Phases 3, 4 And 5 Greenwich Millennium Village, Peartree Way, Greenwich, London, SE10 - Ref: 25/3074/MA

Deferred Planning 3 papers

AI summaryGreenwich Planning Board defers Greenwich Millennium Village Phases 3 to 5 amendment for a site visit and for the applicant to address green public space concerns.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDeferredTo allow a member site visit and applicant response on green space
MoneyNot stated
What happens nextSite visit and applicant responseOn loss of consented and available green public space
Who it affectsGreenwich Millennium Village, Phases 3, 4 and 5On Peartree Way, Greenwich Peninsula, SE10

What was decided

The Planning Board deferred the Section 73 minor material amendment application so members could carry out a site visit and so the applicant could consider and respond to concerns about the loss of consented green public space and available green public space.

Why

The application, reference 25/3074/MA, seeks a minor material amendment to planning permission 19/1545/MA, dated 14/11/2019, and proposes adding a planning condition to confirm that no development or works will take place on Plots 501 and 502 under this permission. Report P3

Concerns were raised during the meeting about the loss of consented green public space and the amount of available green public space within the development.

What happens next

Members will undertake a site visit before the application is reconsidered.

The applicant is to consider and respond to the concerns raised about the loss of consented green public space and available green public space.

Options considered

  • Rejected: Grant the Section 73 minor material amendment (officer recommendation in the agenda item). Members deferred to allow a site visit and further consideration of green public space concerns

Implications

  • Legal: Determination of the Section 73 application for Phases 3, 4 and 5 of Greenwich Millennium Village is delayed pending a site visit and further consideration by the applicant.
  • Other: A proposed additional planning condition would prevent any development or works on Plots 501 and 502 under this permission. Report P3

Who and where

  • Future residents and users of Greenwich Millennium Village Phases 3, 4 and 5 Report P3
  • Greenwich Peninsula ward residents and visitors using public open space at the village
  • The applicant for application 25/3074/MA Report P3

Timeline

  • 14/11/2019: Original planning permission 19/1545/MA granted Report P3
  • 9 September 2025: Applicant submitted Statement of Conformity letter by Waterman Report P3
  • 11 September 2025: Applicant submitted covering letter for application 25/3074/MA Report P3
  • 2026-01-20: Planning Board deferred the application for a site visit and applicant response on green public space concerns

Plain English for the jargon

  • Section 73 application: An application under Section 73 of the Town and Country Planning Act 1990 to vary or remove conditions on an existing planning permission.
  • Minor material amendment: A small change to an existing planning permission, for which a Section 73 application is made.
  • Reserved matters: Details of a planning permission that were not fixed at the outline stage and require later approval, such as appearance, layout, scale and landscaping.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

Resolved that the matter be deferred in order that Members could undertake a site visit and to allow the applicant to consider and respond to concerns raised in respect of the loss of consented green public spac e and available green public space.
Word for word from the decision Greenwich published for this meeting. Source: committees.royalgreenwich.gov.uk

Follow this further

Built from Greenwich's papers

What the report saysPro

Report to Planning Board

Appendices Appendix 1: Plan and Report References

The following drawings and associated documentation have been submitted by the applicant in support of application reference: 25/3074/MA:

3024-JWA-ZZ-ZZ-D-A-1017 Rev P02, 2368-MP-026 Rev P02, Statement of Conformity letter by Waterman dated 9 September 2025 and covering letter dated 11 September 2025.

ITEM NO: 4 – Appendices PAGE NO: 1 Appendices

ITEM NO: 4 – Appendices PAGE NO: 2 Appendices

Appendix 2 – Conditions and Informatives

Condition 1 Approved Drawings The development hereby permitted shall be carried out in accordance with the following approved plans:

2368-MP-001 rev. P01, 010 rev. P02, 011 rev. P08, 012 rev. P03, 013 rev. P02, 014 rev. P02, 015 rev. P02, 016 rev. P01, 2368-P1-100 rev. P01, 110 rev. P01, 111 rev. P01, 112 rev. P01, 113 rev. P01, 114 rev. P01, 115 rev. P01, 116 rev. P01, 117 rev. P01, 118 rev. P01, 119 rev. P01, 120 rev. P01, 121 rev. P01, 122 rev. P01, 130 rev. P01, 131 rev. P01, 132 rev. P01, 2368-01-001rev. P01, 002 rev. P01, 003 rev. P01, 004 rev. P01, 005 rev. P01, 006 rev. P01, 007 rev. P01, 031 rev. P01, 032 rev. P01, 033 rev. P01, 034 rev. P01, 041 rev. P01, 042 rev. P01, 043 rev. P01, 2368-03-001 rev. P01, 002 rev. P01, 003 rev. P01, 004 rev. P01, 005 rev. P01, 006 rev. P01, 007 rev. P01, 008 rev. P01, 009 rev. P01, 010 rev. P01, 011 rev. P01, 012 rev. P01, 031 rev. P01, 032 rev. P01, 033 rev. P01, 041 rev. P01, 2368-05-001 rev. P01,002 rev. P01, 003 rev. P01, 004 rev. P01, 005 rev. P01, 006 rev. P01, 007 rev. P01, 008 rev. P01, 009 rev. P01, 010 rev. P01, 011 rev. P01, 012 rev. P01, 031 rev. P01, 032 rev. P01, 033 rev. P01, 034 rev. P01, 035 rev. P01, 036 rev. P01, 041 rev. P01, 042 rev. P01, 043 rev. P01, 2368-08-001 rev.P01,002 rev.P01, 003 rev.P01, 004 rev.P01, 005 rev.P01, 006 rev.P01, 031 rev.P01, 032 rev.P01, 041 rev.P01, 2368-SK-344 rev. P01, 345 rev. P01, 346 rev. P01, 347 rev. P01, 348 rev. P01, 349 rev. P01, 350 rev. P01, 351 rev. P01, 352 rev. P01, 353 rev. P01, 2581-JW-006 Rev P02, 2581-07-001 Rev P05, 2581-07-002 Rev P05, 2581-07-003 Rev P05, 2581-07-004 Rev P05, 2581-07- 005 Rev P03, 2581-07-006 Rev P03, 2581-07-007 Rev P03, 2581-07-008 Rev P03, 2581-07-009 Rev P03, 2581-07-010 Rev P06, 2581-07-011 Rev P06, 2581-07-012 Rev P03, 2581-07-401 Rev P02, 2581-07-402 Rev P03, 2581-07-414 Rev P02, 2581- SK-172 Rev P01, 2581-SK-171 Rev P01, 126-L21 Rev B, 126-L22 and 3024-JWA- ZZ-ZZ-D-A-1801-P03 and 3024-JWA-ZZ-ZZ-D-A-1017 Rev P02.

Reason 1: For the avoidance of doubt and in the interests of proper planning.

Condition 2 Reserved Matters No building work shall be started until detailed plans/sections and elevations showing the following details in respect of relevant parts of the development have been submitted to, and approved by, the Local Planning Authority and the relevant part of the development shall in all respects be carried out in accordance with the approved plans:

ITEM NO: 4 – Appendices PAGE NO: 3 Appendices

(a) Appearance (b) Layout (c) Scale (d) Landscaping

Plots 206, 207, 208, 209 and 210 shall be implemented in accordance with the details approved under reserved matters application Reference 13/3281/R approved on 15 April 2014.

Plot 504 shall be implemented in accordance with the details approved under reserved matters application Reference 17/0576/R approved on 01 June 2017.

Plots 204 and 205 shall be implemented in accordance with the details approved under reserved matters application Reference 17/1631/R approved on 21 November 2017. Plots 302, 303 and 304 shall be implemented in accordance with the details approved under reserved matters application Reference 18/1318/R approved on 05 September 2018.

Reason 2 In order that the Council is satisfied with the details of the proposed development and to ensure compliance with Policies DH1, DH2, OS(f), IM(a), IM(b), IM(c), and CH1 of the Royal Greenwich Local Plan: Core Strategy with Detailed Policies (July 2014).

Condition 3 Expiration of Planning Permission

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendicies Phases 3, 4 And 5 Greenwich Millennium Village: Ref 25.3074.MAReport 256 KB DownloadRead as text
PDF
Item 4: Addendum to Phases 3, 4 And 5 Greenwich Millennium Village: Ref 25.3074.MAAddendum 48 KB Download
PDF
Phases 3, 4 And 5 Greenwich Millennium Village, Peartree Way, Greenwich, London, SE10: Ref: 25/3074/MAReport 1.1 MB Download

At this meeting

Whole meeting

Who was there

7 of 17 attended
GD
Councillor Gary DillonChair, apologies
SB
Councillor Sandra BauerVice-Chair, in the Chair, present
OB
Councillor Olu BabatolaCommittee Member, absent
CB
Councillor Clare Burke-McDonaldCommittee Member, apologies
MR
Councillor Maisie Richards CottellCommittee Member, apologies
DG
Councillor David GardnerCommittee Member, present
CO
Councillor Calum O'Byrne MulliganCommittee Member, present
‘H
Councillor ‘Lade Hephzibah OlugbemiCommittee Member, present
DS
Councillor Dave SullivanCommittee Member, present
PG
Councillor Patricia GreenwellCommittee Member, present
TR
Councillor Tamasin RhymesCommittee Member, present
NW
Councillor Nick WilliamsGuest, in attendance

All 17 on the meeting page

On this subject at Greenwich

Search all
  1. Phases 3, 4 And 5 Greenwich Millennium Village, Peartree Way, Greenwich, London, SE10 - Ref: 25/3074/MAThis decision
  2. Phases 3, 4 And 5 Greenwich Millennium Village, Peartree Way, Greenwich, London, SE10 - Ref: 25/3074/MAApproved
  3. Maurer, Metcalfe, Holly & New Becquerel Courts, Faraday, Alamaro, DaVinci & Newton Lodges, Greenwich Millenium Village Phases 1 & 2, West Parkside, Greenwich, SE10 0BY - Ref: 24/3879/FDecided
  4. Plot 203, 7 Warman Walk, GMV Phases 345, Greenwich, SE10 0WU - Ref: 24/3389/FDecided

More from Greenwich Planning Board

All decisions
MeetingDecisionOutcome
24 Sep 2026 Former Lewisham College, 1 Deptford Bridge, London, SE8 4HH - Ref: 25/0798/FResolved – That consideration of the application be DEFERRED pending Lewisham Council’s determination of the applicat... Deferred Open
24 Sep 2026 Land at 71-73 Nathan Way, Thamesmead, London, SE28 0BQ - Ref: 26/1040/FResolved - That full planning permission be GRANTED for: A . The Erection of industrial warehouse buildings for flexi... Agreed Open
21 Jul 2026 STC Ivor Grove Sports Club, Ivor Grove, Eltham, London, SE9 2AJResolved that full planning permission be REFUSED for the demolition of all existing sports club buildings and redeve... Refused Open
21 Jul 2026 Land to the east of East Parkside, south of Edmund Halley Way and west of Olympian Way ('Plot 20.02'), Greenwich Peninsula SE10Resolved that full planning permission be GRANTED for the temporary use of land for up to 10 years for the installati... Agreed Open
21 Jul 2026 Garage Sites Opposite to 48 - 53 Sewell Road SE2 9XW & 23 Ampleforth Road SE2 9BD - 17 Sewell Road SE2 9XNResolved that full planning permission be GRANTED for the redevelopment of 2 sites, comprising residential dwellings ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies