That approval be given to make realistic and necessary changes to the concept designs for the Hammersmith Grove South scheme, resulting in a preferred design which can be progressed to public consultation. 2. That authority be delegated to the Director of Transport and Highways in consultation with the Cabinet member for Environment, Transport and Resident’s Services to approve the implementation of the Hammersmith Grove South Scheme, subject to a favourable outcome of public consultation in Autumn 2017. 3. That an order be placed with the Council’s Term Contractor (F M Conway PLC) in the sum not to exceed £760,000.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
1.1This report seeks approval for the progression of the combined NoF (Neighbourhoods of the Future) and MAQF (Mayor’s Air Quality Fund), scheme, which for the purposes of this report will be referred to as the ‘Hammersmith Grove South Scheme’.
Recommendations
2.1That approval be given to make realistic and necessary changes to the concept designs for the Hammersmith Grove South scheme, resulting in a preferred design which can be progressed to public consultation.
2.2That authority be delegated to the Director of Transport and Highways in consultation with the Cabinet member for Environment, Transport and Resident’s Services to approve the implementation of the Hammersmith Grove South Scheme, subject to a favourable outcome of public consultation in Autumn 2017.
2.3That an order be placed with the Council’s Term Contractor (F M Conway PLC) in the sum not to exceed £760,000.
Reasons for decision
3.1Physical improvements to the public highway and programmes of work designed to reduce congestion, manage traffic and promote road safety fall under the council’s statutory duties under a variety of acts including the Traffic Management Act 2004.
3.2Where changes to the highway are proposed, these are to be in line with section 122 of the Road Traffic Regulation Act 1984; securing the expeditious, convenient, and safe movement of vehicular and other traffic (including pedestrians) and the provision of suitable and adequate parking facilities.
3.3The funding streams provided by TfL represent an opportunity to deliver a scheme which will improve the urban realm and pedestrian permeability in addition to providing opportunities to enhance air quality through the use of electric vehicle charging points and engagement with local businesses.
Background
4.1In 2015/16 officers submitted bids to TfL (Transport for London) for both NoF and MAQF2 funding for two separate projects. Both submissions were successful on the basis that they would be match funded by existing or new S106 funding from nearby developments. Early design work was undertaken in 2016.
4.2In late 2016 it was confirmed that S106 match funding was not available and it was proposed to combine funding for both projects (NoF and MAQF2), alongside the council’s sustainable urban drainage [SUDS] and LIP funding to deliver a combined project – the Hammersmith Grove South Scheme.
4.3The approximate cost breakdown of the combined project’s various funding streams is set out in the below table;
Total £300k £460k £760k 4.4. As shown in table 1 there is funding in the 17/18 financial year, resulting in a need to consult publicly on the scheme and deliver its basic elements, as soon as possible.
4.5Design work undertaken to date has centred around the removal of all non- low emissions vehicles from the scheme boundary. Whilst this would be a progressive way to improve air quality, it would preclude access for businesses and residents and the lead in times associated with gaining the relevant permissions from the Department for Transport would likely result in the allocated funding not being spent in 2017 / 2018. Transport for London are comfortable with this element of the scheme being removed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.