Resolved
To approve the award of the contract to refurbish Lena Gardens to Arc Group London Ltd. for £823,867.80 plus 10% contingency of £82,387 (total of £906,254.80) funded from School Condition Allocation
Cabinet approved this item on Monday 4 September 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
To approve the award of the contract to refurbish Lena Gardens to Arc Group London Ltd. for £823,867.80 plus 10% contingency of £82,387 (total of £906,254.80) funded from School Condition Allocation
The Lena Gardens Primary school site has returned to Local Authority control and provides a site well suited to long term educational use. The report recommends award of the contract for refurbishing the premises to provide high quality educational facilities for future use to Arc Group Ltd. This investment will support options for the long-term educational use of the Lena Gardens site.
1. To approve the award of the contract to refurbish Lena Gardens to Arc Group London Ltd. for £823,867.80 plus 10% contingency of £82,387 (total of £906,254.80) funded from School Condition Allocation.
Wards Affected: Addison, Ravenscourt
Our Values Summary of how this report aligns to the H&F Values Building shared prosperity The provision of improved educational facilities for pupils to support improved educational outcomes. Creating a compassionate council The provision of a quality learning environment for future educational use for H&F children and young people. Doing things with local residents, not to Improvements to the Lena Gardens site them responds to concerns raised with the condition of the current school site and provides opportunities for future use. Being ruthlessly financially efficient The refurbishment of the Lena Gardens site represents significantly better value for money as an alternative site for a local primary school. Taking pride in H&F Supporting H&F children with the provision of high-quality educational facilities. Rising to the challenge of the climate The refurbishment will contribute and ecological emergency towards reducing carbon emissions by providing improved building fabric.
Financial Impact
2. The refurbishment of Lena Gardens Primary School is expected to cost up to £906,255 including contingency. The works are expected to span the 2023/24 and 2024/25 financial years.
3. This report requests Cabinet approval to drawdown up to £906,255 from the School Condition Allocation grant (SCA). The DfE has confirmed a SCA grant allocation of £1.42m for 2023/24, which is sufficient to cover the cost of works.
4. The payment will be made to the supplier Arc Group London on the satisfactory completion of works. A Credit Safe report run on 8th August 2023 on the supplier Arc Group London Limited shows the supplier has a credit score of 70 (low risk) and a contract limit of £2,550,000.
Table 1 – Breakdown of project costs
Expenditure Estimates Lena Gardens
Capital: Essential refurbishment, repairs and safeguarding works (Incl. 719,189 Contingency) Capital: Specialist and professional fees 187,066 Subtotal Capital Expenditure £906,255
Funded by:
School Condition Allocation grant £906,255
Financial Implications provided by: Anjeli Chadha, Principal Accountant, 8th August 2023 Reviewed by Tony Burton, Head of Finance, Children’s Services and Education 10th August 2023 Verified by: Sukvinder Kalsi, Director of Finance, 26 June 2023
Contracts and Procurement
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
The refurbishment of Lena Gardens school site for ongoing education useReport | 386 KB | DownloadRead as text |
Follow Cabinet at Hammersmith & Fulham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Oct 2026 | General Fund Medium Term Financial Plan 2027/28 - 2030/31Note the revised Medium Term Financial Strategy for 2027/28 to 2030/31. To agree next steps to take forward the devel... | Noted | Open |
| 12 Oct 2026 | Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparis... | Noted | Open |
| 12 Oct 2026 | LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy... | Approved | Open |
| 12 Oct 2026 | TfL Hammersmith Road Permanent Cycleway 9 (C9)To support the implementation of Transport for London's Permanent Cycleway 9 scheme on Hammersmith Road, subject to c... | Approved | Open |
| 12 Oct 2026 | Approval to Consult on the School Organisation Plan and Primary Place Sufficiency OptionsThat Cabinet: Approve consultation on the draft School Organisation Plan and associated options for managing primary ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.