To note the updated MTFP position and the further work ongoing to produce a balanced budget for 2024-25. Recommendation (to Council: 5 December 2023) That the proposed changes to the Approved and Provisional Capital Programmes, as set out in Appendix 1 to the report, be approved. Reasons: To enable the Council to protect the current level of reserves and to set a balanced budget and a robust Medium-Term Financial Plan.
Word for word from the decision Guildford published for this meeting.Source: democracy.guildford.gov.uk
Guildford Borough Council Report to: Executive Date: 23 November 2023 Ward(s) affected: All Report of Director: Ian Doyle, Transformation and Governance Author: Richard Bates, Executive Head of Finance Tel: 01483 444026 Email: Your email [email protected] Lead Councillor responsible: Richard Lucas (Finance and Property), Julia McShane (Leader) Email: [email protected] Report Status: Open
Medium Term Financial Plan (MTFP) and Financial Recovery Plan – November Update Report 1. Executive Summary 1.1. The Council agreed the 2023-24 budget in February 2023 with a £3.3m shortfall requiring further work to remove this gap, with the fallback position being the deployment of usable reserves.
1.2An updated MTFP position was presented to the Council in July 2023 which set out the key issues and the position in which the Council was now left. In summary this was a remaining in-year deficit of £1.7m and a budget gap of £18.3m over the MTFP period to 2026-27.
1.3A Financial Recovery Plan was presented to Council in August and updated in October. This set out the immediate and medium-term actions being taken to address both the in-year and medium-term budget gaps.
1.4In October, the Interim s151 officer concluded that sufficient progress had been made to avoid the need for a s114 report to be issued but that significant work was still required to produce a balanced budget for 2024-25 and beyond.
1.5This report updates on the MTFP position, potential funding changes, and progress on the Recovery Plan workstreams.
1.6The report also sets out the outcome of the review of the Capital Programme. If approved, this will remove £96.6m from the Approved and Provisional programmes which will reduce the Council’s projected borrowing needs.
1.7Section 9 of the report gives a high-level update on the potential remaining budget gap to be addressed and the actions ongoing to address this. The work to date on the Financial Recovery Plan has reduced the July MTFP gap of £18.3m by £9m to £7.3m.
1.8Although excellent progress has been made, significant further work is still required to produce a balanced budget for 2024-25.
2. Recommendation to Executive That the Executive:
2.1Notes the updated MTFP position and the further work ongoing to produce a balanced budget for 2024-25.
2.2Recommends to Council (5 December 2023) that the proposed changes to the Approved and Provisional Capital Programmes set out in Appendix 1 be approved.
3. Reason for Recommendation: 3.1 To enable the Council to protect the current level of reserves and to set a balanced budget and a robust Medium-Term Financial Plan. 4. Exemption from publication 4.1. None
5. Purpose of Report 5.1. This report sets out the progress to date in addressing the MTFP budget gap through the workstreams established as part of the Council’s Financial Recovery Plan.
5.2The report details the output from the workstream dealing with reviewing the Council’s capital programme and recommends a revised programme for approval.
6. Strategic Priorities 6.1. The budget underpins the Council’s strategic framework and delivery of the Corporate Plan.
7. Background 7.1. The Council agreed the MTFP in February 2023 but with further work required at that stage to remove the need for reserves and balances to be used to close the in-year budget gap.
7.2A number of issues were identified during the audit of the 2020-21 statement of accounts which led to the usable reserves of the Council being restated at a level of around £20 million less than previously reported. Significant due diligence work was undertaken to establish the baseline position and an updated General Fund budget was presented to Council in July 2023. This set out the gravity of the financial position and raised the possibility of the Council issuing a s114 report if insufficient action was taken.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.