Avonmore Primary School - Construction Contractor Procurement Strategy Budget and Request

Approved Executive 5 papers

Cabinet approved this item on Monday 3 June 2024. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

That Cabinet: 1. Notes that Appendix 2 is not for publication on the basis that it contains information relating to the financial or business affairs of any particular person (including the authority holding that information) as set out in paragraph 3 of Schedule 12A of the Local Government Act 1972 (as amended). 2. Notes that Full Council approval will be sought for a total Development capital budget, including contingencies, to deliver the proposed new one form entry school and associated nursery and SEND facilities and new homes, to be funded through a combination of HRA and GF borrowing, Right to Buy receipts and capital sales receipts from shared ownership and private leasehold sales, as set out in exempt Appendix 2 . 3. Authorises the Strategic Head of Regeneration and Development to take decisions on expenditure against this contingency budget subject to the continued viability of the development. 4. Approves the Procurement Strategy, as set out in Appendix 3, to procure a principal construction contractor, using a single stage lump sum JCT standard form of building contract, on a design and build basis, via a two-step mini competition procurement route, using the preferred Notting Hill Genesis Framework Agreement (NHG). That Full Council: 5. Approves a total Development capital budget, to deliver the proposed new school, nursery and new homes. The budget will be funded through a combination of HRA and GF borrowing, Right to Buy receipts and capital sales receipts from shared ownership and private leasehold sales, as set out in exempt Appendix 2 .
Word for word from the decision Hammersmith & Fulham published for this meeting. Source: democracy.lbhf.gov.uk

Follow this further

Built from Hammersmith & Fulham's papers

What the report saysPro

Report to Cabinet

Summary

This report concerns the proposed redevelopment of Avonmore Primary School, Avonmore Road, W14 8RL, (“Site”). This report seeks approval for both a capital budget and the works procurement strategy for the principal construction contractor to complete the development.

The proposed scheme (“Development”) is on the site of the existing school, and has been co-produced with school governors, the wider school community and local residents. It will provide a modern, fit for purpose one form entry (1FE) Primary School, as well as enhanced nursery and Special Educational Needs and Disabilities (SEND) provision. The site can also accommodate 91 new homes, of which 45 will be provided as affordable housing.

The provision of modern, sustainable, high-end school facilities is vital to the council’s Industrial Strategy; access to excellent educational opportunities for every young person across Hammersmith and Fulham is a fundamental element of building shared prosperity and fostering inclusive growth. Similarly, the proposals ensure that the council continues to maximise opportunities to add to the provision of affordable housing across the borough.

In line with the council’s net-zero ambitions, the school facilities and new homes have been designed to high sustainability and environmental standards which translate into an estimated 75% reduction in operational carbon emissions. This reduction will significantly reduce energy costs for the school and future residents, which is particularly important in view of the current economic climate and ongoing cost of living crisis.

As the scheme progresses, the council will continue to explore further means by which it can deliver more benefits to local residents. Subject to planning conditions and funding availability, it may be possible to convert a greater proportion of the market-sale homes to affordable tenures. Furthermore, as the scheme nears completion, a local lettings policy will be designed to ensure that a broad range of local residents are able to access new homes. The council has designed a specific model of intermediate affordable housing targeted at enabling a greater proportion of key workers to access family-sized affordable housing. RECOMMENDATIONS

That Cabinet:

1. Notes that Appendix 2 is not for publication on the basis that it contains information relating to the financial or business affairs of any particular person (including the authority holding that information) as set out in paragraph 3 of Schedule 12A of the Local Government Act 1972 (as amended).

2. Notes that Full Council approval will be sought for a total Development capital budget, including contingencies, to deliver the proposed new one form entry school and associated nursery and SEND facilities and new homes, to be funded through a combination of HRA and GF borrowing, Right to Buy receipts and capital sales receipts from shared ownership and private leasehold sales, as set out in exempt Appendix 2.

3. Authorises the Strategic Head of Regeneration and Development to take decisions on expenditure against this contingency budget subject to the continued viability of the development.

4. Approves the Procurement Strategy, as set out in Appendix 3, to procure a principal construction contractor, using a single stage lump sum JCT standard form of building contract, on a design and build basis, via a two-step mini competition procurement route, using the preferred Notting Hill Genesis Framework Agreement (NHG).

That Full Council:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Site Plan 1Appendix 1 702 KB Download
PDF
Procurement StrategyAppendix 3 328 KB Download
PDF
Public Sector Equality Duty AvonmoreAppendix 4 199 KB Download
PDF
Equality Impact AssessmentAppendix 5 298 KB Download
PDF
Avonmore Primary School: Construction Contractor Procurement Strategy Budget and RequestReport 321 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 11 attended
SC
Councillor Stephen CowanChair, present
BC
Councillor Ben ColemanCommittee Member, apologies
WH
Councillor Wesley HarcourtCommittee Member, present
AJ
Councillor Andrew JonesCommittee Member, present
SH
Councillor Sharon HolderCommittee Member, present
RH
Councillor Rebecca HarveyCommittee Member, present
BK
Councillor Bora KwonCommittee Member, present
RR
Councillor Rowan ReeCommittee Member, present
AS
Councillor Alex SandersonCommittee Member, present
FU
Councillor Frances UmehCommittee Member, present
AA
Councillor Adronie AlfordOther Attendee, present

On this subject at Hammersmith & Fulham

Search all
  1. Avonmore Primary School - Construction Contractor Procurement Strategy Budget and RequestThis decision
  2. Appropriation of Avonmore Primary School Land and Budget AdjustmentApproved
  3. Redevelopment of Avonmore Primary School and Building New HomesAgreed
  4. Avonmore Primary School, Avonmore Road, London W14, Avonmore, 2023/03051/FR3Decided
  5. Constitution Of The Governing Body Of Avonmore Primary SchoolDecided

More from Hammersmith & Fulham Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 General Fund Medium Term Financial Plan 2027/28 - 2030/31Note the revised Medium Term Financial Strategy for 2027/28 to 2030/31. To agree next steps to take forward the devel... Noted Open
12 Oct 2026 Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparis... Noted Open
12 Oct 2026 LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy... Approved Open
12 Oct 2026 TfL Hammersmith Road Permanent Cycleway 9 (C9)To support the implementation of Transport for London's Permanent Cycleway 9 scheme on Hammersmith Road, subject to c... Approved Open
12 Oct 2026 Approval to Consult on the School Organisation Plan and Primary Place Sufficiency OptionsThat Cabinet: Approve consultation on the draft School Organisation Plan and associated options for managing primary ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies