Royal Borough of Greenwich Strategic Risk Register

Noted Executive 4 papers

AI summaryCabinet noted the Council's Strategic Risk Register, which lists key risks to corporate plans, with no direct financial implications and will go to the Audit and Risk Management Panel next week.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted the Strategic Risk Register
MoneyNo direct costNo direct financial implications arise from the decision
What happens nextARM Panel then Full CouncilARM Panel on 21 July 2026, Full Council on 22 July 2026
Who it affectsNot stated

What was decided

Cabinet noted the Council's Strategic Risk Register, comprising Appendices A, B and C of the report. Report 10.1

Cabinet noted that the Strategic Risk Register will be presented to the Audit and Risk Management Panel on 21 July 2026 for consideration. Report P4

Cabinet noted that the Strategic Risk Register will be presented to Full Council for noting on 22 July 2026. Report P4

Why

The Council is legally required to maintain a sound system of internal control that includes effective arrangements for the management of risks. Report 7.1

The report is for noting and gives rise to no direct legal or Human Rights Act implications. Report P4

What happens next

The Audit and Risk Management Panel will consider the updated Strategic Risk Register on 21 July 2026, in line with Part 3 of the Council's Constitution. Report P4

Full Council will note the updated Strategic Risk Register on 22 July 2026. Report P4

No consultation is required and none has been undertaken in respect of this report. Report 8.1

Options considered

  • Chosen: Note the Strategic Risk Register and refer it on. Forms part of the Council's wider assurance framework as set out in Part 3 of the Constitution. Report P4

Implications

  • Legal: The Council is legally required to have a sound system of internal control, including risk management, and the report gives rise to no direct legal or Human Rights Act implications. Report 7.1, P4
  • Risk: The report sets out a register of the key risks that threaten the Council's corporate plans and strategies, including the controls in place and actions to manage the risks. Report P5
  • Equalities: The decisions recommended have a remote or low relevance to the substance of the Equality Act, with no apparent equality impact on end users. Report P5
  • Climate: The decision has a remote or low relevance to the Greenwich Carbon Neutral Plan agreed by Cabinet on November 2020. Report P5
  • Other: Cabinet's consideration of the Strategic Risk Register forms part of the Council's wider assurance framework. Report P4

Who and where

  • The Council's governance and risk management framework, overseen by the Audit and Risk Management Panel and Full Council Report P4

Timeline

  • November 2020: Cabinet agreed the Greenwich Carbon Neutral Plan Report P5
  • 11 June 2026: Sign-off of legal, equalities, climate, risk and community engagement implications Report P4, P5
  • 12 July 2026: Finance and resources sign-off by the Accountancy Business Change Manager Report P4
  • 15 July 2026: Cabinet noted the Strategic Risk Register
  • 21 July 2026: Audit and Risk Management Panel to consider the Strategic Risk Register Report P4
  • 22 July 2026: Full Council to note the Strategic Risk Register Report P4

Plain English for the jargon

  • Strategic Risk Register: A register of the key risks that threaten the Council's corporate plans and strategies, including controls and actions to manage the risks.
  • Audit and Risk Management Panel (ARM Panel): A Council body responsible, under Part 3 of the Constitution, for independent assurance of the risk management framework and the control environment.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

Noted the Council’s Strategic Risk Register (Appendices A, B and C of the report). Noted that the Strategic Risk Register will be presented to the Audit & Risk Management Panel for consideration on 21 July 2026. Noted that the Strategic Risk Register will be presented to Full Council for noting on 22 July 2026.
Word for word from the decision Greenwich published for this meeting. Source: committees.royalgreenwich.gov.uk

Follow this further

Built from Greenwich's papers

What the report saysPro

Report to Cabinet

CABINET DATE ITEM NO 15 July 2026 7 TITLE WARD (S) Royal Borough of Greenwich All Strategic Risk Register CHIEF OFFICER CABINET MEMBER Director of Resources Finance and Resources DECISION CLASSIFICATION IS THE FINAL DECISION ON THE RECOMMENDATIONS Non-Key IN THIS REPORT TO BE MADE AT THIS MEETING? Non-exempt Appendix Yes

1. Decision required

This report makes the following recommendations to Cabinet:

1.1To note the Council’s Strategic Risk Register (Appendices A, B and C).

1.2To note that the Strategic Risk Register will be presented to the Audit & Risk Management Panel for consideration on 21 July 2026.

1.3To note that the Strategic Risk Register will be presented to Full Council for noting on 22 July 2026.

2. Links to Our Greenwich missions

2.1This report relates to the Council’s agreed missions as follows:

• Our Council is an adaptive organisation, enabling it to navigate the increasing number of challenges it faces while remaining financially sustainable • Our Council works in the most efficient and effective ways possible

2.2The Strategic Risk Register is part of the Council’s governance, risk management and internal control framework. It supports and helps underpin the overarching ambition to develop the Borough, using resources effectively and efficiently.

ITEM NO: 7 PAGE NO: 1 3. Purpose of Report and Executive Summary

3.1On 21 July 2026, the Council’s Strategic Risk Register will be presented to the Audit & Risk Management (ARM) Panel in line with Part 3 of the Constitution, which details the Terms of Reference of the ARM Panel including the following responsibilities:

Governance, risk and control • To monitor the effective development and operation of risk management in the Council including progress in addressing risk- related issues reported to the Panel.

Accountability arrangements • To report to those charged with governance on the Panel’s findings, conclusions and recommendations concerning the adequacy and effectiveness of the governance, risk management and internal control framework, financial reporting arrangements and internal and external audit functions.

3.2The purpose of this report is for Cabinet to note the Strategic Risk Register, which will be considered by the ARM Panel; and referred to Full Council for noting.

4. Introduction and Background

4.1The Strategic Risk Register (Appendices A, B and C) contains the key risks that threaten the Council’s plans and strategies, and sets out the controls and mitigating actions in place to manage the risks.

4.2The Strategic Risk Register is owned by the Greenwich Management Team (GMT).

4.3In line with the Council’s organisational structure as detailed in Part 7 of the Constitution, each risk in the register is assigned to one designated Director who owns and retains responsibility for the risk.

4.4As part of the Council’s risk register review process, GMT scrutinises the Strategic Risk Register to ensure it continues to accurately reflect the key strategic risks facing the Council. They also consider the: • reasonableness of individual risk evaluations; • adequacy and effectiveness of identified internal controls; and

ITEM NO: 7 PAGE NO: 2 • progress in the implementation and completion of agreed mitigating actions.

4.5Due consideration is also given to any newly identified risks and/or escalated risks from departmental risk registers proposed for potential inclusion within the Strategic Risk Register. Where such risks are identified or proposed, they are clearly denoted as “NEW” within the risk title.

4.6For the current review and reporting cycle, no new or escalated risks have been identified for inclusion in the Strategic Risk Register.

4.7The Strategic Risk Register provides a snapshot in time of the strategic risks identified and considered as part of the Council’s risk register review process.

4.8The identification, management, review and reporting of risks including to various Committees and within decision reports as part of the Council’s decision-making process remain a continuous process.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 1.7 MB Download
PDF
Appendix BAppendix B 462 KB Download
PDF
Appendix CAppendix C 320 KB Download
PDF
Royal Borough of Greenwich Strategic Risk RegisterReport 76 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 18 attended
AO
Councillor Anthony OkerekeChair, present
JS
Councillor Jackie SmithVice-Chair, present
JA
Councillor Joshua AyodeleCommittee Member, present
SB
Councillor Sandra BauerCommittee Member, present
TC
Councillor Tom CreswellCommittee Member, present
AK
Councillor Adel KhairehCommittee Member, present
ML
Councillor Mariam LolavarCommittee Member, present
AM
Councillor Asli MohammedCommittee Member, present
CO
Councillor Calum O'Byrne MulliganCommittee Member, apologies
RT
Councillor Rachel Taggart-RyanCommittee Member, present
CE
Chief ExecutiveOfficer, in attendance
DO
Director of ResourcesOfficer, in attendance

All 18 on the meeting page

On this subject at Greenwich

Search all
  1. Royal Borough of Greenwich Strategic Risk RegisterThis decision
  2. Royal Borough of Greenwich Strategic Risk RegisterNoted
  3. Review of Premises Licence for: The Borough Hall, Royal Hill, Greenwich, SE10 8RE (LN/17321)Agreed
  4. Royal Borough of Greenwich Outdoor Events PolicyAgreed
  5. Royal Borough of Greenwich Strategic Risk RegisterNoted
  6. Royal Borough of Greenwich Strategic Risk RegisterNoted

More from Greenwich Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Royal Greenwich Safeguarding Adults Board Annual Report 2025-26Noted the 2025/26 Royal Greenwich Safeguarding Adults Board Annual Report Noted Open
23 Sep 2026 Private Housing Enforcement Policy 2026 to 2029Agreed to adopt the amended Private Sector Housing Enforcement Policy in Appendix 1 including the revised schedule of... Agreed Open
23 Sep 2026 Approval to publish the Local Flood Risk Management StrategyApproved the publication of the completed Greenwich’s Local Flood Risk Management Strategy (LFRMS). Approved Open
23 Sep 2026 2025/26 OutturnNoted the Council’s revenue outturn position for 2025/26 as at the end of March 2026 Noted Open
23 Sep 2026 Draft Statement of Accounts 2025/26Considered the authority’s draft Statement of Accounts for the year ended 31 March 2026 (including the Pension Fund A... Decided Open