To authorise the entering into of a contract for the appointment of NEC Supervisors with a financial cap of £2 million pounds for a term of 4 years; and 2. To delegate to the Joint Strategic Director for Finance authority to enter into call-off contracts of any value under this contract in consultation with the Portfolio Holder if it is a Key Decision. Reason(s): It will save time and resources for the Council to undertake a single procurement exercise and award a contract enabling services to be called off as and when required for individual projects. Other options considered and rejected by the Executive: None. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting.Source: democracy.guildford.gov.uk
3.1It will save time and resources for the Council to undertake a single procurement exercise and award a contract enabling services to be called off as and when required for individual projects.
4.0Status of Report
Open
5.0Strategic Priorities
5.1A resilient and well managed Council as the consideration of the contracts being procured provides best value and use of council resources.
Background
6.1The Council is in the process of procuring a contract for an NEC Supervisor (see below for further details) which can be utilised by a) the WUV Project; b) the Council as a whole as and when required during the lifetime of the contract. There will be a spend cap on the contract of £2 million over the term of contract allowing for multiple projects to utilise the contract.
6.2The New Engineering Contract (NEC) essentially provides a suite of contracts that can be used for construction and engineering projects. As part of the WUV Project, the Council has entered into a number of NEC Contracts. This particular contract is for an NEC Supervisor which is a contract required to appoint a specific Consultant (Supervisor) to manage and monitor the works being carried out under NEC Contracts. 6.3 The process for appointing Ross Quality was via a direct award on the Pagabo NEC Supervisor Framework. They are the top ranked supplier for quality and cost.
6.4Whilst this contract is intended to be utilised by the Council generally, the WUV Project currently has two NEC Contracts in existence which require an NEC Supervisor to be put in place imminently as the works in the main NEC Contracts are due to start and as such it was impracticable to publish a Notice of Key Decision in the Forward Plan in order to comply with the statutory 28 days’ notice requirement.
Options
7.1If we do not enter into a contract, the Council will not have any one in place to monitor or manager the NEC contracts it enters. This presents a significant risk to the Council given the nature and requirements of NEC contracts.
7.2The contract is awarded enabling NEC Supervisors to be appointed as and when necessary. This will provide appropriate oversight, management and monitoring on the Council’s NEC contracts without the need for multiple procurements and therefore it saves time and money.
Consultation
8.1Consultation was sought with Procurement and Legal services prior to and during the procurement process.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.