CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Guildford Borough Council
Executive, Thursday 23 November 2023 at 6.00pm

Capital and Investment Outturn Report 2022-23

Noted Executive 6 papers

Executive noted this item on Thursday 23 November 2023. Below is the council's own wording, with the papers it was decided on.

ItemEX37

Resolved

Recommendation (to Council: 5 December 2023) (1) That the capital and investment outturn report be noted. (2) That the actual prudential indicators reported for 2022/23, as detailed in Appendix 1 to the report, be approved. Reasons: 1. To comply with the Council’s treasury management policy statement, the Chartered Institute of Public Finance and Accountancy (CIPFA) Code of Practice on treasury management and the CIPFA Prudential Code for Capital Finance in Local Authorities. 2. As per the treasury management code although the scrutiny of treasury management (and indeed all finance) has been delegated to the Corporate Governance & Standards Committee, ultimate responsibility remains with full Council, this report therefore fulfils that need. Other options considered and rejected by the Executive: None. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Guildford Borough Council Report to: Executive Date: 23 November 2023 Ward(s) affected: All Report of Director: Transformation & Governance Author: Vicky Worsfold, Lead Specialist Finance and Deputy CFO Tel: 01483 444834 Email: [email protected] Lead Councillor responsible: Richard Lucas Tel: [phone removed] Email: [email protected] Report Status: Open

Capital and Investment outturn report 2022/23 1. Executive Summary

1.1This outturn report includes capital expenditure, non-treasury investments and treasury management performance for 2022/23 financial year.

Capital programme

1.2In total, expenditure on the General Fund capital programme was £35.4 million against the original budget of £158 million, and a revised1 budget of £169 million. Details of the revised estimate and

1 Revised budget being the budget approved at Council in February plus any unspent amounts brought

forward from previous financial year and supplementary estimates. actual expenditure in the year for each scheme is included at Appendix 3.

1.3The budget for Minimum Revenue Provision (MRP) was £1.5 million and the outturn was £1.38 million. This was due to slippage in the programme in 2021/22.

1.4Officers have reviewed the programme and have determined that there are schemes that are no longer required, that no longer meet the original business case or have been removed pending a new business case in light of the Council’s ongoing budget deficit. These schemes are detailed in the Financial Recovery Plan within the capital programme workstream. Removing these schemes will reduce the Council’s underlying need to borrow for capital purposes and will generate a saving to the revenue account in respect of MRP and interest.

Non-treasury investments

1.5The Council’s investment property portfolio stood at £178 million at the end of the year. Our rental income was £9.5 million, and our income return 5.7% against the benchmark of 4.7%.

Treasury management

1.6The Council’s cash balances have built up over several years and reflect our strong balance sheet with considerable revenue and capital reserves in the HRA. Officers carry out the treasury function within the parameters set by the Council each year in the capital and investment strategy. On 31 March 2023, the Council held £98 million in investments, £295 million in borrowing, of which £147 million is HRA, £32 million relates to the Weyside Urban Village project (WUV), and £115 million of short term borrowing, so net debt of £197 million.

1.7We borrowed short-term from other local authorities for cash flow purposes in the year and took out a loan for WUV under the infrastructure rate. We capitalise borrowing interest to capital schemes using the pooled interest rate of the Council, so whether we are borrowing short or long term the borrowing associated with the capital programme expenditure is capitalised against the project and not charged to the GF as interest payable.

1.8The report (section 8) confirms that the Council complied with its prudential indicators, treasury management policy (TMP) statement and treasury management practices for 2022/23. The policy statement is included and approved annually as part of the Capital and investment Strategy and the TMPs are approved under delegated authority.

1.9Treasury management performance compared to estimate for the year is summarised in the table below. The report highlights the factors affecting this performance throughout the report and in Appendix 1. Estimate Actual Estimate Actual % % (£000) (£000) General fund Capital Financing 245,861 175,204 Requirement (CFR) Housing Revenue Account CFR 217,024 199,204 Total CFR 462,885 374,408

Return on investments 1.69 1.62 1,278 1,900 Interest paid on external debt 5,987 5,471 Total net interest paid 4,709 3,571

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital and Investment Outturn Report 2022-23Report 167 KB DownloadRead as text
PDF
Item 10 (1): C&I Outturn Report: App 1: TM Activity and Treasury & Prudential IndicatorsAppendix 179 KB Download
PDF
Item 10 (2): C&I Outturn Report: App 2: Fund Report 22-23Appendix 1.5 MB Download
PDF
Item 10 (3): C&I Outturn Report: App 3: Capital schemesAppendix 443 KB Download
PDF
Item 10 (4): C&I Outturn Report: App 4: Schedule of investments at 31 March 2023Appendix 100 KB Download
PDF
Item 10 (5): C&I Outturn Report: App 5: Economic Review March 23Appendix 59 KB Download

At this meeting

Whole meeting

Who was there

8 of 20 attended
JM
Councillor Julia McShaneChairperson, present
TH
Councillor Tom HuntVice-Chair, present
AG
Councillor Angela GoodwinCommittee Member, present
CH
Councillor Catherine HoustonCommittee Member, present
RL
Councillor Richard LucasCommittee Member, present
CM
Councillor Carla MorsonCommittee Member, present
GP
Councillor George PotterCommittee Member, present
MR
Councillor Merel Rehorst-SmithCommittee Member, present
DB
Councillor Dawn BennettGuest, in attendance, virtual
RB
Councillor Ruth BrothwellGuest, in attendance, virtual
JW
Councillor James WalshGuest, in attendance, virtual
FW
Councillor Fiona WhiteGuest, in attendance, virtual

All 20 on the meeting page

On this subject at Guildford

Search all
  1. Capital and Investment Outturn Report 2022-23This decision
  2. Capital and Investment Strategy 2024/25 - 2028/29Approved
  3. Capital and Investment Strategy (2023-24 to 2027-28)Approved
  4. Capital and Investment outturn report 2021-22Approved
  5. Capital and Investment Strategy (2022-23 to 2026-27)Approved
  6. Capital and Investment outturn report 2020-21Approved

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open