Resolved
RESOLVED 1. The Board noted progress in development of the business case for the WLO. 2. The Board noted the proposed arrangements for funding the project from Strategic Investment Pot resources held by the West London Alliance.
West London Economic Prosperity Board noted this item on Monday 11 October 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED 1. The Board noted progress in development of the business case for the WLO. 2. The Board noted the proposed arrangements for funding the project from Strategic Investment Pot resources held by the West London Alliance.
West London Economic Prosperity Board
11 October 2021 Title West London Orbital (Standing Item)
Report of Niall Bolger, LB Hounslow
Status Public
Urgent No
Enclosures N/A Andrew Barry-Purssell, West London Planning Policy and Officer Contact Details Infrastructure Delivery Manager, West London Alliance, E: [email protected]; T: [phone removed]
Summary This report provides the Board with an update on work with Transport for London and Network Rail to develop the business case for the West London Orbital and the inception of joint governance arrangements for the project. It notes the current situation regarding funding for the project from the resources secured from the Strategic Investment Pot and sets out likely next stages.
Recommendations Leaders are asked to:
i) NOTE progress in development of the business case for the WLO; and ii) NOTE the proposed arrangements for funding the project from Strategic Investment Pot resources held by the West London Alliance.
1. WHY THIS REPORT IS NEEDED
1.1The West London Economic Prosperity Board (WLEPB) has consistently identified the West London Orbital (WLO) Overground rail line as a shared strategic priority for West London, integral to the sub-region’s sustainable development. The Board has agreed that progress and next steps relating to the WLO should be a standing item on its agenda. The West London Alliance
1 (WLA) and West London boroughs continue to work closely with Transport for London (TfL) and the Greater London Authority and Network Rail to develop and refine the business case for the project. The WLA has secured funding to contribute to the costs of the work, most recently £3.6 million from the retained business rates-based Strategic Investment Pot. TfL’s current budgetary situation has made the availability of this funding essential to work on the project proceeding. Joint governance arrangements have been set up to ensure the work proceeds effectively, transparently and accountably. This report takes stock of progress to date, seeks comments on the direction taken and sets out likely next steps.
2. DEVELOPMENT OF THE WLO BUSINESS CASE
2.1It will be recalled that the Strategic Outline Business Case for the WLO, published in June 2019, recommended that work on the project should move forward. This started in the autumn of 2019 and has focussed on feasibility and funding with a view to establishing whether to proceed to more detailed work to identify a preferred route and frequency option to take forward.
2.2As reported to the Board’s meeting in February, work by Network Rail (NR) concluded that the originally proposed 8 train per hour (tph) service cannot be achieved without unacceptable impacts on other services unless substantial – and probably unaffordable – improvements to infrastructure are made. Since then NR has carried out further work, looking at what could be achieved with some flexibility in the timing of existing services. This found that 4 tph along the whole route with an additional 2tph between Hendon/West Hampstead and Old Oak Common Lane is possible.
2.3Work has also started on engineering design to identify the additional infrastructure and other work that might be required at key locations along the WLO route. The work is being carried out by Atkins and at time of writing this was about halfway complete. The boroughs concerned are being kept informed of progress and any issues identified are being raised with the consultants. This work is due to complete in November.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
West London Orbital (standing item)Report | 281 KB | DownloadRead as text |
Follow West London Economic Prosperity Board at Hammersmith & Fulham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Oct 2021 | Minutes of the previous meetingRESOLVED The minutes of the meeting held on 26 May 2021 were approved. | Approved | Open |
| 11 Oct 2021 | West London Economic Recovery - Update on Build & Recover plan delivery and associated workRESOLVED 1. The Board note and commented on the progress in delivering activity under the West London Build & Recover... | Noted | Open |
| 11 Oct 2021 | West London Innovation District ConceptRESOLVED 1. The Board noted the mapping work undertaken to better understand the innovation landscape across West Lon... | Noted | Open |
| 11 Oct 2021 | WLA Economy & Skills Programme UpdatesRESOLVED 1. The Board noted the updates provided on the West London Alliance’s Economy & Skills Programme. | Noted | Open |
| 11 Oct 2021 | Forward PlanRESOLVED The Board noted the draft forward plan. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.