AGREED UNANIMOUSLY BY THE CABINET MEMBERS PRESENT: That Cabinet: 1. Notes Appendix A is not for publication on the basis that it contains information relating to the financial or business affairs of any particular person (including the authority holding that information) as set out in paragraph 3 of Schedule 12A of the Local Government Act 1972 (as amended). 2. Approves total one-off investment of up to £1.799m to be funded from the IT and Technology reserve. 3. Approves Azure cloud hosting services to be commissioned from Microsoft via Trustmarque. These costs are contained in exempt Appendix A. 4. Approves a Change Control Notice to be issued to BT to procure the necessary exit management services via the Managed Compute Lot 3 agreement. These c osts are contained in exempt Appendix A. 5. Approves the additional technical and project management staff resource to be procured to complete the migration. These costs are contained in exempt Appendix A. 6. Notes that a separate procurement strategy has been approved to utilise the GCloud 12 framework to secure an Azure migration and ongoing support partner. The costs are contained in exempt Appendix A.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
Currently many critical systems used across Hammersmith & Fulham (H&F) are hosted by BT as part of the ‘Managed compute’ service. These systems include things such as H&F’s print servers and line of business systems such as Power BI and the Capita income management system. Technology has moved on and the existing hosting solution is outdated, inflexible and costly. This paper seeks authority for the investment funding to move H&F systems to Microsoft Azure hosting. The migration to Azure is in line with the Council’s Digital and Information Strategy and ambitions as expressed in Hello ‘hybrid’ Future, providing H&F with a modern platform that is agile, easily scalable and future proof, as well as with more cost- effective technical services.
The new solution is designed to be flexible and will allow critical line of business systems to constantly transform and evolve so they can always meet the needs of H&F residents and be operated in the most cost-effective way. As well as the benefits for the resident facing services, Microsoft Azure is a foundation block for the further improvement of digital systems. It will enable the H&F network to be transformed into a modern cloud-based version with minimal reliance on old fashioned infrastructure in physical buildings. It will also allow the deployment of the most up-to-date user computing capability during the Tech-tonic 2 programme.
The benefits Microsoft Azure brings will enable a productive agile workforce equipped with the technology needed to work in a modern and flexible way. The migration will complete by October 2023 when the current infrastructure contract expires.
Recommendations
That Cabinet:
1. Notes Appendix A is not for publication on the basis that it contains information relating to the financial or business affairs of any particular person (including the authority holding that information) as set out in paragraph 3 of Schedule 12A of the Local Government Act 1972 (as amended). 2. Approves total one-off investment of up to £1.799m to be funded from the IT and Technology reserve.
3. Approves Azure cloud hosting services to be commissioned from Microsoft via Trustmarque. These costs are contained in exempt Appendix A.
4. Approves a Change Control Notice to be issued to BT to procure the necessary exit management services via the Managed Compute Lot 3 agreement. These costs are contained in exempt Appendix A.
5. Approves the additional technical and project management staff resource to be procured to complete the migration. These costs are contained in exempt Appendix A.
6. Notes that a separate procurement strategy has been approved to utilise the GCloud 12 framework to secure an Azure migration and ongoing support partner. The costs are contained in exempt Appendix A.
Wards Affected: All
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.