Guildford Borough Council
Executive, Thursday 17 July 2025 at 6.00pm

Weyside Urban Village Development

Agreed Executive 1 paper

Executive agreed this item on Thursday 17 July 2025. Below is the council's own wording, with the papers it was decided on.

ItemEX42

Resolved

Notes the current financial position of WUV at the 2025 Financial Review, outlined in Exempt Appendix 2. 2. Notes the forecast deficit - outlined in Exempt Appendix 1. 3. Delegates to the Strategic Director of Economy, Planning and Place, in consultation with the Lead Councillor for Economy and Place and Lead Councillor for Finance, authority to enter into such other contracts and legal agreements connected with Weyside Urban Village as may be necessary [1] to deliver the programme in compliance with Contract Procedure Rules, the Council’s Constitution and within the approved budget. Reason(s): 1. To ensure that there is sufficient understanding of the projected financial forecast of the programme and specifically, to highlight the worsened forecast deficit position. 2. To ensure that statutory service agreements and construction agreements can be entered into for the delivery of services and infrastructure for the development and to ensure that Homes England Housing Infrastructure Fund (HIF) milestones are achieved. 3. To support the delivery of the Council’s Corporate Strategy (2024-2034) priorities, by unlocking the high-quality development of a strategic site, creating employment opportunities through regeneration and facilitating affordable housing. Other options considered and rejected by the Executive: Option 1. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None. [1] ....as may be necessary to deliver the programme, in compliance etc. Would be a slightly better recommendation.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Guildford Borough Council Report to: Executive Date: 17 July 2025 Ward(s) affected: Bellfields and Slyfield Report of Director: Economy, Planning and Place Author: Abi Lewis, Assistant Director of Regeneration & Economic Development Tel: 01483 444908 Email: [email protected] Lead Councillor responsible: Cllr Tom Hunt Tel: [phone removed] Email: [email protected] Report Status: Part Exempt (Appendices)

Weyside Urban Village Development 1. Executive Summary 1.1 Weyside Urban Village ("WUV") is a major 41-hectare brownfield regeneration scheme that Guildford Borough Council (the "Council") anticipates could deliver approximately 1,500 homes across a range of tenures, as well as 2,000 square metres of community space and 6,500 square metres of employment space.

1.2Over 44 percent of the site is currently in Council ownership, and 100 percent will be achieved on completion of land transfers with Thames Water Utilities Ltd (“TWUL”). The conditional contract with TWUL was signed on 25 April 2019 (the "TW Agreement").

1.3In February 2020, the Council committed £334.9 million to de-risk the infrastructure and site assembly process needed across the Weyside Urban Village site. In conjunction with its own financial commitment, the Council has also secured and benefited from substantial grant funding from Homes England’s Housing Infrastructure Fund (HIF) of £52.3m and Local Enterprise Partnership (LEP) funding of £8m, with grant draw down in alignment with the implementation of the infrastructure.

1.4As part of the overarching governance of the Weyside programme, this report is presented to the Executive, outlining the forecast financial position of the scheme and high-level progress achieved.

1.5The broader macro-economic landscape and its impact on the construction industry over the last 24 months has been profound. At the end of 2021, the Building Cost Information Service (BCIS) - which provides cost and price data for the UK construction industry - reported that the annual growth in its material cost index reached a forty-year high. Since then, pressures on supply chains have persisted and labour shortages have become more acute. Although the lifting of Covid restrictions led to a return of high activity levels, the war in Ukraine and high rates of inflation have put the construction industry in further turmoil. The impact of these issues is being felt at a local level, albeit construction costs have stabilised somewhat yet financing costs have increased significantly.

1.6This report sets out the current financial forecast to the end of the programme, which provides the background for the mitigation strategy to address the potential financial deficit that has arisen resulting from increased borrowing costs and the macro-economic factors referred above.

2. Recommendation to Executive That the Executive:

2.1Notes the current financial position of WUV at the 2025 Financial Review, outlined in Exempt Appendix 2.

2.2Notes the forecast deficit - outlined in Exempt Appendix 1.

2.3Delegates to the Strategic Director of Economy, Planning and Place, in consultation with the Lead Councillor for Regeneration and Lead Councillor for Finance and Property, authority to enter into such other contracts and legal agreements connected with Weyside Urban Village as may be necessary to deliver the programme in compliance with Contract Procedure Rules, the Council’s Constitution and within the approved budget.

3. Reasons for Recommendation: 3.1. To ensure that there is sufficient understanding of the projected financial forecast of the programme and specifically, to highlight the worsened forecast deficit position.

3.2To ensure that statutory service agreements and construction agreements can be entered into for the delivery of services and infrastructure for the development and to ensure that Homes England Housing Infrastructure Fund (HIF) milestones are achieved.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Weyside Urban Village DevelopmentReport 97 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 9 attended
JM
Councillor Julia McShaneChairperson, present
TH
Councillor Tom HuntVice-Chair, present
AG
Councillor Angela GoodwinCommittee Member, apologies
CH
Councillor Catherine HoustonCommittee Member, present
RL
Councillor Richard LucasCommittee Member, apologies
CM
Councillor Carla MorsonCommittee Member, present
MR
Councillor Merel Rehorst-SmithCommittee Member, present
FW
Councillor Fiona WhiteCommittee Member, present
AC
Councillor Amanda CreeseGuest, in attendance, virtual

On this subject at Guildford

Search all
  1. Weyside Urban Village DevelopmentThis decision
  2. Weyside Urban Village - Award of contract to deliver the Internal Estate Road Phase 2.Approved
  3. Land transaction relating to the relocation of the Surrey County Council Waste Facility, part of Weyside Urban VillageApproved
  4. Annual Weyside Urban Village ReportDecided
  5. Land transaction relating to the relocation of the Surrey County Council Waste Facility, part of Weyside Urban VillageApproved
  6. Weyside Urban Village: Financial Mitigation OptionsNoted

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies