(1) That the sum of £835,000 be transferred from the provisional General Fund Capital Programme to the approved General Fund Capital Programme in respect of the Castle Street/ Tunsgate public realm scheme. (2) That the Director of Environment be authorised, in consultation with Lead Councillor for Infrastructure and Governance, to make all necessary arrangements and enter into any relevant agreements to deliver the scheme. Reason for To enable the scheme for public realm enhancements in Tunsgate to proceed. Alternative options considered and rejected by the Executive: None Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None To enable the scheme for public realm enhancements in Tunsgate to proceed.
Word for word from the decision Guildford published for this meeting.Source: democracy.guildford.gov.uk
Executive Report Ward(s) affected: Holy Trinity Report of Director of Environment Author: Gaurav Choksi Tel: 01483 444515 Email: [email protected] Lead Councillor responsible: Matt Furniss Tel: [phone removed] Email: [email protected] Date: 18 July 2017
Tunsgate Public Realm Scheme: Approval of Capital Funding Executive Summary
The Council is promoting a scheme for public realm enhancements in Tunsgate in Guildford town centre. The proposed scheme involves pedestrianisation of Tunsgate for the majority part of the day. This will complement the private sector investment in the area and contribute towards regeneration of this part of the town.
The project supports the aims and objectives of the Council to regenerate the town centre and to improve accessibility and pedestrian environment. The project is included in the Council’s draft capital programme, with a budget of £2,000,000 for a wider scheme covering Castle Street, Tunsgate and Chapel Street.
Tunsgate is phase one of the wider scheme. The current estimated cost is £835,000. This report requests approval to transfer £835,000 from the provisional capital programme to the approved capital programme.
Recommendation to Executive
(1) That the sum of £835,000 be transferred from the provisional General Fund Capital Programme to the approved General Fund Capital Programme in respect of the Castle Street / Tunsgate public realm scheme (2) That the Director of Environment be authorised, in consultation with Lead Councillor for Infrastructure and Governance, to make all necessary arrangements and enter into any relevant agreements to deliver the scheme.
Reason for Recommendation: To enable the scheme for public realm enhancements in Tunsgate to proceed. 1. Purpose of Report
1.1The report sets out the background to the proposed public realm enhancement scheme in Tunsgate.
1.2The public realm enhancements in Castle Street, Tunsgate and Chapel Street are included in the Council’s provisional capital programme, with a budget of £2,000,000.
1.3Tunsgate is phase one of the wider scheme covering the Castle Street, Tunsgate and Chapel Street. The current estimated cost for the Tunsgate scheme is £835,000.
1.4This report requests approval to transfer £835,000 from the provisional capital programme to the approved capital programme.
1.5It is important that the funding is approved to enable the works to take place in a phased approach, if practical starting this year with footways on both sides in line with the reopening of Tunsgate Quarter.
2. Strategic Priorities
2.1The public realm enhancements in Tunsgate deliver on the following key strategic priorities:
2.2Our Borough: The public realm enhancements in Tunsgate will assist in the delivery of the Council’s strategic priorities to create an attractive, competitive, multi-faceted and vibrant town with improved accessibility and pedestrian environment.
2.3Our Economy: The proposed scheme will complement the private sector investment in the area, support the increase in footfall in the area and add to the vitality of this part of the town. Increased levels of walking to and around the town centre will have a positive effect on the local retail economy as some recent studies suggest that pedestrians and cyclists actually spend more on a trip into a town than a motorist.
2.4Our Infrastructure: The scheme will make the area more attractive.
2.5Our Environment: Increased walking and cycling, where it replaces motorised forms of transport such as the car, will improve air quality and reduce carbon emission levels. The new street lighting will be low energy warm-tone LED which will result in energy reduction.
2.6Our Society: Increased walking and cycling has a positive impact on the health of a person. The emerging Surrey Health and Well-being Strategy has identified obesity as one of the priority public health challenges. 3. Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.