That approval be given to the implementation of a combined Chi ldren’s Centre and Community Centre to be located within the boundary of Fulham Court or Barclay Close Estates(subject to any necessary statutory consents and the outcome of comprehensive resident consultation). 2. To authorise the Chief Executive of H& F Homes and the Chief Executive of the Council to finalise the location of the Centre in conjunction with the Cabinet Members for Housing and Children’s Services. 3. To approve a programme of consultation with residents to evaluate the possibility of physical estate improvement. 4. To agree to earmark £4.057m of funding from the HRA Disposal Receipts over the years 2009/2013 to enable the works programme to proceed, subject to detailed resident consultation and further approval, and to agree the provisional annual budgets across the 2009/2013 years as shown in the body of the report to Cabinet on 11 January 2010 (subject to confirmation at tender approval stage) and that £0.450m of grant funding be applied regarding the provision of a Children’s Centre. 5. To approve the delegation to H&F Homes of the responsibility for the development and delivery of the physical improvement programme, subject to detailed approval being sought to the final scheme from the Cabinet.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
CABINET MEMBER FULHAM COURT ESTATE IMPROVEMENT Ward: FOR HOUSING STRATEGY: PHASE 1 PHYSICAL Town Councillor Lucy Ivimy IMPROVEMENTS, FURTHER REPORT
CABINET MEMBER Further to the decision taken on 11 January FOR CHILDREN’S 2010, a further decision is needed to clarify SERVICES Councillor Sarah Gore (recommendation 1) that approval be given to the implementation of a combined Children’s Centre and Community Centre to be located within the boundary of Fulham Court or Barclay Close Estates (subject to any necessary statutory consents and the outcome of comprehensive resident consultation and in consultation with the Cabinet Members for Housing and Childrens’ Services).
The report approved on 11 January is attached as an Appendix and sets out work being undertaken to formulate an Estate Improvement Strategy for Fulham Court and seeks approval to the implementation of phase 1–physical improvement programme. The estate has suffered from a number of complex issues for a long time. A strategy is being developed to transform it, and to improve residents’ quality of life through a multi agency steering group and a HAS A PEIA BEEN process to understand the problems and to COMPLETED? develop a vision for transformation. The strategy YES will seek to harness resources from numerous sources to create a deliverable programme of physical and social improvements over the next 3-4 years.
CONTRIBUTORS Recommendations:
CSD/HFH/FCS/LS/ 1. That approval be given to the ENV/NHSH&F/CHSD/ implementation of a combined Children’s RSD Centre and Community Centre to be ADLDS located within the boundary of Fulham DFCS Court or Barclay Close Estates (subject to any necessary statutory consents and the outcome of comprehensive resident consultation).
2. To authorise the Chief Executive of H& F Homes and the Chief Executive of the Council to finalise the location of the Centre in conjunction with the Cabinet Members for Housing and Children’s Services.
3. To approve a programme of consultation with residents to evaluate the possibility of physical estate improvement.
4. To agree to earmark £4.057m of funding from the HRA Disposal Receipts over the years 2009/2013 to enable the works programme to proceed, subject to detailed resident consultation and further approval, and to agree the provisional annual budgets across the 2009/2013 years as shown in the body of the report to Cabinet on 11 January 2010 (subject to confirmation at tender approval stage) and that £0.450m of grant funding be applied regarding the provision of a Children’s Centre.
5. To approve the delegation to H&F Homes of the responsibility for the development and delivery of the physical improvement programme, subject to detailed approval being sought to the final scheme from the Cabinet. 1. BACKGROUND
2. Cabinet approved on 11 January 2010 the implementation of a Children’s Centre (subject to any necessary statutory consents and comprehensive resident consultation). The report approved in January is attached as the Appendix to this report.
3. That report stated (para. 3.2.4) that replicating the successful model of combining a Children’s Centre with a Community Centre similar to the centre developed on the Old Oak Estate will enable a seamless service to be delivered under one roof.
4. The Community Centre was to be replaced at a later phase in the project as stated in para 6.1 & para 6.3 of the attached report. This decision was made so as not to delay the provision of the Children’s Centre. (para. 3.2.6). A decision to move ahead with the provision of a Children’s Centre is urgent. The Council has a capital allocation of £450,000 (which comes from the DCFS) available to provide a Children’s Centre and this needs to be spent by the end of March 2011.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.