(1) That the work undertaken to date be noted and that the project be progressed to RIBA stage 4 . (2) That officers explore external funding options, including the National Lottery Heritage Fund. (3) That a fundraising officer be appointed . (4) That the sum of £1,200,000 be transferred from the provisional capital programme to the approved capital programme to fund the required work. (5) That the Director of Environment, in consultation with the Lead Councillor for Skills, Arts and Tourism, Lead Councillor for Finance and Asset Management and Director of Finance, be authorised to review the existing contracts for external consultants and either re-negotiate or re-procure them in order to ensure best value for money. Reason: To progress further the architectural and technical designs, surveys, audience development programme, submission of planning and grant funding applications. Alternative options considered and rejected by the Executive: A. Undertake minimal refurbishment of the existing project within existing capital budget B. Deliver a phased project which still requires external match funding but a reduced scale of development Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None
Word for word from the decision Guildford published for this meeting.Source: democracy.guildford.gov.uk
Executive Report Ward(s) affected: Holy Trinity Report of Director of Environment Author: Paul Bassi, Tel: 01483 444515 Email: [email protected] Lead Councillor responsible: Nikki Nelson-Smith Tel: 01483 568554 Email: [email protected] Date: 19 March 2019
Guildford Museum development project – update Executive Summary
The museum project is a step change and forward-thinking transformational project of substantial scale and influence that will make a significant positive contribution to Guildford’s attraction as place to live, work, play and be creative.
The proposed landmark new build extension and refurbishment of the existing museum buildings will create a destination hub for Guildford’s cultural and leisure offer, showcasing prestigious national events and exhibitions as well as celebrating Guildford’s own past and its contribution to innovation globally, notably the digital and satellite industry.
The impact of similar museums and other cultural institutions has demonstrated the boost they give to local economies; generating greater spend by visitors, increasing employment and providing a catalyst to grow creative industries and support existing businesses. The proposed museum is estimated to contribute £2.4million GVA per annum to the local economy.
Through modernised programmes of activities, the museum will be more financially sustainable and resilient. The range of additional income-generating activities includes a welcoming café that will link the Museum to the Castle grounds and events that will draw new audiences with extended opening hours.
In 2016/17 museum visitor numbers fell to 9,642. This demonstrates the need to radically change what we offer to enable Guildford to live up to its status as the county town of surrey. If completed to our expectations, 70,000 visitors per year is a realistic estimate of what we could expect post completion.
With an emphasis on greater partnership and collaboration, Guildford’s businesses, other cultural attractions, educational institutions and the third sector will play an integral part of the overall offer. The museum will provide a hub for art and heritage attractions both within and beyond Guildford. Partners such as the Carollian Wonderland Trust, Surrey Archaeological Society and Surrey Infantry Museum will all provide greater depth and interest to the museum offer.
Work to date has focused on the development of Guildford Museum’s vision, audience development, display interpretation and architectural design options and has involved specialist, external experts such as ZMMA (architectural designs and Interpretation Planning), Julia Holberry Associates (audience development and activity planning), and Fourth Street (business planning).
Following previous work to identify the best site, a new build extension within the courtyard of the Museum is proposed. This will re-orientate the Museum towards the Castle and town centre and provide a unique opportunity to consolidate and draw on the attraction of the Castle. The site does however present a challenge due to its access, sensitive historic setting and topography. As such, the cost estimate has taken account of these factors.
The Council has already allocated £6.5million in its provisional budget.. This would be insufficient to meet council’s aspiration however and external funding will be required. Seeking additional funding is a conventional approach adopted by councils and cultural organisations for projects of this nature and scale. The current budget provided does presents a good level to offer as match funding.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.