Cabinet, Monday 2 November 2020 at 6.30pm

Business Case & Procurement Strategy for the major refurbishment of three housing estates: Sulivan Court SW6, Becklow Gardens W12, and Emlyn Gardens W12

Approved Executive 1 paper

Cabinet approved this item on Monday 2 November 2020. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

It is recommended that Cabinet approves the Business Case & Procurement Strategy for procurement of each of the following works contracts: 1. The major refurbishment of Sulivan Court estate SW6 at an estimated value of £6.081m . 2. The major refurbishment of Emlyn Gardens estate W12 at an estimated value of £4.5m 3. The major refurbishment of Becklow Gardens estate W12 at an estimated value of £4.3m 4. Approves a £5.8m capital budget, funded by HRA borrowing, to progress Becklow Gardens and Emlyn Gardens with the remaining £3m funded from uncommitted and unallocated budgets identified within the overall programme.
Word for word from the decision Hammersmith & Fulham published for this meeting. Source: democracy.lbhf.gov.uk

Follow this further

Built from Hammersmith & Fulham's papers

What the report saysPro

Report to Cabinet

Summary

This report seeks approval of the Business Case & Procurement Strategy for the major refurbishment of three housing estates: Sulivan Court SW6, Becklow Gardens W12, and Emlyn Gardens W12.

Recommendations

It is recommended that Cabinet approves the Business Case & Procurement Strategy for procurement of each of the following works contracts:

1. The major refurbishment of Sulivan Court estate SW6 at an estimated value of £6.081m.

2. The major refurbishment of Emlyn Gardens estate W12 at an estimated value of £4.5m

3. The major refurbishment of Becklow Gardens estate W12 at an estimated value of £4.3m

4. Approves a £5.8m capital budget, funded by HRA borrowing, to progress Becklow Gardens and Emlyn Gardens with the remaining £3m funded from uncommitted and unallocated budgets identified within the overall programme.

Wards Affected: Sands End, Askew H&F Priorities

Our Priorities Summary of how this report aligns to the H&F Priorities  Building shared prosperity The procurement strategy will require suppliers to demonstrate their commitment to social value including how they can support local businesses  Creating a compassionate Investment in social housing enables the council council to fulfil its landlord function and provide good-quality homes to local people that are safe, secure and genuinely affordable  Doing things with local Residents have been consulted in the residents, not to them preparation of this scheme including formal ballots to decide door styles and communal redecorations. The consultation will continue post-procurement to include site set-up arrangements and further information on the delivery stage.  Being ruthlessly financially The project will be competitively tendered efficient and awarded on the basis of most economically advantageous tender as set out in the procurement strategy. There will be robust contract management and a strong site presence to ensure quality standards and value for money.  Taking pride in H&F The evaluation criteria set out in the procurement strategy will require contractors to give details of their approach to energy consumption, use of sustainable materials, transport plan, site waste management, and noise pollution.

Financial Impact

The HRA Capital Programme approved on 1 July 2019 included a budget for the works for Sulivan Court Phase 2 - the amount allocated is £6.081m which is sufficient to meet the estimated costs of the scheme.

The July 2019 report had no specific budget allocation for Becklow Gardens and Emlyn Gardens as the scope of the works required had not been confirmed at the time.

However, the £8.8m cost of these schemes will form part of the additional capital compliance works within a revised 2021 HRA Financial Plan to be considered by Cabinet in 2021. Due to a favourable movement of interest rates in comparison to that forecasted in the 2020 Financial Plan the HRA can sustain the cost of servicing the debt associated with these additional compliance works. The financial modelling that underpins the plan has been stress tested for steeper increases in future interest rates which has confirmed it can accommodate an additional capital budget for the £5.8m required for Becklow Gardens and Emlyn Gardens, funded by HRA borrowing. The remaining £3m will come from what remains of the unallocated budget for future years that was approved by Full Council on 26 February 2020 via the “Four Year Capital Programme 2020 to 2024 and Capital Strategy 2020/21” report. Following this approval, there will be £1m remaining of the unallocated capital budget.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Business Case & Procurement Strategy for the major refurbishment of three housing estates: Sulivan Court SW6, Becklow Gardens W12, and Emlyn Gardens W12Report 400 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
SC
Councillor Stephen CowanChair, apologies
SF
Councillor Sue FennimoreCommittee Member, present
BC
Councillor Ben ColemanCommittee Member, present
AC
Councillor Adam ConnellCommittee Member, present
LC
Councillor Larry CulhaneCommittee Member, present
WH
Councillor Wesley HarcourtCommittee Member, present
AJ
Councillor Andrew JonesCommittee Member, apologies
LH
Councillor Lisa HomanCommittee Member, present
SM
Councillor Sue MacmillanCommittee Member, present
MS
Councillor Max SchmidCommittee Member, present

On this subject at Hammersmith & Fulham

Search all
  1. Business Case & Procurement Strategy for the major refurbishment of three housing estates: Sulivan Court SW6, Becklow Gardens W12, and Emlyn Gardens W12This decision
  2. Business Case for Covid Funding for Children's Front door ServicesAgreed
  3. Linford Christie Outdoor Stadium - Outline Business CaseAgreed
  4. Linford Christie Business Case - UpdateNoted
  5. Business Case & Procurement Strategy In Relation To Lightning ProtectionApproved
  6. Business Case & Procurement Strategy: The Procurement Of LED Lighting For Residential Blocks And Estate Column LightingApproved

More from Hammersmith & Fulham Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 General Fund Medium Term Financial Plan 2027/28 - 2030/31Note the revised Medium Term Financial Strategy for 2027/28 to 2030/31. To agree next steps to take forward the devel... Noted Open
12 Oct 2026 Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparis... Noted Open
12 Oct 2026 LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy... Approved Open
12 Oct 2026 TfL Hammersmith Road Permanent Cycleway 9 (C9)To support the implementation of Transport for London's Permanent Cycleway 9 scheme on Hammersmith Road, subject to c... Approved Open
12 Oct 2026 Approval to Consult on the School Organisation Plan and Primary Place Sufficiency OptionsThat Cabinet: Approve consultation on the draft School Organisation Plan and associated options for managing primary ... Approved Open