Weyside Urban Village - Award of contract to deliver the Internal Estate Road Phase 2.

Approved Executive 1 paper

AI summaryGuildford Executive waived contract rules to directly award Winvic Construction Ltd a £1,827,530.64 contract for the Internal Estate Road Phase 2 at Weyside Urban Village, with works due to start in January 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedContract Procedure Rules waived to enable award
Money£1,827,530.64Contract sum, within WUV programme budget
What happens nextSeal contract, start works January 2026Six month build period planned
Who it affectsWeyside Urban Village site and occupiersIndustrial estate occupiers may face traffic management

What was decided

The Executive approved waiving the Council's Contract Procedure Rules and directly awarding the Internal Estate Road Phase 2 construction contract to Winvic Construction Ltd. Report P2

The original open tender procurement was abandoned because delays to consents, programming and technical design made it impossible to enter the contract as tendered; the new direct award uses the same scope and terms as the original exercise. Report 3.1, 6.4

Why

There is a narrow window in Q4 2025/26 between completion of construction at the new Sewage Treatment Works and the operational start of the new GBC depot, and only Winvic can deliver in time after winning the earlier competitive tender. Report 3.3, 6.4, 11.1

Procurement and legal advice is that the works are not a Covered Procurement under the Procurement Act 2023, but the Council's own rules would normally require competition, so a waiver is needed. Report 3.2, P37

The works deliver essential highways infrastructure that is critical to enabling access across the whole Weyside Urban Village site and supports the Council's Corporate Strategy priorities on homes, prosperity and sustainability. Report 3.3, 7.1, P21, P22, P23

What happens next

Once approvals are received, the contract with Winvic Construction Ltd will be sealed and the contractor will start on site in January 2026 for an anticipated six month build period. Report 3.1, 8.1

The completed road will be offered to Surrey County Council as highways authority for long term management and maintenance after the statutory maintenance period. Report 6.2

The money

  • £1,827,530.64 Contract sum for the Internal Estate Road Phase 2 works, within the WUV programme budget reported in July 2025 Report P35

Options considered

  • Rejected: Do nothing. Would miss the narrow window before the new depot becomes operational, force a new procurement exercise and delay demolition and remediation of the existing depot site earmarked for disposal in Q2 2026/7 Report 11.1
  • Chosen: Approve the direct award to Winvic (Recommended). Enables the works to progress as scheduled, reducing impact on the wider Weyside Urban Village programme Report 11.2

Implications

  • Financial: Contract sum of £1,827,530.64 sits within the WUV programme budget last reported to Full Council in July 2025. Report P35, 9.2
  • Legal: Waiver is sought under Contract Procedure Rules 13.2(a) on time criticality and 13.2(e) on market investigation; the works are not a Covered Procurement under the Procurement Act 2023. Report P36, P37
  • Risk: Any delay could interfere with the scheduled opening of the new GBC depot and affect service mobilisation and wider programme dependencies. Report 10.2
  • Other: Works will require traffic management across the industrial estate, with overnight working planned to minimise daytime disruption, and effective communication with occupiers is flagged as critical. Report 10.1
  • Equalities: The Public Sector Equality Duty has been considered and no direct equality implications arise, though the contractor is expected to consider impacts on those with protected characteristics. Report 12.3, P45
  • Staffing: There are no HR implications arising from the recommendations. Report 12.4
  • Climate: There are no climate change or sustainability implications arising from the recommendations. Report 12.5, 12.6

Who and where

  • Occupiers of the Slyfield industrial estate where the road works will take place Report 10.1
  • Surrey County Council as future highways authority for the completed road Report 6.2
  • Future users of the Weyside Urban Village development Report 3.3, 7.1
  • Winvic Construction Ltd as the directly awarded contractor Report P2

Timeline

  • Q3 2024/5: Original open tender procurement exercise for the works Report 6.1
  • 29 July 2025: Full Council received annual financial position report for WUV, also considered by Overview and Scrutiny and Executive Report 9.2, 16.1
  • 4 December 2025: Executive decision to waive Contract Procedure Rules and direct award to Winvic
  • Q4 2025/26: Limited window of opportunity to carry out the works between Sewage Treatment Works construction completion and new GBC depot becoming operational Report 3.3
  • January 2026: Contractor due to commence on site Report 3.1, 8.1
  • Approximately six months from January 2026: Anticipated build period Report 3.1, 8.1
  • Q2 2026/7: Existing depot site earmarked to be marketed for disposal following demolition and remediation Report 11.1

Plain English for the jargon

  • Weyside Urban Village (WUV): Guildford Borough Council's major development programme on which it is financially and legally committed, scheduled to complete before the new Unitary authority is created.
  • Internal Estate Road Phase 2: Highways works at the Slyfield industrial estate including reconstruction of part of Westfield Road, junction reformation, a new estate road, substation and Thames Water access, and resurfacing of an existing road section.
  • Covered Procurement: A procurement regulated under the Procurement Act 2023; officers advise this works contract falls below that threshold and is therefore not covered.
  • Contract Procedure Rules waiver: Approval under the Council's own rules to depart from the usual requirement for competition, here granted under rules 13.2(a) and 13.2(e) on time criticality and market grounds.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEX93

Resolved

Waive the Council’s Contract Procudure Rules and, in doing so, approve the direct award of the contract for the construction of the Internal Estate Road Phase 2 to Winvic Construction Ltd. Reason(s): 1. A tender exercise was undertaken and Winvic were the successful bidder. There were delays to the programme as a result of obtaining necessary consents, programming and further technical design work which were beyond the control of the Council or Winvic. As a result it was not possible to enter the contract as tendered with Winvic and the procurement has been abandoned. 2. It is now proposed that the Council directly awards a contract for these works to Winvic as all outstanding matters have been resolved. Procurement and legal advice is that this is not a covered procurement given the value but it must still comply with our Contract Procedure Rules which would usually require competition. 3. The recommendation in this report is therefore that Executive waive the Contract Procedure Rules to directly award the contract to Winvic to support the broader Weyside Urban Village programme by facilitating the delivery of essential highways infrastructure, critical to enabling access across the entire site. There is a limited window of opportunity to carry out these works in Q4 2025/26, between the completion of the construction elements at the new Sewage Treatment Works and the operational commencement of the new GBC depot. Other options considered and rejected by the Executive: Do nothing. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Recommendations

2.1That the Executive resolves to:

2.1.1 Waive the Council’s Contract Procurement Rules and, in doing so, approve the direct award of the contract for the construction of the Internal Estate Road Phase 2 to Winvic Construction Ltd.

3 Reason(s) for recommendation:

3.1A tender exercise was undertaken and Winvic were the successful bidder. There were delays to the programme as a result of obtaining necessary consents, programming and further technical design work which were beyond the control of the Council or Winvic. As a result it was not possible to enter the contract as tendered with Winvic and the procurement has been abandoned.

3.2It is now proposed that the Council directly awards a contract for these works to Winvic as all outstanding matters have been resolved. Procurement and legal advice is that this is not a covered procurement given the value but it must still comply with our Contract Procedure Rules which would usually require competition.

2 Weyside Urban Village: Award of contract to deliver Internal Estate Road Phase 2

3.3The recommendation in this report is therefore that Executive waive the Contract Procedure Rules to directly award the contract to Winvic to support the broader Weyside Urban Village programme by facilitating the delivery of essential highways infrastructure, critical to enabling access across the entire site. There is a limited window of opportunity to carry out these works in Q4 2025/26, between the completion of the construction elements at the new Sewage Treatment Works and the operational commencement of the new GBC depot.

4. Next steps

3.1Once approvals are received, the contract with Winvic Construction Ltd. will be sealed, enabling the contractor to commence with the works in January 2026. It is anticipated that this will be a 6 month build period.

5 Exemption from publication

5.1This report is not exempt from publication.

6 Background and Proposal

6.1The Council ran a procurement exercise through an open tender in Q3 2024/5 for the following works:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Weyside Urban Village: Award of contract to deliver the Internal Estate Road Phase 2.Report 131 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 9 attended
JM
Councillor Julia McShaneChairperson, present
TH
Councillor Tom HuntVice-Chair, present
AG
Councillor Angela GoodwinCommittee Member, present
CH
Councillor Catherine HoustonCommittee Member, present
RL
Councillor Richard LucasCommittee Member, present
CM
Councillor Carla MorsonCommittee Member, present
MR
Councillor Merel Rehorst-SmithCommittee Member, present
FW
Councillor Fiona WhiteCommittee Member, apologies
SK
Sharon KeenlysideCouncil Staff, expected

On this subject at Guildford

Search all
  1. Weyside Urban Village - Award of contract to deliver the Internal Estate Road Phase 2.This decision
  2. Land transaction relating to the relocation of the Surrey County Council Waste Facility, part of Weyside Urban VillageApproved
  3. Annual Weyside Urban Village ReportDecided
  4. Land transaction relating to the relocation of the Surrey County Council Waste Facility, part of Weyside Urban VillageApproved
  5. Weyside Urban Village DevelopmentAgreed
  6. Weyside Urban Village: Financial Mitigation OptionsNoted

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies