Noted the Royal Borough’s updated Strategic Risk Register (Appendices A, B and C) . Noted that the updated Strategic Risk Register was presented to the Audit & Risk Management Panel for consideration on 25th February 2025. Noted that the Strategic Risk Register was presented to Cabinet on 9th April 2025 to note and refer to Council for noting.
Word for word from the decision Greenwich published for this meeting.Source: committees.royalgreenwich.gov.uk
COUNCIL DATE ITEM No. 25th June 2025 11 TITLE WARD (S) Royal Borough of Greenwich All Strategic Risk Register CHIEF OFFICER CABINET MEMBER Director of Resources Finance, Resources and Social Value DECISION CLASSIFICATION IS THE FINAL DECISION ON Non-Key THE RECOMMENDATIONS Non-exempt Appendix IN THIS REPORT TO BE MADE AT THIS MEETING? Yes
1. Decision required
This report makes the following recommendations to Council: 1.1 To note the Royal Borough’s updated Strategic Risk Register (Appendices A, B and C).
1.2To note that the updated Strategic Risk Register was presented to the Audit & Risk Management Panel for consideration on 25th February 2025.
1.3To note that the Strategic Risk Register was presented to Cabinet on 9th April 2025 to note and refer to Council for noting.
2. Links to Our Greenwich missions
2.1This report relates to the Council’s agreed missions as follows:
• Our Council is an adaptive organisation, enabling it to navigate the increasing number of challenges it faces while remaining financially sustainable • Our Council works in the most efficient and effective ways possible ITEM NO: 11 PAGE NO 1 2.2 The Strategic Risk Register is part of the Council’s risk management framework and associated control environment. It supports and helps underpin the overarching ambition to develop the Borough, using resources effectively and efficiently.
3. Purpose of Report and Executive Summary
3.1The Royal Borough’s updated Strategic Risk Register was presented to the Audit & Risk Management Panel, and to Cabinet.
3.2The purpose of this report is for Council to note the updated Strategic Risk Register.
4. Introduction and Background 4.1 The updated Strategic Risk Register (Appendices A, B and C) contains the key risks that threaten the Council’s plans and strategies, and sets out the controls and mitigating actions in place to manage the risks.
4.2The Strategic Risk Register is owned by the Greenwich Management Team (GMT).
4.3In line with the Council’s organisational structure as detailed in Part 7 of the Constitution, each risk in the register is assigned to one designated Director who owns and retains responsibility for the risk.
4.4As part of the usual Risk Register review process, GMT scrutinises each risk in the Strategic Risk Register to ensure it continues to represent the key risks facing the Council. They also consider the reasonableness of individual risk assessments, the effectiveness of identified internal controls and progress made with implementation and completion of identified mitigating actions. Consideration is also given to any new and/or escalated risks for inclusion in the Strategic Risk Register, which are highlighted as “NEW” in the risk title. 4.5 For this review and reporting cycle, however, there is no new and/or escalated risk.
ITEM NO: 11 PAGE NO 2 4.6 The Strategic Risk Register presents risks captured at a point in time.
4.7The identification, management, review and reporting of risks to various Committees and within decision reports as part of the Council’s decision making process remains a continuous process.
4.8In addition to the detailed Strategic Risk Register (Appendix A), the following risk reports, which provide helpful summaries and visuals were also considered and agreed by GMT: • Risk Dashboard (Appendix B) – a high level representation of assessments, overall control effectiveness, actions status and assessment trends • Risk Profile (Appendix C) – heatmap showing the gross, net and target risk assessments; and guidance on the 5x5 matrix (likelihood and impact definition)
Gross Level of risk (i.e., likelihood & impact) assuming no controls or actions are in place Net Level of risk (i.e., likelihood & impact) after existing internal controls have been applied and assumed to be effective Target Desired Level of risk after all mitigation actions have been completed and internal controls applied remain effective
5. Available Options
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.