That the transfers to/from reserves, as set out in Section 8 and Appendix 2 of the report submitted to the Executive be approved. 2. That the growth and savings items included in the General Fund Summary at Appendix 2 and set out in detail in Appendix 3 to the report be approved. 3. That the savings identified in the updated savings strategy at Appendix 4 to the report, to be delivered over the medium-term plan period, be approved. 4. That the financial risk register set out in Appendix 5 to the report be approved, and that the Executive notes that level of reserves are currently sufficient to meet the Council’s risks. The Executive made the following recommendations to Council (9 February 2022): 1. That the budget, as set out in the General Fund Summary in Appendix 2 to the report be approved, and specifically that the Council Tax requirement for 2022-23 be set at £ 10,898,310. 2. That the proposed fees and charges for 2022-23 relating to General Fund services and attached at Appendix 6 to the report be adopted with effect from 1 April 2022. 3. That the Band D Council Tax for 2022-23 be set at £186.82, an increase of £5 (2.75%) Reason: To enable the Council to set the Council Tax requirement and council tax for the 2022-23 financial year. Other options considered and rejected by the Executive: None. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting.Source: democracy.guildford.gov.uk
This report outlines the proposed budget for 2022-23, which includes a Council Tax requirement of £10,898,310 and a Council Tax increase of £5 per year (2.75%), resulting in a Band D charge of £186.82. As set out in the report, the Council is required to set a balanced budget for 2022-23.
We received the provisional Local Government Finance Settlement (LGFS) for 2021-22 on 16 December 2021. The figures included in the budget presented reflect the information contained in the settlement.
The Settlement Funding Assessment (SFA) consists of the local share of business rates, and revenue support grant and is set out in the provisional LGFS. The settlement enables us to retain £2.929 million of business rates in 2022-23 the same amount as we retained in 2021-22 and 2020-21. Core Spending Power has increased to £15million, within the core spending power calculation, the Government has assumed that we will raise the Council Tax by the maximum amount (£5 or 2% whichever is the higher).
Overall, the LGFS was positive for the Council as it included additional funding of £240,000 grant to compensate the Council for the Business Rates Multiplier not increasing in line with inflation £131,000 lower tier services grant (this grant was £237,000 in 2021-22 but was meant to have been a one-off grant) £202,000 services grant which is a one-off grant for 2022-23 (to partly offset the National Insurance increase) £766,000 New Homes Bonus grant for 2022-23 only The ability to raise council tax by a maximum of £5 (2.75%) rather than 2.0%, this additional increase will generated a further £86,000 in council tax income The Joint Executive Advisory Board (JEAB) considered the outline budget at its meeting held 11 November 2021. The Executive approved the Outline Budget on 23 November 2021.
The Chief Finance Officer’s statutory report is included at Appendix 1. This gives information about the strategic context within which our budget has been prepared, the medium term financial plan, the robustness of the estimates, adequacy of reserves and budget risks. Appendix 2 provide the General Fund Summary showing a balanced budget for 2022-23 but that the Council has a budget gap of £1.5million in 2023-24 which will rise to £3.3million by 2025-26. Appendix 3 shows the budget movement summary of growth and savings which have been included in the General Fund Summary. Appendix 4 details progress made against the Council’s Savings Strategy. Appendix 5 details the financial risk register, Council is asked to note that the level of reserves are currently sufficient to meet the Council’s risks.
The financial monitoring report for the first eight months of 2021-22 was reported to the Corporate Governance and Standards Committee on 20 January 2022. The projected net expenditure on the General Fund for the current financial year is estimated to be £0.2million less than the original estimate due mainly to actions undertaken as part of the voluntary non-essential expenditure freeze which was put in place a previously projected overspend due to the on-going impact of the COVID19 pandemic. Any ongoing variances between actual expenditure and budget identified in 2021-22 have been taken into account when preparing the budget for 2022-23.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.