To enter a one year contract with an anticipated approximate value of £700,000 with Kincraig Construction Limited. Reason(s): To enable the council to undertake and manage the refurbishment of void properties so that these can be relet. Other options considered and rejected by the Executive: Not to enter the contract which present a significant risk to the council until the longer term procurement exercise can be undertaken. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting.Source: democracy.guildford.gov.uk
To enable the council to undertake and manage the refurbishment of void properties so that these can be relet.
4.0Status of Report
Open
5.0Strategic Priorities
This contract supports the council’s strategic priorities for decent and affordable homes and a resilient and well managed council.
Background
6.1The strategy for the re-procurement of a suitably qualified contractor to undertake refurbishment works of void properties involves both a short term and long term plan. It is recognised that this is an essential contract and therefore it was recommended that a one year contract was procured quickly to enable time for a longer term procurement exercise to be completed. This will enable time for a robust and thorough procurement exercise to be completed for a longer term contract.
6.2The council went out to the market for the one year contract through a quote process and three suppliers were approached and asked to submit against the council’s specification in accordance with the tender documentation. This was in accordance with the council’s procurement procedure rules. The tender went out at the beginning of June and submissions were requested by 21 June 2024 as it was recognised that this in a key contract in delivery of our housing services. SS / J-SCS-065 / 00945327 / Version : Page 2 6.2 The proposed contract form is an industry standard JCT Measured Term Contract which provides for the call-off of works as and when required. The contract has been amended to include terms and conditions specific to the council and includes provisions in relation to contract management.
6.3The council received two tender returns and these were evaluated by two Housing Technical Services Officers in accordance with the criteria published in the tender documentation. The standstill period commenced on 18 July 2024 following completion of the evaluation. The standstill period expired on 29 July 2024 and the council was then able to proceed with contract finalisation for the award.
6.4This contract forms part of the response to the housing fraud investigation and needs to be completed as a matter of urgency so that the council can resume a structured plan of refurbishments works on void properties.
Options
7.1Not to enter the contract which present a significant risk to the council until the longer term procurement exercise can be undertaken.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.