Resolved
RESOLVED : That officers be authorised to spend Section 106 monies as set out in this report.
Cabinet decided this item on Monday 8 May 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED : That officers be authorised to spend Section 106 monies as set out in this report.
1.1This report is the second report for S106 spend in 2016/17 and seeks authority to spend £6.8m
2.1That officers be authorised to spend Section 106 monies as set out in this report.
3. INTRODUCTION AND BACKGROUND
3.1The Council enters into agreements with developers and land owners under Section 106 of the Town and Country Planning Act 1990 to enable mitigation of impacts of development and to enable delivery of necessary social and physical infrastructure. 3.2 For a Council to enter into an agreement under S106 of the Town and Country Planning Act, the obligations need to comply with the tests set out in Regulation 122 of the Community Infrastructure Regulations 2010. All obligations must be:
i. Necessary to make the development acceptable in planning terms; ii. Relevant to the development being permitted; and iii. Reasonably in all other respects.
3.3Funds received pursuant to S106 agreements must be used for the purposes specified in those agreements or, where there is flexibility within the terms of the agreement, for purposes that comply with the tests set out above.
4. Projects to be funded
The following projects are funded from S106 monies to address needs generated by the developments taking place.
4.1£823,979 towards Economic Development Learning & Skills staffing and projects to deliver the regeneration strategy for the borough funded from: -
Numbers shown in italics relate to the legal agreements.
£55,000 – 258 – 264 Goldhawk Road 805
£106,560 – 271 – 281 King Street 830
£12,074 – Thaxton Road / North End Road 538
£204,742 – Westfield WSTF
£9,000 – 282 – 292 Goldhawk Road 784
£5,550 – 28 – 36 Glenthorne Road 729
£57,999 – 51 Townmead Road 721
£4,500 – 58 Shepherds Bush Green 687
£47,980 – Guardian House 698
£40,000 – Hammersmith Pallais 605
£104,243 – Riverside Studios 801
£176,331 – Quayside Lodge 161
4.2£1,470,000 towards capital education projects in the borough to be funded from : -
£671,620 – Fulham Reach 716 £298,827 – Stowe Road Depot 693
£240,000 – Riverside Studios 801
£259,553 – 258 – 264 Goldhawk 805
4.3£40,000 towards environmental monitoring at Earls Court to measure and mitigate the impact of the works currently taking place on the site funded from:-
£40,000 – Earls Court 733
4.4£443,000 towards new and existing CCTV projects to improve the security and safety in the borough being funded from: -
£164,188 – Westfield WSTF
£10,000 – Fulham Broadway 403
£20,005 – West 12 413
£31,717 – Chelsea Village 458
£33,232 – Empress State Building 468
£15,000 – 725 – 761A Harrow Road 635
£168,857 – Chelsea Creek 722
4.5544,992 towards Parks and Environmental improvement to increase the capacity of the public open spaces in the borough being funded form –
£1,457 – Fulham Reach 716
£408,637 – Janet Adegoke 712
£39,991 – Westfield WSTF
£33,176 – Service Station, Du Cane Road 773
£40,000 – 725 -761 Harrow Road 635
£21,730 – Chelsea Village 458
4.6£1,160,000 towards Development projects being carried out by the Council to be funded from: -
£255,000 – M&S White City 867
£602,000 – Westfield WSTF
£254,000 – London House 794 £49,000 – 258 – 264 Goldhawk Road 805
4.7£100,000 towards North End Road extended markets and other high street activities funded from: -
£25,000 – Westfield WSTF
£25,000 – Sovereign Court 776
£25,000 – Parsons Green Club 799
£25,000 – Woodlands 753
4.8£50,000 towards Wandsworth Bridge Parade improvements funded from: -
£25,000 – Chelsea Creek, Lots Road 732
£25,000 – Imperial Wharf 808
4.9£1,972,328 towards the delivery of Genuinely Affordable Housing Projects funded from: -
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2016/17 Final Section 106 ExpenditureReport | 237 KB | DownloadRead as text |
Follow Cabinet at Hammersmith & Fulham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Oct 2026 | General Fund Medium Term Financial Plan 2027/28 - 2030/31Note the revised Medium Term Financial Strategy for 2027/28 to 2030/31. To agree next steps to take forward the devel... | Noted | Open |
| 12 Oct 2026 | Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparis... | Noted | Open |
| 12 Oct 2026 | LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy... | Approved | Open |
| 12 Oct 2026 | TfL Hammersmith Road Permanent Cycleway 9 (C9)To support the implementation of Transport for London's Permanent Cycleway 9 scheme on Hammersmith Road, subject to c... | Approved | Open |
| 12 Oct 2026 | Approval to Consult on the School Organisation Plan and Primary Place Sufficiency OptionsThat Cabinet: Approve consultation on the draft School Organisation Plan and associated options for managing primary ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.