Royal Borough of Greenwich Strategic Risk Register
NotedCommittee4 papers
AI summaryRoyal Borough of Greenwich Council noted its updated Strategic Risk Register, with no new or escalated risks added this cycle. The Register had already been noted by Cabinet on 15 July 2026 and considered by the Audit & Risk Management Panel on 21 July 2026.
Written from the decision and the officer reportPDF Pro
OutcomeNotedAppendices A, B and C recorded by Council
MoneyNo direct financial implications
What happens nextContinuous risk reviewIdentification, management and reporting of risks remain ongoing
Who it affectsCouncil governance and risk managementOwned by Greenwich Management Team
What was decided
Council noted the Strategic Risk Register, made up of Appendices A, B and C, which lists the key risks threatening the Council's plans and strategies together with controls and mitigating actions. Report P3, 4.1
Council noted that the Register had been presented to Cabinet on 15 July 2026 for noting. Report 1.2
Council noted that the Register had been presented to the Audit & Risk Management Panel on 21 July 2026 for consideration, in line with Part 3 of the Constitution. Report 1.3, P38
Why
The Council is legally required to maintain a sound system of internal control, which includes effective arrangements for managing risks. Report 7.1, P35
The Strategic Risk Register forms part of the Council's governance, risk management and internal control framework, supporting the overarching ambition to develop the Borough using resources effectively. Report 5.1, P9
The Greenwich Management Team scrutinises the Register each cycle to check that it reflects current strategic risks, that risk scores are reasonable, and that controls and mitigating actions are adequate. Report 4.4
What happens next
Each risk remains assigned to a designated Director, who owns and retains responsibility for it, with departmental risk registers feeding into the Strategic Risk Register as needed. Report 4.3, 4.5
Risks continue to be reported through committees and in decision reports as part of ongoing decision making. Report 4.8
Options considered
Chosen: Note the report. Report is for information only; only one option available Report 5.2, 6.1
Implications
Legal: No direct legal or Human Rights Act implications arise from this report. Report P39
Financial: No direct financial implications arise from this report. Report P42
Equalities: The decision has remote or low relevance to the Equality Act and to the Council's Equity and Equality Charter and Equality Objectives 2020-2024, with no apparent impact on end users. Report P43, P44
Climate: The decision has remote or low relevance to the Greenwich Carbon Neutral Plan agreed by Cabinet on November 2020. Report P45
Risk: The Register sets out controls and mitigating actions for each strategic risk, with a Risk Dashboard and Risk Profile heatmap providing high-level summaries and trend visuals. Report 4.1, 4.9, P24
Who and where
Greenwich Management Team, which owns the Strategic Risk Register Report 4.2
Designated Directors, each assigned responsibility for a specific risk under the Council's Constitution Report 4.3
Audit & Risk Management Panel, which provides independent assurance on the risk management framework Report P36, P37
Timeline
November 2020: Cabinet agreed the Greenwich Carbon Neutral Plan (referenced for climate relevance assessment) Report P45
15th July 2026: Cabinet noted the updated Strategic Risk Register Report 1.2, P38
21st July 2026: Audit & Risk Management Panel considered the updated Strategic Risk Register and agreed it Report 1.3, P38
22nd July 2026: Full Council noted the Strategic Risk Register Report P1
Plain English for the jargon
GMT: Greenwich Management Team, which owns the Strategic Risk Register
Gross risk: Level of risk (likelihood and impact) assuming no controls or actions are in place
Net risk: Level of risk after existing internal controls have been applied and are assumed to be effective
Target risk: Desired level of risk after all mitigation actions are completed and internal controls remain effective
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13
Resolved
Noted the Council’s Strategic Risk Register (Appendices A, B and C of the Report). Noted that the Strategic Risk Register was presented to Cabinet on 15th July 2026 for noting. Noted that the Strategic Risk Register was presented to the Audit & Risk Management Panel for consideration on 21st July 2026.
Word for word from the decision Greenwich published for this meeting.Source: committees.royalgreenwich.gov.uk
COUNCIL DATE ITEM No. 22nd July 2026 13 TITLE WARD (S) Royal Borough of Greenwich All Strategic Risk Register CHIEF OFFICER CABINET MEMBER Director of Resources Finance and Resources DECISION CLASSIFICATION IS THE FINAL DECISION ON THE RECOMMENDATIONS Non-exempt Appendix IN THIS REPORT TO BE MADE AT THIS MEETING? Yes
1. Decision required
This report makes the following recommendations to Council: 1.1 To note the Council’s Strategic Risk Register (Appendices A, B and C).
1.2To note that the Strategic Risk Register was presented to Cabinet on 15th July 2026 for noting.
1.3To note that the Strategic Risk Register was presented to the Audit & Risk Management Panel for consideration on 21st July 2026.
2. Links to Our Greenwich missions
2.1This report relates to the Council’s agreed missions as follows:
• Our Council is an adaptive organisation, enabling it to navigate the increasing number of challenges it faces while remaining financially sustainable • Our Council works in the most efficient and effective ways possible
ITEM NO: 13 2.2 The Strategic Risk Register is part of the Council’s governance, risk management and internal control framework. It supports and helps underpin the overarching ambition to develop the Borough, using resources effectively and efficiently.
3. Purpose of Report and Executive Summary
3.1The Council’s Strategic Risk Register was presented to Cabinet and Audit & the Risk Management Panel.
3.2The purpose of this report is for Council to note the Strategic Risk Register.
4. Introduction and Background
4.1The updated Strategic Risk Register (Appendices A, B and C) contains the key risks that threaten the Council’s plans and strategies, and sets out the controls and mitigating actions in place to manage the risks.
4.2The Strategic Risk Register is owned by the Greenwich Management Team (GMT).
4.3In line with the Council’s organisational structure as detailed in Part 7 of the Constitution, each risk in the register is assigned to one designated Director who owns and retains responsibility for the risk.
4.4As part of the Council’s risk register review process, GMT scrutinises the Strategic Risk Register to ensure it continues to accurately reflect the key strategic risks facing the Council. They also consider the: • reasonableness of individual risk evaluations; • adequacy and effectiveness of identified internal controls; and • progress in the implementation and completion of agreed mitigating actions.
4.5Due consideration is also given to any newly identified risks and/or escalated risks from departmental risk registers proposed for potential inclusion within the Strategic Risk Register. Where such risks are
ITEM NO: 13 identified or proposed, they are clearly denoted as “NEW” within the risk title.
4.6For the current review and reporting cycle, no new or escalated risks have been identified for inclusion in the Strategic Risk Register.
4.7The Strategic Risk Register provides a snapshot in time of the strategic risks identified and considered as part of the Council’s risk register review process.
4.8The identification, management, review and reporting of risks including to various Committees and within decision reports as part of the Council’s decision-making process remain a continuous process.
4.9In addition to the detailed Strategic Risk Register (Appendix A), the following risk reports, which provide helpful summaries and visuals, were also considered and agreed by GMT:
• Risk Dashboard (Appendix B) – a high-level representation of assessments, overall control effectiveness, actions status and assessment trends • Risk Profile (Appendix C) – heatmap showing the gross, net and target risk assessments; and guidance on the 5x5 matrix (likelihood and impact definition)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.