Guildford Borough Council
Executive, Thursday 17 July 2025 at 6.00pm

HRA Fire Doors Programme

Noted Executive

Executive noted this item on Thursday 17 July 2025. Below is the council's own wording, with the papers it was decided on.

ItemEX37

Resolved

Note the overspend of £1.6m against the approved original contract estimate of £2.5m. 2. Note an additional committed spend of £0.8m within the original contract, which will take the total spend on the contract to £4.9m. 3. Note the budget allocation was £3.6m and therefore an overspend on the existing fire door programme budget of £0.5m has occurred. 4. Subject to full Council approving the additional budget of £2.4m to approve the award of a new contract to Shellen through the Pretium Framework agreement delivered through Hyde in order to complete the remaining programme of fire door installation. This will cover the £1.6m remaining programme and the £0.8m works committed under the old contract but not yet complete. 5. Note the intention of the Strategic Director for Housing, Communities & Environment to agree to provide doors, at the Council’s expense, to the 50 leasehold properties in the Council’s four high rise blocks, with an estimated cost of £125,000 in line with para 3.6 below; and 6. That the Executiverecommend that full Council (meeting on 29 July 2025) resolve to: ( i ) Note the overspend of £0.5m against the approved budget and authorise the Chief Financial Officer to make any necessary changes to the HRA capital programme budget; and (ii) Approve a capital budget of £2.4m to complete the fire door programme over the next two years. Reason(s): 1. Failure to complete the installation of fire doors will leave the residents and Council potentially at risk. The doors and frames being replaced are certified fire doors which will protect residents in the event of a fire. The current doors are not fire certified and cannot be confirmed as compliant with current fire regulations. Appendix 1 sets out the duties and potential breaches the Council as the accountable body, could face if the doors are not replaced. 2. A direct award to Shellen would prevent further delays in completing the programme. Completing the door programme with a single provider will allow standardisation of doors, which will provide continuity of service and doors across the housing portfolio. 3. In addition, the recommendation to direct award would provide value for money. The contractor priced the original tender in early 2022 and prices have increased by 16% through annual inflation and demand. This would equate to £256k saving on the £1.6m remainder of the programme vs a new contract. Shellen have confirmed if awarded the direct contract for the remainder of the door programme they will stand by the original pricing. 4. Pretium have confirmed a direct award can be made to Shellen through the Pretium framework managed by Hyde. The Procurement team have also confirmed they approve this route. 5. Members are asked to note the overspend of the approved budget and that this, and the contractual overspend, will be referred to the Audit & Risk Committee for their consideration. 6. The provision of doors on leasehold properties in high rise buildings will provide assurance that all doors are compliant, to protect ... EX37
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

Papers for this item

Kept in our archive, download once signed in

No papers were published with this item. The decision above is the council's full record of it.

At this meeting

Whole meeting

Who was there

6 of 9 attended
JM
Councillor Julia McShaneChairperson, present
TH
Councillor Tom HuntVice-Chair, present
AG
Councillor Angela GoodwinCommittee Member, apologies
CH
Councillor Catherine HoustonCommittee Member, present
RL
Councillor Richard LucasCommittee Member, apologies
CM
Councillor Carla MorsonCommittee Member, present
MR
Councillor Merel Rehorst-SmithCommittee Member, present
FW
Councillor Fiona WhiteCommittee Member, present
AC
Councillor Amanda CreeseGuest, in attendance, virtual

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies