Resolved
(1) That under Section 100A (4) of the Local Government Act 1972 (as amended), the public be excluded from the meeting for consideration of Appendices 1, ... view the full minutes text for item CO38
Council decided this item on Tuesday 29 July 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) That under Section 100A (4) of the Local Government Act 1972 (as amended), the public be excluded from the meeting for consideration of Appendices 1, ... view the full minutes text for item CO38
Guildford Borough Council Report to: Council Date: 29 July 2025 Ward(s) affected: Bellfields and Slyfield Report of Director: Economy, Planning and Place Author: Abi Lewis, Assistant Director of Regeneration & Economic Development Tel: 01483 444908 Email: [email protected] Lead Councillor responsible: Cllr Tom Hunt Tel: [phone removed] Email: [email protected] Report Status: Part Exempt (Appendices)
Weyside Urban Village Development 1. Executive Summary 1.1 Weyside Urban Village ("WUV") is a major 41-hectare brownfield regeneration scheme that Guildford Borough Council (the "Council") anticipates could deliver approximately 1,500 homes across a range of tenures, as well as 2,000 square metres of community space and 6,500 square metres of employment space.
1.2Over 44 percent of the site is currently in Council ownership, and 100 percent will be achieved on completion of land transfers with Thames Water Utilities Ltd (“TWUL”). The conditional contract with TWUL was signed on 25 April 2019 (the "TW Agreement").
1.3In February 2020, the Council committed £334.9 million to de-risk the infrastructure and site assembly process needed across the Weyside Urban Village site. In conjunction with its own financial commitment, the Council has also secured and benefited from substantial grant funding from Homes England’s Housing Infrastructure Fund (HIF) of £52.3m and Local Enterprise Partnership (LEP) funding of £8m, with grant draw down in alignment with the implementation of the infrastructure.
1.4As part of the overarching governance of the Weyside programme, this report is presented to the Executive, outlining the forecast financial position of the scheme and high-level progress achieved.
1.5The broader macro-economic landscape and its impact on the construction industry over the last 24 months has been profound. At the end of 2021, the Building Cost Information Service (BCIS) - which provides cost and price data for the UK construction industry - reported that the annual growth in its material cost index reached a forty-year high. Since then, pressures on supply chains have persisted and labour shortages have become more acute. Although the lifting of Covid restrictions led to a return of high activity levels, the war in Ukraine and high rates of inflation have put the construction industry in further turmoil. The impact of these issues is being felt at a local level, albeit construction costs have stabilised somewhat yet financing costs have increased significantly.
1.6This report sets out the current financial forecast to the end of the programme, which provides the background for the mitigation strategy to address the potential financial deficit that has arisen resulting from increased borrowing costs and the macro-economic factors referred above.
1.7At its meeting on 17 July 2025, the Executive considered this report and approved the recommendation below. This report is submitted to the Council for noting.
2. Recommendation to Executive That the Executive:
2.1Notes the current financial position of WUV at the 2025 Financial Review, outlined in Exempt Appendix 2.
2.2Notes the forecast deficit - outlined in Exempt Appendix 1. 2.3 Delegates to the Strategic Director of Economy, Planning and Place, in consultation with the Lead Councillor for Regeneration and Lead Councillor for Finance and Property, authority to enter into such other contracts and legal agreements connected with Weyside Urban Village as may be necessary to deliver the programme in compliance with Contract Procedure Rules, the Council’s Constitution and within the approved budget.
3. Reasons for Recommendation: 3.1. To ensure that there is sufficient understanding of the projected financial forecast of the programme and specifically, to highlight the worsened forecast deficit position.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Annual Weyside Urban Village ReportReport | 97 KB | DownloadRead as text |
Follow Council at Guildford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Sep 2026 | Appointment of an Interim Monitoring OfficerThat Deborah Davies, Joint Head of Governance, be appointed as the Council’s interim Monitoring Officer until the Str... | Decided | Open |
| 15 Sep 2026 | Proposed Changes to the Scheme of Officer Delegations & Proper Officer Scheme(1) That the proposed changes to the Scheme of Delegation and Proper Officer Scheme, as set out in Appendices 1 and 2... | Approved | Open |
| 15 Sep 2026 | Overview and Scrutiny Annual Report(1) To approve the attached at Appendix 1 to the report submitted to the Council. (2) To not amend the current O&S wo... | Approved | Open |
| 15 Sep 2026 | Freedom of the BoroughThat a meeting of the Council be arranged specially convened for the purpose of admitting The Ranger Regiment to the ... | Decided | Open |
| 15 Sep 2026 | Councillor Ruth Brothwell - Review of Attendance at MeetingsThat, in accordance with Section 85 of the Local Government Act 1972, the Council agrees that Councillor Ruth Brothwe... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.