AI summaryGreater Manchester Bee Network Committee notes the Access for All rail accessibility update covering 19 station schemes across six tranches, backed by £94m of devolved funding, and asks to review the funding prioritisation criteria.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted report and will review prioritisation criteria
Money£94m devolved fundingFrom CRSTS and Integrated Settlement, for 15 of 19 schemes
What happens nextReview of prioritisation criteriaWithout disrupting works already in progress
Who it affectsDisabled and mobility-impaired rail passengersAcross 19 rail station schemes in six tranches
What was decided
The Committee noted the Access for All Programme Update report covering progress on 19 rail station accessibility schemes across six tranches. Report 3.2, 4.1
The Committee will be given an early opportunity to review the criteria used to prioritise Access for All funding, provided this does not disrupt schemes already in progress.
Why
Only 58% of Greater Manchester rail stations are currently step free, and the region wants to extend integrated, accessible journeys beyond Metrolink and buses to the rail network. Report 1.3, 1.4
National Department for Transport Access for All funding has been slow and uncertain, with awards not always matching local priorities such as Swinton and Levenshulme. Report 3.1, 2.6
To address this, GMCA has allocated £94m of devolved CRSTS and Integrated Settlement funding to progress 15 of the 19 schemes, giving greater certainty and speed of delivery. Report 3.2
What happens next
Tranche 1: Walkden station works continue, with Network Rail now approved to progress after mining risk works; Daisy Hill and Irlam were delivered in early 2025. Report 4.2
Tranche 2 construction is under way at Bryn, with Swinton, Reddish North and Hindley to follow; all four are forecast to complete in Spring 2027.
Tranche 3 detailed design is under way with construction forecast to start in early 2027 and complete in early 2028; Tranche 4 outline design contract is scheduled for June 2026, completing in 2029; Tranche 5 outline design contract is scheduled for November 2026. Report 4.5, 4.6, 4.7
The money
£94m GMCA devolved funding from CRSTS and the Integrated Settlement for the Access for All programme Report 3.2
Options considered
Rejected: Rely on national Department for Transport Access for All funding rounds. Protracted delays and uncertainty, with awards not aligned to local priorities, so the £94m devolved alternative was used instead Report 3.1, 3.2
Chosen: Use £94m of devolved CRSTS and Integrated Settlement funding to progress 15 schemes directly. Gives certainty, flexibility, supply chain engagement and avoids long pauses between competitive national rounds Report 3.2
Implications
Financial: £94m of devolved CRSTS and Integrated Settlement funding is committed, over and above Department for Transport Access for All allocations. Report 3.2
Legal: Although GM manages the funding, responsibility for accessible stations remains with the infrastructure owner, usually Network Rail. Report P2
Equalities: Programme aims to improve step-free access for disabled people and those with mobility challenges, with 58% of GM rail stations currently step free rising to a planned 70% by 2029. Report 1.1, 1.3, 4.9
Risk: Continued uncertainty over national Access for All funding poses an ongoing risk; for the 2024 to 2029 round only initial feasibility was funded, with a ministerial decision on delivery expected in late 2027. Report 2.6, 3.1
Staffing: The new Metrolink operations and maintenance contract begins in July 2027 and will include enhanced maintenance and response obligations for lifts and escalators. Report 5.7
Who and where
Disabled passengers and people with mobility challenges using Greater Manchester rail stations Report 1.1, 1.3
Passengers relying on Metrolink lifts, with 36 lifts across 28 stops currently averaging 87% in-service time Report 5.1, 5.2
Residents and users of 19 named rail stations across Salford, Bolton, Stockport, Wigan, Tameside, Manchester, Oldham and Trafford Report P44
Local councillors, MPs and the City Mayor receiving updates on Walkden station Report 4.3
Timeline
early 2025: Daisy Hill and Irlam station accessibility schemes delivered Report 4.2
end of 2025: Construction started at Bryn station under Tranche 2
Spring 2027: Tranche 2 schemes (Bryn, Swinton, Reddish North, Hindley) forecast to complete
Summer 2026 to end of 2027: 8 of 36 Metrolink lifts due to be replaced (Heaton Park, Dane Road, Brooklands, Firswood, Hollinwood, Failsworth, Freehold, Chorlton) Report 5.5
June 2026: Outline design contract for Tranche 4 stations (Bredbury, Woodsmoor, Davenport) scheduled to be awarded Report 4.6
November 2026: Outline design contract for Tranche 5 stations (Broadbottom, Hall I' Th' Wood, Moorside) scheduled to be awarded Report 4.7
early 2027: Tranche 3 construction (Newton for Hyde, Flowery Field, Levenshulme) forecast to start Report 4.5
early 2028: Tranche 3 schemes planned to complete Report 4.5
2027 to 2032: Remaining 28 Metrolink lifts planned for replacement Report 5.5
July 2027: New Metrolink operations and maintenance contract scheduled to commence Report 5.7
late 2027: Ministerial decision expected on which 2024 to 2029 Access for All schemes progress to delivery Report 2.6
2029: Tranche 4 schemes forecast to complete, taking step-free GM rail stations from 58% to 70% Report 4.6, 4.9
Plain English for the jargon
Access for All (AfA): UK Government rail accessibility programme, launched in 2006, which has delivered step-free access at over 270 stations.
Bee Network: Greater Manchester's integrated public transport network covering Metrolink, buses and rail.
CRSTS: City Region Sustainable Transport Settlement, a devolved transport funding pot for city regions.
Integrated Settlement: Greater Manchester's devolved consolidated transport funding arrangement with Government.
TfGM: Transport for Greater Manchester, the regional transport body that reports to GMCA.
GMCA: Greater Manchester Combined Authority, the body overseeing Bee Network Committee decisions.
Tranche: A package or grouping of Access for All rail station schemes being developed together.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
T hat the report be noted. 2. That the Committee be given the opportunity to review the existing criteria for the prioritisation of funding for the programme as soon as possible, but in such a way that will not disrupt works already in progress.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
Legal Considerations Although the funding for the accessibility works is devolved through GM, responsibility for accessible stations remains with the infrastructure owner, which in most cases is Network Rail.
Financial Consequences – Revenue No direct implications from this report.
Financial Consequences – Capital No direct implications from this report.
Number of attachments to the report: 1 Appendix A: GM Priority List
Comments/recommendations from Overview & Scrutiny Committee N/A
Background Papers 12 December 2025 – On the Right Track for Growth: The GM Rail Vision to 2050
Tracking/ Process Does this report relate to a major strategic decision, as set out in the GMCA Constitution ?
No.
Exemption from call in Are there any aspects in this report which means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency? No. 1. Introduction
1.1Improving the accessibility of the Bee Network is an essential element of the Greater Manchester Strategy’s objective to create a transport network for a global city region. Accessible public transport is vital for enabling all residents, including disabled people and those with mobility challenges, to participate fully in economic, social, and community life.
1.2The Metrolink network has set a high standard for accessibility, with step-free access at all stops, demonstrating the region’s commitment to inclusive travel. Bus franchising has enabled accessibility improvements allowing GMCA and TfGM to specify bus accessibility standards including additional wheelchair spaces, low-floor bus entry, audio-visual announcements, clearer signage and dedicated driver training.
1.3Building on this, Greater Manchester’s ambition is to significantly enhance the accessibility of rail stations across the area, ensuring that everyone can benefit from integrated, seamless journeys. Currently only 58% of GM rail stations are step free.
1.4Historically, improvements to rail station access have depended on ring-fenced funding from the Department for Transport, with station prioritisation informed by local intelligence but ultimately determined at a national level. This remains the case for DfT controlled Access for All funding. However, Greater Manchester’s devolved Integrated Settlement and Bee Network Rail Integration provide the opportunity to prioritise and direct investment to improve rail station access based on local priorities.
2. National Access for All Funding
2.1Delivery of Access for All (AfA) schemes has traditionally been funded through the UK Government’s long‑running rail accessibility investment programme. Administered by the Department for Transport (DfT), the national Access for All programme, launched in 2006, has delivered step‑free access at over 270 stations across Great Britain.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Bee Network Committee at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.