To note that Exempt Appendix 1 is not for publication on the basis that it contains information relating to the financial or business affairs of any particular person (including the authority holding that information) as set out in paragraph 3 of Schedule 12A of the Local Government Act 1972. To approve LBHF to be formally part of the London Partnership 6. To delegate authority to the Executive Director of Place, to manage and approve the agreements associated with LBHF’s position in the Partnership. To approve the procurement of a concession contract for Electric Vehicle Charge Point (EVCP) services via an open or such other tendering process as the Executive Director of Place approves following a recommendation from the Assistant Director of Procurement and Commercial Services, led by the Lead Partner, in a collaborative procurement process. To delegate authority to the Executive Director of Place, in consultation with the Executive Director of Finance and Corporate Services, to approve the procurement documents for market when they are finalised.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
The London Borough of Hammersmith and Fulham and five other local authorities (Ealing Council, Haringey Council, Brent Council, Hillingdon Council, and Harrow Council) have formed a partnership, known as the London Partnership 6, to secure Local Electric Vehicle Infrastructure (LEVI) funding from Office for Zero Emission Vehicles (OZEV).
The partnership aims to procure a service through a concession agreement via an open or such other tender process for the supply, installation, operation and maintenance of EV charge points in return for a revenue share at no capital cost to the Council. Each partner is expected to enter individual contracts with the selected provider(s) to ensure clear accountability.
This report requests the authority to proceed with procurement with the partnership.
Recommendations
1. To note that Exempt Appendix 1 is not for publication on the basis that it contains information relating to the financial or business affairs of any particular person (including the authority holding that information) as set out in paragraph 3 of Schedule 12A of the Local Government Act 1972.
2. To approve LBHF to be formally part of the London Partnership 6.
3. To delegate authority to the Executive Director of Place, to manage and approve the agreements associated with LBHF’s position in the Partnership.
4. To approve the procurement of a concession contract for Electric Vehicle Charge Point (EVCP) services via an open or such other tendering process as the Executive Director of Place approves following a recommendation from the Assistant Director of Procurement and Commercial Services, led by the Lead Partner, in a collaborative procurement process. 5. To delegate authority to the Executive Director of Place, in consultation with the Executive Director of Finance and Corporate Services, to approve the procurement documents for market when they are finalised.
Wards Affected: All
Summary of how this report aligns to the H&F Our Values Corporate Plan and the H&F Values Building shared The delivery of further charge points through the LEVI prosperity bid would improve and maintain EV charging provision across the borough, thus supporting the Council in its strategic aim of achieving net zero carbon emissions by 2030. Transport emissions impact on quality of life and public health as well as create opportunities for work, education, leisure etc. Creating a LBHF’s LEVI bid focusses on improving the equitable compassionate council distribution of EV charging points across the borough. Investment in a more equitable EV charging network is crucial to ensure all residents have fair access to accessible and affordable charging. Doing things with local Officers will ensure that residents are informed about residents, not to them decisions affecting Electric Vehicle Infrastructure (EVI) close to their homes. Where dedicated bays are introduced, a consultation as part of a traffic order will be undertaken. Direct requests for charge points will be assessed. Being ruthlessly The collective procurement for multiple boroughs seeks financially efficient to maximise value for money in the way in which additional electric vehicle charge points are secured to enhance provision for the borough. Taking pride in H&F The procurement evaluation will consider the project’s environmental impact, including reviewing contractors’ approach to energy consumption and charging tariffs. Rising to the challenge The aim of this scheme is to support the transition from of the climate and more polluting vehicles to electric vehicles whilst ecological emergency recognising that more sustainable modes will be prioritised.
Financial Impact
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.