Greater Manchester Combined Authority
Bee Network Committee, Thursday 26 March 2026 at 2.00pm

Refreshed Approach to Network Development

Noted Committee 1 paper

AI summaryBee Network Committee endorses new rolling process for planning bus service changes, with £15 million in 2026/27 funding and a first package of changes reaching every Greater Manchester local authority.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNew four phase process for prioritising bus network changes
Money£15 millionAllocated in 2026/27 to Bee Network Improvement Fund
What happens nextSummer 2026Engagement begins after local elections
Who it affectsAll ten GM local authorities33,000 more people within 400m of twice hourly service

What was decided

The committee noted the reasons for a refreshed approach to bus network development.

The committee endorsed the proposed revised approach to network development, including the criteria that will be used to prioritise proposed changes to the bus network.

Why

The original area by area review approach was developed before franchising and could leave some parts of the conurbation waiting years for improvements. Report 3.1

Members told the committee in June 2025 that the process needed to change to deliver interventions more quickly and be more responsive to communities. Report 3.2

Bus usage, punctuality and customer satisfaction have risen since the Bee Network launched, and the new process aims to support continued growth and reliability. Report 1.3, 2.5

What happens next

Subject to endorsement, Transport for Greater Manchester (TfGM) will implement the refreshed approach following the upcoming local elections, with engagement beginning early in summer 2026. Report 7.1

A further package of interventions is planned for announcement late in 2026. Report 7.1

The first round of early interventions, listed in Appendix 1, is planned for delivery in the 2026/27 financial year, subject to final costing and approval. Report 6.1, 7.2

The money

  • £15 million Allocated in the GMCA budget in 2026/27 for the Bee Network Improvement Fund to support Network Development and other enhancement activity. Report 3.4
  • 30% Target to grow bus usage by 2030 from the 2022/23 baseline. Report P19
  • 80% Target for buses to arrive on time (less than one minute early and five minutes late). Report P20
  • 90% Target for Greater Manchester residents to be within 400m of a bus or tram that comes at least twice an hour during weekday daytimes. Report P21
  • 200m Target number of passengers a year by 2030, with over 80% of buses running on time consistently. Report P82
  • just over 150 million Annual bus journeys in 2022/23, grown to over 170 million today. Report 2.5

Options considered

  • Rejected: Area based network reviews, working local authority by local authority around the clockface of Greater Manchester. Did not account for the need to take a holistic view of city region routes, and could leave some areas waiting years for improvements. Report 3.1, 3.2
  • Chosen: New rolling pipeline approach using consistent criteria to identify and prioritise service improvements across the whole city region. Provides quicker, more direct interventions for more places, an always on engagement approach, and a city region wide view of proposals. Report 3.3, 3.5

Implications

  • Legal: Any changes to the franchising scheme will require legal consideration and, in some cases, a statutory consultation before proposals can be taken forward. Report P2, 5.16, 5.21
  • Financial: An overall budget envelope for Bee Network improvements in 2026/27 is set out in the report, with the size of the Bee Network Improvement Fund determined by patronage growth and available funds from the Transport Levy, Mayoral Precept and Central Government. Report 3.4, P3
  • Risk: Vehicle capacity at depots is restricted, and limited numbers of buses and drivers are available, with the transition to a fully zero emission bus fleet by 2030 also requiring some fleet relocations that could delay interventions. Report 5.15
  • Other: The process will run twice a year and produce outputs aligned to five annual service change dates (end of January, during April, late July, late August or early September, and late October). Report 5.22, P73

Who and where

  • Residents of all ten Greater Manchester local authorities (Bolton, Bury, Manchester, Oldham, Rochdale, Salford, Stockport, Tameside, Trafford and Wigan), with interventions touching every area in the first 2026/27 package. Report 6.1, P83
  • People who travel to key employment, retail and leisure destinations, including Logistics North, Middlebrook Retail Park, Stakehill Industrial Estate, Kingsway Business Park, Manchester Airport and the Trafford Centre. Report P80, P90, P91, P112, P126, P139
  • Users of the night time economy and cultural attractions in Manchester city centre, East Didsbury, MediaCity, Stockport, Altrincham, Sale and Stretford. Report P81, P102, P108, P120, P127, P137
  • Communities with long standing connectivity gaps, including Heywood, Middleton, Hollingworth, Hyde, Partington and Mosley Common, where new or improved links are proposed. Report P117, P134, P136, P145

Timeline

  • September 2023: Bee Network bus services launched and the transition to franchising completed. Report 1.2, 2.5
  • June 2025: Update on network development and connectivity brought to the Bee Network Committee, prompting the call for a refreshed approach. Report P6, 3.2
  • Earlier in March 2026: Mayor announced the first package of Network Development interventions for 2026/27. Report 6.1
  • Early summer 2026: Engagement activity for the refreshed approach to commence following local elections. Report 7.1
  • Late 2026: Further package of interventions planned for announcement. Report 7.1
  • September 2026: Some late night trips on Sundays to Wednesdays to be withdrawn from services 36, V1 and equivalent night bus routes in Bolton, Salford and Wigan. Report P93, P123, P144
  • 2026/27 financial year: First Network Development interventions planned for implementation, subject to final costing and approval. Report 6.1
  • 2030: Targets for bus usage growth, on time performance, twice hourly catchment coverage and full transition to a zero emission bus fleet. Report P19, P20, P21, 5.15, P82

Plain English for the jargon

  • Bee Network: Greater Manchester's integrated public transport system, bringing together bus, tram, cycling and walking routes under a single brand.
  • Franchising: The system introduced in Greater Manchester under which the bus network is planned and controlled by Transport for Greater Manchester, rather than being run solely on a commercial basis by individual operators.
  • TfGM: Transport for Greater Manchester, the body responsible for transport policy and delivery across the city region, including the Bee Network.
  • GMCA: Greater Manchester Combined Authority, the governing body made up of the ten Greater Manchester councils and the Mayor.
  • GMS: Greater Manchester Strategy, the overarching plan for the city region's economic, social and environmental development.
  • Clockface: A metaphor used in the report for working around the ten Greater Manchester local authorities in turn, as originally proposed for area based network reviews.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

T hat the reasons for a refreshed approach to bus network development be noted. 2. That the proposed revised approach to network development, including criteria that will be used to prioritise proposed changes to the bus network be endorsed.
Word for word from the decision Greater Manchester Combined Authority published for this meeting. Source: democracy.greatermanchester-ca.gov.uk

Follow this further

Built from Greater Manchester Combined Authority's papers

What the report saysPro

Report to Bee Network Committee

Risk management

N/A

Legal Considerations Any changes to the franchising scheme will require legal consideration. In some cases, a statutory consultation may be required before proposals can be taken forward.

Financial Consequences – Revenue An overall budget envelope for Bee Network improvements 2026/27 is set out in paragraph 3.3.

Financial Consequences – Capital N/A Number of attachments to the report: 1 • Appendix 1: List of early interventions

Comments/recommendations from Overview & Scrutiny Committee N/A

Background Papers Network Development Principles and Connectivity Assessment – Report to Bee Network Committee, June 2025

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Refreshed Approach to Network DevelopmentReport 369 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 18 attended
GM
GM Mayor Andy BurnhamChair, expected
EO
Councillor Eamonn O'BrienVice-Chair, expected
HK
Councillor Hamid KhurramCommittee Member, expected
AQ
Councillor Alan QuinnCommittee Member, expected
TR
Councillor Tracey RawlinsCommittee Member, expected
JC
Councillor Josh ChartersCommittee Member, expected
PB
Councillor Phil BurkeCommittee Member, expected
CM
City Mayor Paul DennettCommittee Member, expected
GB
Councillor Grace BaynhamCommittee Member, expected
SH
Councillor Stephen HomerCommittee Member, expected
AW
Councillor Aidan WilliamsCommittee Member, expected
PP
Councillor Paul PrescottCommittee Member, expected

All 18 on the meeting page

More from Greater Manchester Combined Authority Bee Network Committee

All decisions
MeetingDecisionOutcome
24 Sep 2026 ApologiesApologies were received and noted from Cllr Nazia Rehman (Wigan), City Mayor Paul Dennett (Salford), Cllr Stephen Hom... Noted Open
24 Sep 2026 Appointment UpdatesThat the update on the appointments made at the June meeting of the GMCA be noted. 2. That the appointments of the Ma... Noted Open
24 Sep 2026 Appointments to Outside BodiesThat the appointment of Cllr Barry Winstanley, Cllr Grace Baynham & Cllr Michael Welton to the Greater Manchester Acc... Noted Open
24 Sep 2026 Terms of Reference & Rules of ProcedureThat the terms of reference and rules of procedure be noted. Noted Open
24 Sep 2026 Declarations of InterestThere were none. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies