The Clarence, 148 North End Road London W14 9PP, West Kensington, 2023/03336/FUL
AgreedPlanning1 paper
AI summaryPlanning committee authorises grant of permission for The Clarence pub in West Kensington, allowing 11 self-contained flats with a retained pub, subject to a £207,278 affordable housing contribution and 27 conditions.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedSubject to legal agreement and conditions
Money£207,278 affordable housing contributionOff-site, secured by legal agreement
What happens nextComplete legal agreement, then grantMinor changes to conditions allowed
Who it affectsWest Kensington residents and pub usersThe Clarence, 148 North End Road
What was decided
The committee authorised the Executive Director for Place to grant planning permission once a satisfactory legal agreement is completed and the 27 listed conditions are met. Report P8, P10
The Executive Director for Place, after consulting the Assistant Director, Legal Services and the Chair of the Planning and Development Control Committee, was authorised to make minor changes to the conditions. Report P9
Officers concluded the scheme is acceptable, providing 11 flats and retaining the public house, with planning balance weighed in favour of approval subject to conditions and a legal agreement. Report P7, P72, 6.21
Why
The development would deliver 11 self-contained flats (4 one-bed, 6 two-bed and 1 three-bed) that meet London Plan space standards, supporting the borough's housing targets. Report 6.12, 6.17, P155
The public house at basement and ground floor would be retained and remain viable, with only a modest 3.6% reduction in overall floorspace and a slightly smaller beer garden. Report 6.4, 6.5, 6.7
Subject to conditions, the scheme would not unacceptably harm neighbours' amenity, the Barons Court Conservation Area, transport, or environmental matters including air quality, flood risk and land contamination. Report P72, 6.32, 6.48
What happens next
A legal agreement must be completed before planning permission is granted, securing the £207,278 affordable housing contribution and any planning obligations. Report P8, 6.20
The 27 listed conditions cover time limit, approved plans, materials, construction management, cycle and waste storage, energy, noise, air quality, flood risk, and land contamination. Report P10, P11, P12, P22, P27, P29, P35, P41, P47, P59
Before development starts, the applicant must submit a preliminary risk assessment, site investigation scheme, quantitative risk assessment, remediation method statement and other details required by the land contamination conditions. Report P59, P61, P62, P64, P66
The money
£207,278 Financial contribution in-lieu of on-site affordable housing, secured by legal agreement Report 6.20
Options considered
Chosen: Officer recommendation: grant planning permission subject to legal agreement and 27 conditions. Scheme is acceptable in planning terms, providing 11 flats and retaining the public house, with no unacceptable impacts subject to conditions and obligations. Report P7, P8, P72, 6.21
Implications
Financial: A £207,278 financial contribution in-lieu of on-site affordable housing will be secured through a legal agreement, after an independent viability review identified a surplus. Report 6.20
Legal: Permission cannot be issued until a satisfactory legal agreement is completed; the applicant is Opticrealm Limited, working through an agent. Report P4, P8
Equalities: A previous 2019 scheme for an 87-bedroom tourist hostel was refused and an appeal dismissed, partly for failing the 10% wheelchair access target; the current 11-flat scheme addresses this. Report 2.1, 2.2, P97
Climate: The development must follow the approved Energy and Sustainability Statement, achieve a water efficiency limit of 105 litres per person per day, and provide air source heat pumps and wastewater heat energy recovery systems. Report P27, P37, P56, P57
Risk: Potentially contaminative land uses are understood to occur at or near the site, requiring a preliminary risk assessment, site investigation, quantitative risk assessment, remediation, verification and possible long-term monitoring. Report P59, P60, P61, P62, P64, P66, P68, P69
Other: Construction must follow a Construction Management Plan and Construction Logistics Plan, with working hours restricted to 0800-1800 Monday to Friday and 0800-1300 on Saturdays, and no works on Sundays or Bank Holidays. Report P20, P22
Who and where
Future residents of 11 new self-contained flats at The Clarence Report P5, 6.12, 6.17
Existing customers and operators of the retained public house at basement and ground floor Report 6.4, 6.5, 6.7
Neighbouring residents in West Kensington, including properties on Cheesemans Terrace, Perham Road, Sun Road and North End Road Report P83, P84, P85, P88, P89, 1.2
Visitors to the Barons Court Conservation Area and surrounding townscape Report 1.3, 6.43, 6.48
Timeline
July 2019: Previous appeal for 87-bedroom tourist hostel dismissed Report 2.2, P97
22 December 2023: Application form received Report P75
07/07/2026: Planning and Development Control Committee meeting date Report P4
Plain English for the jargon
PTAL: Public Transport Accessibility Level, a Transport for London rating from 0 to 6b indicating access to public transport; the site is rated 6a, the highest tier.
NDSS: Nationally Described Space Standard, the minimum Gross Internal Area and room size standards for new dwellings set out in national policy.
SuDS: Sustainable Drainage Systems, features that manage rainwater runoff to reduce flood risk.
Agent of Change: London Plan Policy D14 principle that puts the responsibility for noise mitigation on the new noise-sensitive development rather than the existing noise-generating use.
WWHERS: Wastewater Heat Energy Recovery System, a device that recovers heat from drain water to warm incoming fresh water.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11
Resolved
RESOLVED That the Executive Director for Place be authorised to grant planning permission upon the completion of a satisfactory legal agreement and subject to the conditions listed in the report and changes in the Addendum. That the Executive Director for Place, after consultation with the Assistant Director, Legal Services and the Chair of the Planning and Development Control Committee be authorised to make any minor changes to the proposed conditions, which may include the variation, addition or deletion of conditions, any such changes shall be within their discretion.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
Reg. No: Case Officer; 2023/03336/FUL Robert Cook Date valid: 09/01/2024 Conservation Area: Committee Date: Barons Court 07/07/2026 Applicant: Opticrealm Limited C/O Agent
Description: Reconfiguration and retention of existing public house at basement and ground floor levels; erection of two additional floors at roof level, erection of five storey rear and side extensions at ground, first, second, third and fourth floor levels including the formation of an undercroft to ac- cess the rear yard from street level (facing May Street) in connection with the change of use of the ancillary public house uses (Class Sui Generis) at upper floor levels to 11 self-contained flats and enlarged ancillary commercial floorspace at ground floor level including bin stores; al- terations including installation of new door openings at ground floor level facing May Street ele- vation; installation of new doors and windows to outside courtyard at ground floor.
Application type: Full Planning Application
Officer Recommendation:
(1) That the Committee resolve that the Executive Director of Place be authorised to grant plan- ning permission upon the completion of a satisfactory legal agreement and subject to the condi- tions listed below.
(2) That the Committee resolve that the Executive Director of Place , after consultation with the Assistant Director, Legal Services and the Chair of the Planning and Development Control Committee be authorised to make any minor changes to the proposed conditions, which may include the variation, addition or deletion of conditions, any such changes shall be within their discretion.
Conditions:
1) Time Limit The development hereby permitted shall not commence later than the expiration of 3 years beginning with the date of this planning permission.
Condition required to be imposed by section 91(1)(a) of the Town and Country Planning Act 1990 (as amended by section 51 of the Planning and Compulsory Purchase Act 2004). 2) Approved Plans/Drawings The development hereby permitted shall be carried out in complete accordance with the following approved drawing numbers, other than where those details are altered pursu- ant to the conditions of this planning permission:
To ensure full compliance with the planning application hereby approved and to prevent harm arising through deviations from the approved plans.
3) Materials Prior to commencement of the relevant part of the works, details of the external facing materials (including manufacturer's specifications, photographs and/ or a physical sam- ple) shall be submitted to, and approved in writing by the Council. The development shall be carried out and completed in accordance with the approved details. The devel- opment shall be permanently retained in accordance with the approved details.
To ensure a satisfactory external appearance, in accordance with Policies DC1, DC4 and DC8 of the Local Plan (2018).
4) No Water Tanks No water tanks, water tank enclosures or other structures (excluding solar panels and air source heat pumps) shall be erected upon the roof of the building hereby permitted.
It is considered that such structures would seriously detract from the appearance of the building, contrary to Policy DC4 of the Local Plan (2018).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Councillor Adrian Pascu-TulbureCommittee Member, present
Hear about the next one first
Follow Planning and Development Control Committee at Hammersmith & Fulham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.