Tunsgate Public Realm Scheme - Approval of Capital Funding

Approved Executive 3 papers

Executive approved this item on Tuesday 18 July 2017. Below is the council's own wording, with the papers it was decided on.

ItemEX30

Resolved

(1) That the sum of £835,000 be transferred from the provisional General Fund Capital Programme to the approved General Fund Capital Programme in respect of the Castle Street/ Tunsgate public realm scheme. (2) That the Director of Environment be authorised, in consultation with Lead Councillor for Infrastructure and Governance, to make all necessary arrangements and enter into any relevant agreements to deliver the scheme. Reason for To enable the scheme for public realm enhancements in Tunsgate to proceed. Alternative options considered and rejected by the Executive: None Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None To enable the scheme for public realm enhancements in Tunsgate to proceed.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Executive Report Ward(s) affected: Holy Trinity Report of Director of Environment Author: Gaurav Choksi Tel: 01483 444515 Email: [email protected] Lead Councillor responsible: Matt Furniss Tel: [phone removed] Email: [email protected] Date: 18 July 2017

Tunsgate Public Realm Scheme: Approval of Capital Funding Executive Summary

The Council is promoting a scheme for public realm enhancements in Tunsgate in Guildford town centre. The proposed scheme involves pedestrianisation of Tunsgate for the majority part of the day. This will complement the private sector investment in the area and contribute towards regeneration of this part of the town.

The project supports the aims and objectives of the Council to regenerate the town centre and to improve accessibility and pedestrian environment. The project is included in the Council’s draft capital programme, with a budget of £2,000,000 for a wider scheme covering Castle Street, Tunsgate and Chapel Street.

Tunsgate is phase one of the wider scheme. The current estimated cost is £835,000. This report requests approval to transfer £835,000 from the provisional capital programme to the approved capital programme.

Recommendation to Executive

(1) That the sum of £835,000 be transferred from the provisional General Fund Capital Programme to the approved General Fund Capital Programme in respect of the Castle Street / Tunsgate public realm scheme (2) That the Director of Environment be authorised, in consultation with Lead Councillor for Infrastructure and Governance, to make all necessary arrangements and enter into any relevant agreements to deliver the scheme.

Reason for Recommendation: To enable the scheme for public realm enhancements in Tunsgate to proceed. 1. Purpose of Report

1.1The report sets out the background to the proposed public realm enhancement scheme in Tunsgate.

1.2The public realm enhancements in Castle Street, Tunsgate and Chapel Street are included in the Council’s provisional capital programme, with a budget of £2,000,000.

1.3Tunsgate is phase one of the wider scheme covering the Castle Street, Tunsgate and Chapel Street. The current estimated cost for the Tunsgate scheme is £835,000.

1.4This report requests approval to transfer £835,000 from the provisional capital programme to the approved capital programme.

1.5It is important that the funding is approved to enable the works to take place in a phased approach, if practical starting this year with footways on both sides in line with the reopening of Tunsgate Quarter.

2. Strategic Priorities

2.1The public realm enhancements in Tunsgate deliver on the following key strategic priorities:

2.2Our Borough: The public realm enhancements in Tunsgate will assist in the delivery of the Council’s strategic priorities to create an attractive, competitive, multi-faceted and vibrant town with improved accessibility and pedestrian environment.

2.3Our Economy: The proposed scheme will complement the private sector investment in the area, support the increase in footfall in the area and add to the vitality of this part of the town. Increased levels of walking to and around the town centre will have a positive effect on the local retail economy as some recent studies suggest that pedestrians and cyclists actually spend more on a trip into a town than a motorist.

2.4Our Infrastructure: The scheme will make the area more attractive.

2.5Our Environment: Increased walking and cycling, where it replaces motorised forms of transport such as the car, will improve air quality and reduce carbon emission levels. The new street lighting will be low energy warm-tone LED which will result in energy reduction.

2.6Our Society: Increased walking and cycling has a positive impact on the health of a person. The emerging Surrey Health and Well-being Strategy has identified obesity as one of the priority public health challenges. 3. Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 06 (1): Tunsgate Public Realm Scheme: App 1: plan (northern end)Appendix 131 KB Download
PDF
Item 06 (2): Tunsgate Public Realm Scheme: App 2: plan (southern end)Appendix 127 KB Download
PDF
Tunsgate Public Realm Scheme: Approval of Capital FundingReport 173 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 26 attended
PS
Councillor Paul SpoonerChairperson, present
MF
Councillor Matt FurnissVice-Chairperson, present
DB
Councillor David BilbéCommittee Member, apologies
RB
Councillor Richard BillingtonCommittee Member, present
PB
Councillor Philip BrookerCommittee Member, present
GD
Councillor Geoff DavisCommittee Member, present
GE
Councillor Graham EllwoodCommittee Member, present
MI
Councillor Michael IllmanCommittee Member, present
NN
Councillor Nikki Nelson-SmithCommittee Member, apologies
IR
Councillor Iseult RocheCommittee Member, present
TC
Tracey ColemanOfficer, expected
PO
Philip O'DwyerOfficer, expected

All 26 on the meeting page

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies