Resolved

Decision (1) That a supplementary estimate of £380,000 for the planning appeal costs in relation to the Howard of Effingham School, Wisley Airfield and Guildford Railway Station, to be financed from the budget pressures reserve, be approved. (2) That the unspent balance on the masterplan reserve of £134,000 be transferred to the 2016-17 major projects team budget to finance ongoing work in relation to the scoping and feasibility assessment of projects that have arisen following the Allies and Morrison town centre masterplan. (3) That the transfer to reserves of the sums included in the proposed budget at Appendix 3 to the report submitted to the Executive, plus any additional transfers to or from reserves set out in section 10 of the report, be approved. Recommend (to Council 8 February 2017): (1) That the proposed fees and charges for 2017-18 relating to General Fund services, and attached at Appendix 5 to the report submitted to the Executive be adopted with effect from 1 April 2017. (2) That the budget be approved, and specifically that the Council Tax requirement (excluding parish precepts) for 2017-18 be set at £9,164,601. (3) That the Band D Council Tax for 2017-18 (excluding parish precepts) be set at £161.82, an increase of £5 (3.19%). Reason for Recommendation: To enable the Council to set the Council Tax requirement and council tax for the 2017-18 financial year. Alternative options considered and rejected by the Executive: None Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Executive Report Wards affected: All Report of Chief Finance Officer Author: Claire Morris Tel: 01483 444827 Email: [email protected] Lead councillor responsible: Michael Illman Tel: [phone removed] Email: [email protected] Date: 24 January 2017

Business planning – General Fund Budget 2017-18 Executive Summary

This report outlines the proposed budget for 2017-18, which includes a Council Tax requirement of £9,164,601 (excluding parish precepts) and a Council Tax increase of £5 per year (3.19%), resulting in a band D charge of £161.82. As described in paragraph 10.3, the Council expects to achieve a balanced budget for 2017-18.

We received the provisional Local Government Finance Settlement (LGFS) for 2017-18 on 15 December. The figures included in the outline budget presented to the Executive on 29 November 2016 were on the 4-year local government finance settlement issued by Government in February 2016. The Settlement Funding Assessment (SFA) set out in the provisional LGFS was the same as the assumptions included in the outline budget. Our SFA (which includes assumed income from the Business Rates Retention Scheme) is a reduction of 19.2% from 2016-17. Within the settlement, the government has assumed that we will increase our Council Tax by £5 per annum.

The provisional award of New Homes Bonus (NHB) for 2017-18, also notified to us on 15 December, is slightly higher than anticipated despite an overall reduction in NHB nationally. The government have announced that only growth above a 0.4% baseline will attract NHB from 2017-18 onwards and it is consulting on options to further reduce NHB allocations where there is no local plan in place or houses are built following a successful appeal. In preparing the outline budget, officers had assumed that the government would reduce the NHB allocation in 2017-18 if no local plan was in place but had not anticipated the implementation of a 0.4% baseline growth assumption therefore the overall impact of the changes was a small increase in NHB grant from the amount assumed in the outline budget. The budget includes previously reported1 additional investment in our services of £2.9 million to meet our corporate plan priorities, which has now reduced to £1.9 million. The reason for the decrease is reductions in the revenue implications of the crematorium rebuild project in 2017-18, and a reduction in the waste anticipated growth in waste and recycling. The principal areas of additional investment in services included in the budget relates to our ambitious corporate plan and includes:

1. Design and feasibility work to implement the sustainable movement corridor (£100,000) 2. Feasibility study to investigate the installation of a bridge on A323 Guildford Road, Ash over the railway line at Ash Railway Station (£80,000) 3. Progression of design and feasibility work for a redevelopment at Bedford Road in line with the vision set out in the Allies and Morrison town centre masterplan (£400,000) 4. Progression of further feasibility work to redesign the Guildford gyratory system (£120,000) 5. A platform capacity study to inform improvements and a development brief for Guildford Railway Station (£150,000) 6. Increase in costs relating to waste and recycling (£286,000) 7. Increase in playground repairs and maintenance (£60,000) 8. Provision for the loss of various grant funding from Surrey County Council (£455,000) 9. Additional procurement officer resources (£35,000)

In addition, the budget makes provision for the cost of the new apprenticeship levy on large employers of £135,000 and £60,000 to meet the increased requirements of the Data Protection Act.

The Chief Finance Officer’s (CFO) report is included at Appendix 1. This gives information about the strategic context within which our budget has been prepared, the medium term financial plan, the robustness of the estimates, adequacy of reserves and budget risks.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Business Planning: General Fund Budget 2017-18Report 317 KB DownloadRead as text
PDF
Item 09 (1): General Fund Budget 2017-18: App 1: CFO reportAppendix 575 KB Download
PDF
Item 09 (2): General Fund Budget 2017-18: App 2: Medium Term Financial StrategyAppendix 123 KB Download
PDF
Item 09 (3): General Fund Budget 2017-18: App 3: GF SummaryAppendix 126 KB Download
PDF
Item 09 (4): General Fund Budget 2017-18: App 4: Bid SummaryAppendix 122 KB Download
PDF
Item 09 (5): General Fund Budget 2017-18: App 5: Fees and ChargesAppendix 718 KB Download

At this meeting

Whole meeting

Who was there

9 of 23 attended
PS
Councillor Paul SpoonerChairperson, present
MF
Councillor Matt FurnissVice-Chairperson, present
DB
Councillor David BilbéCommittee Member, present
RB
Councillor Richard BillingtonCommittee Member, apologies
GD
Councillor Geoff DavisCommittee Member, present
GE
Councillor Graham EllwoodCommittee Member, present
MI
Councillor Michael IllmanCommittee Member, present
NN
Councillor Nikki Nelson-SmithCommittee Member, present
IR
Councillor Iseult RocheCommittee Member, present
TR
Councillor Tony RoothCommittee Member, present
SS
Sue SturgeonOfficer, expected
JW
James WhitemanOfficer, expected

All 23 on the meeting page

On this subject at Guildford

Search all
  1. Business Planning - General Fund Budget 2017-18This decision
  2. General Fund outline budget 2021-22 and Business Planning 2021-22 to 2024-25Approved
  3. Business and Planning Act for the Licensed TradeApproved
  4. Business Planning - General Fund Outline Budget 2020-21Approved
  5. Business Planning - General Fund Outline Budget 2020-21Agreed
  6. Business Planning - General Fund Budget 2019-20Approved

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies