton, Bury, Manchester, Oldham, Rochdale, Salford, Stockport, Tameside, Trafford, Wigan

What was decided

The Committee approved drawdown of Integrated Settlement (CRSTS) funding across 14 schemes, including Bury Interchange £25.1m, City Centre Radials £11.65m, Prestwich Travel Hub £12m, Partington Sustainable Travel £7.37m, and Ashton and Stalybridge £5m. Report P6

The Committee approved drawdown of Active Travel funding across six schemes, including Bury Radcliffe Metrolink Access Ramp and Parkhills Road, Heywood Street Junctions £4m, Islington Neighbourhood £1.44m, and Manchester School Streets £0.6m. Report P6

The Committee approved £49.7m Core Highways Maintenance and Local Safety and Minor Works funding, and £15.6m Local Highways Maintenance funding, both for 2026/27, and delegated authority to the Group Chief Executive with the Vice-Chair to approve further drawdowns before the next meeting. Report P6, 4.2, 5.1

Why

Circa £1.103bn of the £1.27bn allocated to the transport infrastructure pipeline has been released to date and works continue to be delivered at pace. Report 1.3

Recommendations aim to support continued development and delivery of the Bee Network pipeline, mitigate risk of not fully expending Government funding, and contribute to Greater Manchester Strategy pledges on housing, transport, safer streets and a greener future. Report P9, 1.4, P23, P24, P25, P26

Most schemes have been reviewed under the local assurance framework by an independent TfGM panel and are deemed to demonstrate appropriate strategic case, value for money and deliverability. Report 2.7, 2.17, 2.36, 2.49, 2.57, 3.5, 3.19

What happens next

Bury Interchange Phase 1 contract to be awarded this summer, with detailed design and Full Business Case review completed; procurement of a Development Partner/Registered Provider for residential element underway. Report 2.21, 2.22, 2.23

Golborne Station: delegated authority granted to enter into a Design and Build Contract for main construction works once outstanding contractual and commercial arrangements with the identified contractor are concluded, following DfT confirmation of CRSTS retained scheme status. Report 2.30, 2.31, 2.32

Partington Sustainable Travel Scheme expected to start on site July 2026; Salford Islington Neighbourhood works planned August to November 2026; Bury Radcliffe and Parkhills schemes due to start on site October 2026; Aimson Road East / Shaftesbury Avenue scheme expected to start on site September 2026. Report 2.36, 3.6, 3.20, 3.25

The money

  • £1.585m City Centre Bus Strategy Phase 2 delivery drawdown Report P6, 2.2
  • £11.65m City Centre Radials Programme (Wellington Road North, Oldham Road, Early Interventions, remaining Manchester corridor development) Report P6, P45
  • £4.2m Improving Journeys, Orbital Bus Routes Programme drawdown Report P6, 2.16
  • £1.0625m Bus Depot Engineering Asset Renewals across nine depots over next 12 months Report P6, 2.18
  • £25.1m Bury Interchange drawdown to facilitate contract award for Phase 1 and progression of Phase 2 design development Report P6, 2.23
  • £1.512m North-West GM Rapid Transit expansion Strategic Outline Case (third SOC) Report P6, 2.27
  • £7.37m Trafford Partington Sustainable Travel Scheme drawdown Report P6, 2.36
  • £0.1m Salford Ordsall Neighbourhood additional development funding Report P6, 2.39
  • £0.25m Reallocation of previously approved Peel Green Active Travel scheme development funding underspend to Ordsall Neighbourhood Report P6, 2.39
  • £1.95m Salford Chapel Street / Trinity Way Phase 1 drawdown Report P6, 2.44
  • £5m Tameside Ashton and Stalybridge Packages drawdown Report P6, 2.50
  • £12m Bury Prestwich Travel Hub and Park and Ride drawdown Report P6, 2.52
  • £1.6m Manchester Wythenshawe Active Travel Programme Phase 1 drawdown Report P6, 2.54
  • £0.626m Stockport Electric Vehicle Charging Infrastructure drawdown Report P6, 2.58
  • £1.44m Salford Islington Neighbourhood ATF4 drawdown Report P6, 3.6
  • £0.07m Stockport Ladybrook Valley Phase 2 TCF drawdown Report P6, 3.10
  • £0.73m Reallocation of ATF4 funding from completed Heatons and Romiley schemes to Ladybrook Valley Phase 2 Report 3.10, 3.11
  • £0.6m Manchester School Streets drawdown (eight permanent schemes, ANPR cameras and TRO revisions) Report P6
  • £4m Bury Radcliffe Metrolink Access Ramp and Parkhills Road, Heywood Street Junctions drawdown Report P6, 3.20
  • £0.09m Trafford Flixton Community Streets TCF drawdown to close out scheme Report P6, 3.22
  • £0.5m Trafford Aimson Road East / Shaftesbury Avenue Junction Scheme additional TCF drawdown (total scheme cost £1.1m, £0.6m previously drawn) Report P6, 3.25
  • £49.7m Core Highways Maintenance and Local Safety and Minor Works funding for 2026/27, allocated to ten GM local authorities Report P6
  • £15.6m Local Highways Maintenance funding for 2026/27, allocated to ten GM local authorities Report P6, 4.2
  • £1.27bn Total transport infrastructure pipeline allocation (of which circa £1.103bn released to date) Report 1.3
  • £2.47bn GM Transport for City Regions funding allocation confirmed in June 2025 Spending Review for period April 2027 to March 2032 Report 1.5

Options considered

  • Chosen: Approve drawdown of Integrated Settlement funding and Full Business Cases for 14 named schemes. Continued development and delivery of the Bee Network pipeline; supports GMS pledges Report P6, 1.4
  • Chosen: Approve drawdown of Active Travel funding and Full Business Cases for six named schemes. Schemes independently reviewed and demonstrate strategic case, value for money and deliverability Report P6, 3.5, 3.19
  • Chosen: Reallocate £0.25m previously approved Peel Green Active Travel scheme development funding underspend to Ordsall Neighbourhood scheme. Following deferment of Peel Green scheme informed by public engagement feedback Report 2.39
  • Chosen: Reallocate £0.73m ATF4 funding from completed Heatons Link Phase 2 and Romiley to Stockport schemes to Ladybrook Valley Phase 2. Ladybrook Valley scheme cost pressures, including revised accessible ramp design, require additional funding Report 3.9, 3.10
  • Chosen: Delegate authority to Group Chief Executive in consultation with Vice-Chair to approve further drawdowns before September 2026. Support effective decision making between Committee meetings to avoid delays Report 5.1, P156

Implications

  • Financial: Total drawdown requests in the region of £140m; mitigation of programme risk of not fully expending Government funding. Report 1.4, P9
  • Legal: Significant contract workstream supported by internal and external legal teams; Legal Delivery/Funding Agreements to be produced for full scheme and development cost approvals using template agreements agreed with GMCA. Report P10
  • Equalities: Overall Equalities Impact Assessment rating G with mostly positive impacts overall; mix of positive and negative impacts to consider. Report P7, P8
  • Climate: Carbon assessment overall score 1; new build non-residential buildings, transport, active travel, mobility and access all rated G; contribution to GM Carbon Neutral 2038 target assessed at 0.5. Report P7, P8
  • Risk: A programme risk register is maintained and updated regularly by TfGM. Report P9
  • Other: Local Transport Plan 2050 was consulted on between 09 December 2025 and 09 March 2026; Spending Review in June 2025 confirmed GM's TCR allocation of £2.47bn for April 2027 to March 2032. Report 1.5

Who and where

  • Residents and users of the Bee Network across all ten Greater Manchester local authority areas Report 1.1, 1.2
  • Ten GM local authorities receiving highways maintenance and minor works allocations (Bolton, Bury, Manchester, Oldham, Rochdale, Salford, Stockport, Tameside, Trafford, Wigan) Report 4.2, P151, P153
  • Bury Council, including residents of Prestwich, Radcliffe, and the wider area benefiting from interchange redevelopment, travel hub and active travel schemes Report 2.19, 2.22, 2.51, 3.16
  • Salford residents and users of Ordsall, Chapel Street / Trinity Way, and Islington areas Report 2.37, 2.40, 3.3
  • Stockport residents, including those without off-street parking targeted by social housing EVCI provision (over 5000 properties, approximately 100 new 7kw charging bays) Report 2.55, P113
  • Manchester residents, including pupils and parents at eight schools benefiting from permanent School Streets schemes Report 3.12, 3.13
  • Trafford residents in Partington and Flixton, and road users on Shaftesbury Avenue (approximately 25,000-30,000 vehicles per day) Report 2.33, 3.21, 3.23

Timeline

  • June 2026 to June 2027: City Centre Bus Strategy Phase 2 operational interventions delivered Report 2.2
  • Summer 2026: Construction of Wigan, Bolton and Wigan, Leigh junction upgrades expected to commence Report P49
  • Summer 2026: Bury, Rochdale pelican to puffin crossing upgrade scheduled to commence Report P56
  • July 2026: Partington Sustainable Travel Scheme expected to start on site Report 2.36
  • July 2026: Stockport Ladybrook Valley Phase 2 new ramp construction planned to commence Report 3.11
  • August 2026: Salford Islington Neighbourhood works planned to commence on site Report 3.6
  • September 2026: Trafford Aimson Road East / Shaftesbury Avenue scheme expected to start on site Report 3.25
  • Autumn 2026: Construction of City Centre Radials A6 parallel routes packages to begin; Manchester School Streets delivery starting Report 2.8
  • September 2026: Next anticipated Bee Network Committee meeting Report 5.1
  • October 2026: Bury Radcliffe Metrolink Access Ramp and Parkhills Road, Heywood Street schemes due to start on site Report 3.20
  • November 2026: Salford Islington Neighbourhood and Stockport Ladybrook Valley Phase 2 completion scheduled Report 3.6, 3.11
  • Early 2027: Wigan, Bolton and Wigan, Leigh junction upgrades and Salford Crescent, MediaCityUK bus stop upgrades scheduled to complete Report P49, P57
  • Spring 2027: Stockport Road West, Bredbury improvement scheme completion expected Report P55
  • Autumn 2026: Stockport Marple Community Hub due to open, including EV charging bays Report P113
  • End of 2026: Further 155 electric buses to be deployed across Oldham and Hyde Road depots Report P21

Plain English for the jargon

  • Bee Network: Greater Manchester's planned high-quality, affordable and fully integrated public transport and active travel system, including bus, tram (Metrolink), rail and walking, wheeling and cycling.
  • CRSTS: City Region Sustainable Transport Settlement, a Government capital funding stream for major transport schemes.
  • Integrated Settlement: Greater Manchester's consolidated funding settlement incorporating CRSTS and future Transport for City Regions (TCR) funding.
  • Full Business Case (FBC): Final stage of the five-case business case process (Strategic Outline, Outline, Full Business Case) used to approve scheme delivery and drawdown of funds.
  • Active Travel Fund (ATF): Government funding stream for walking, wheeling and cycling infrastructure, distributed in tranches.
  • Transforming Cities Fund (TCF): Government capital funding for local transport improvements, including active travel.
  • MCF: Mayoral Challenge Fund, a Greater Manchester fund supporting local transport improvements.
  • SCOOT: Split Cycle Offset Optimisation Technique, a traffic signal control system that adjusts signal timings in real time to reduce delays.
  • CYCLOPS: Cycle Optimised Protected Signals, a junction design that fully separates cyclists from motor traffic.
  • VMS: Variable Message Signs used to provide real-time journey time information to road users.
  • TRO: Traffic Regulation Order, the legal instrument used to enforce traffic restrictions such as those introduced by School Streets.
  • TfGM: Transport for Greater Manchester, the public body responsible for transport strategy and delivery across GM.
  • GMCA: Greater Manchester Combined Authority, the governance body for the city region.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

That the current position, recent progress and key milestones on the transport infrastructure pipeline be noted. 2. That approval be given to the drawdown of Integrated Settlement funding and associated scheme progression as follows: •City Centre Bus Strategy Phase 2: £1.585m and Full Business Case; •City Centre Radials Programme: £11.65m and Full Business Case for Programme Wide Early Interventions and Wellington Road North, Stockport; •Improving Journeys Programme: £4.2m and Full Business Cases; •Bus Depot Engineering Asset Renewals: £1.0625m; •Bury Interchange: £25.1m and note the update on the residential development; •North-West GM Metrolink Programme: £1.512m; •Golborne Station: Note the recent confirmation received from DfT in relation to CRSTS retained scheme status and grant delegated authority to the Group Chief Executive, in conjunction with the Vice-Chair of the Bee Network Committee, to approve the associated funding allocation and drawdown requirements to enable a contract for the main construction works to be entered into, subject to the conclusion of all outstanding contractual and commercial arrangements with the identified contractor; •Trafford: Partington Sustainable Travel Scheme: £7.37m and Full Business Case; •Salford: Ordsall Neighbourhood: £0.1m and note the reallocation of £0.25m previously approved development funding underspend from Peel Green Active Travel scheme; •Salford: Chapel Street / Trinity Way: £1.95m and Full Business Case for Phase 1; •Tameside: Ashton and Stalybridge Packages: £5m and Full Business Case; •Bury: Prestwich Travel Hub / Park and Ride: £12m and Full Business Case; •Manchester: Wythenshawe Active Travel Programme Phase 1: £1.6m and Full Business Case; and •Stockport: Electric Vehicle Charging Infrastructure: £0.626m and Full Business Case. 3. That approval be given for the drawdown of Active Travel Funding, associated scheme progression and amendments to previously approved scheme budgets as follows: •Salford: Islington Neighbourhood: £1.44m and Full Business Case; •Stockport: Ladybrook Valley Phase 2: £0.07m; •Manchester: School Streets: £0.6m and Full Business Case; •Bury: Radcliffe Metrolink Access Ramp and Parkhills Road – Heywood Street Junctions: £4m and Full Business Cases; •Trafford: Flixton Community Streets: £0.09m; and •Trafford: Aimson Road East / Shaftesbury Avenue Junction Scheme: £0.5m and Full Business Case. 4. That approval be given to the drawdown and allocations of £49.7m Core Highways Maintenance and Local Safety & Minor Works funding for 2026/27. 5. That approval be given for the drawdown and allocations of £15.6m Local Highways Maintenance funding for 2026/27. 6. That authority be delegated to approve any further funding drawdowns which might be required before the next anticipated Bee Network Committee in September 2026 to the Group Chief Executive in consultation with Vice-Chair of the Bee Network Committee.
Word for word from the decision Greater Manchester Combined Authority published for this meeting. Source: democracy.greatermanchester-ca.gov.uk

Follow this further

Built from Greater Manchester Combined Authority's papers

What the report saysPro

Report to Bee Network Committee

Bee Network Committee Date: Thursday 25th June 2026

Subject: Transport Infrastructure Pipeline

Report of: Chris Barnes, Interim Infrastructure Delivery Director, TfGM.

Purpose of Report This report provides an update on progress delivering a pipeline of transport infrastructure improvements to support the Bee Network: a high -quality, affordable and fully integrated public transport and active travel system which can support sustainable economic growth and the wider GM Integrated Pipeline. The report makes a number of recommendations for members to support the continued development and delivery of the pipeline programme.

Recommendations: The Committee are requested to:

1. Note the current position, recent progress and key milestones on the transport infrastructure pipeline; 2. Approve the drawdown of Integrated Settlement (CRSTS) funding and associated scheme progression as follows: • City Centre Bus Strategy Phase 2: £1.585m and Full Business Case; • City Centre Radials Programme: £11.65m and Full Business Case for Programme Wide Early Interventions and Wellington Road North, Stockport; • Improving Journeys Programme: £4.2m and Full Business Cases; • Bus Depot Engineering Asset Renewals: £1.0625m; • Bury Interchange: £25.1m and note the update on the residential development; • North-West GM Metrolink Programme: £1.512m; • Golborne Station: Note the recent confirmation received from DfT in relation to CRSTS retained scheme status and grant delegated authority to the Group Chief Executive, in conjunction with the Vice-Chair of the Bee Network Committee, to approve the associated funding allocation and drawdown requirements to enable a contract for the main construction works to be entered into, subject to the conclusion of all outstanding contractual and commercial arrangements with the identified contractor; • Trafford: Partington Sustainable Travel Scheme: £7.37m and Full Business Case; • Salford: Ordsall Neighbourhood: £0.1m and note the reallocation of £0.25m previously approved development funding underspend from Peel Green Active Travel scheme; • Salford: Chapel Street / Trinity Way: £1.95m and Full Business Case for Phase 1; • Tameside: Ashton and Stalybridge Packages: £5m and Full Business Case; • Bury: Prestwich Travel Hub / Park and Ride: £12m and Full Business Case; • Manchester: Wythenshawe Active Travel Programme Phase 1: £1.6m and Full Business Case; and • Stockport: Electric Vehicle Charging Infrastructure: £0.626m and Full Business Case. 3. Approve the drawdown of Active Travel Funding, associated scheme progression and amendments to previously approved scheme budgets as follows: • Salford: Islington Neighbourhood: £1.44m and Full Business Case; • Stockport: Ladybrook Valley Phase 2: £0.07m; • Manchester: School Streets: £0.6m and Full Business Case; • Bury: Radcliffe Metrolink Access Ramp and Parkhills Road – Heywood Street Junctions: £4m and Full Business Cases; • Trafford: Flixton Community Streets: £0.09m; and • Trafford: Aimson Road East / Shaftesbury Avenue Junction Scheme: £0.5m and Full Business Case. 4. Approve the drawdown and allocations of £49.7m Core Highways Maintenance and Local Safety & Minor Works funding for 2026/27. 5. Approve the drawdown and allocations of £15.6m Local Highways Maintenance funding for 2026/27. 6. Delegate authority to approve any further funding drawdowns which might be required before the next anticipated Bee Network Committee in September 2026 to the Group Chief Executive, in consultation with Vice-Chair of the Bee Network Committee. Contact Officers Chris Barnes Interim Infrastructure Delivery [email removed] Director, TfGM David Budd Interim Transport Plan & Develop [email removed] Director, TfGM Richard Nickson Network Director, Active Travel, TfGM [email removed] Equalities Impact, Carbon and Sustainability Assessment: Recommendation - Key points for decision-makers Carbon Assessment Insert text Overall Score 1

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Transport Infrastructure PipelineReport 977 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 16 attended
GM
GM Mayor Andy BurnhamChair, expected
EO
Councillor Eamonn O'BrienVice-Chair, expected
HK
Councillor Hamid KhurramCommittee Member, expected
AQ
Councillor Alan QuinnCommittee Member, expected
TR
Councillor Tracey RawlinsCommittee Member, expected
JC
Councillor Josh ChartersCommittee Member, expected
CM
City Mayor Paul DennettCommittee Member, expected
GB
Councillor Grace BaynhamCommittee Member, expected
SH
Councillor Stephen HomerCommittee Member, expected
PP
Councillor Paul PrescottCommittee Member, expected
HS
Councillor Howard SykesCo-Optee, expected
MW
Councillor Max WoodvineCo-Optee, expected

All 16 on the meeting page

On this subject at Greater Manchester Combined Authority

Search all
  1. Transport Infrastructure PipelineThis decision
  2. Transport Infrastructure PipelineNoted
  3. Transport Infrastructure PipelineNoted
  4. Transport Infrastructure PipelineApproved
  5. Transport Infrastructure PipelineNoted
  6. Transport Infrastructure PipelineNoted

More from Greater Manchester Combined Authority Bee Network Committee

All decisions
MeetingDecisionOutcome
24 Sep 2026 ApologiesApologies were received and noted from Cllr Nazia Rehman (Wigan), City Mayor Paul Dennett (Salford), Cllr Stephen Hom... Noted Open
24 Sep 2026 Appointment UpdatesThat the update on the appointments made at the June meeting of the GMCA be noted. 2. That the appointments of the Ma... Noted Open
24 Sep 2026 Appointments to Outside BodiesThat the appointment of Cllr Barry Winstanley, Cllr Grace Baynham & Cllr Michael Welton to the Greater Manchester Acc... Noted Open
24 Sep 2026 Terms of Reference & Rules of ProcedureThat the terms of reference and rules of procedure be noted. Noted Open
24 Sep 2026 Declarations of InterestThere were none. Decided Open