Sacred Heart High School , 212 Hammersmith Road, London W6 7DG, Hammersmith Broadway, 2021/02737/FUL
DecidedPlanning1 paper
AI summaryPlanning committee authorises officer to grant permission to convert Sacred Heart High School's 1930s gym into a theatre, subject to a legal agreement and 24 conditions.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedSubject to 24 planning conditions and minor changes allowed
MoneyNot stated
What happens nextComplete legal document, then grantPermission to follow satisfactory legal agreement
Who it affectsNot stated
What was decided
The Executive Director of Place was authorised to grant planning permission upon completion of a satisfactory legal document and subject to the 24 conditions listed in the report as amended by the addendum. Report P11, P13
The Executive Director of Place, after consultation with the Assistant Director of Legal Services and the Chair of the Planning and Development Control Committee, was authorised to make minor changes to the legal document heads of terms or conditions, including variation, addition or deletion of conditions. Report P12
Conditions cover time limits, approved drawings, materials, construction management, air quality, tree protection, fire safety, servicing, lighting, noise, ventilation, drainage, archaeology and Secured by Design. Report P14, P16, P23, P25, P27, P29, P37, P41, P43, P45, P47, P49, P58, P60, P62
Why
Officers concluded the change of use from gym to theatre is acceptable on land use grounds, retaining and enhancing the school's facilities and adding a community venue, in line with Local Plan Policies CF1 and CF2. Report P66, 6.2, 6.6
The design was judged to be high quality. Officers identified less than substantial harm to the Grade II* listed Sacred Heart School, but considered this was outweighed by the public benefits of the scheme, with no harm to the Brook Green Conservation Area or the locally listed buildings on Bute Gardens. Report P67, 6.21, 6.22, 6.38
No objections were received from around 184 neighbouring properties consulted. The Twentieth Century Society objected on heritage grounds, but Historic England did not direct the application to be called in. Report 4.1, 4.2, 4.3
What happens next
Complete the legal document covering community use, air quality, construction logistics and a school travel plan before permission is issued. Report P73, P11
Discharge the pre-commencement and pre-occupation conditions as the development progresses, including the demolition and construction management plans, arboricultural assessment, archaeology written scheme of investigation and air quality dust management plans. Report P23, P25, P27, P29, P37, P58
The development must begin within three years of the date of the planning permission. Report P14
Options considered
Chosen: Approve subject to legal agreement and conditions (officer recommendation). High quality design; less than substantial heritage harm outweighed by public benefits; no neighbour objections Report P10, P11, P67, 4.1
Rejected: Refuse to allow consideration of the Twentieth Century Society's heritage objection. Officers assessed harm as less than substantial and weighed it against the scheme's public benefits under NPPF paragraphs 214 to 216 Report 4.3, 6.39
Implications
Legal: Planning obligations to be secured by legal agreement cover community use, an air quality dust management plan, a construction logistics plan and an updated school travel plan. Report P73
Equalities: The new theatre is to be wheelchair accessible for both audiences and performers, with a separate self-contained entrance off the courtyard facing Bute Gardens. Report 3.4
Climate: Conditions require an Air Source Heat Pump or other electrical only heating and cooling system, a ventilation strategy with filtration against NO2 and particulates, and external lighting limits to protect amenity and air quality. Report P45, P49, P55
Risk: The site lies within Flood Zones 2 and 3. The development must follow the approved Flood Risk Assessment and Surface Water Drainage Strategy, including the December 2025 addendum. Report 1.2, P62
Other: Construction hours are limited to 0800 to 1800 Monday to Friday and 0800 to 1300 on Saturdays, with no work on Sundays or bank holidays. Deliveries are restricted to specified times. Report P27, P57
Who and where
Sacred Heart High School, the applicant and operator of the new theatre and performing arts centre Report P6, 3.1, 6.4
Pupils of Sacred Heart High School, who will gain expanded drama and performing arts teaching space Report 3.4, 6.4
Local community users of the new facility outside school hours Report 3.4, P73
Residents of around 184 neighbouring properties consulted on the application Report 4.1
Occupiers of Victorian villas on Bute Gardens, which are locally listed and adjoin the site Report 1.1, 6.38
Heritage assets including the Grade II* listed Sacred Heart School and the Brook Green Conservation Area Report 1.1, 1.4
Hammersmith Library, a Grade II listed building on the western boundary Report 1.1
Timeline
November 2020: Flood Risk Assessment and Surface Water Drainage Strategy Report produced Report P62
19.08.2021: Application form received by the council Report P77
10/11/2025: FWS Fire Strategy dated and approved under condition 13 Report P41
December 2025: Flood Risk Assessment and Surface Water Drainage Strategy Report Addendum produced Report P62
14.04.2026: Planning and Development Control Committee resolves to authorise grant of permission Report P6
Within 3 years of permission: Development must commence, otherwise permission expires Report P14
Plain English for the jargon
Grade II* listed: A building of more than special interest, on the second highest tier of statutory listing in England.
Brook Green Conservation Area: An area of special architectural or historic interest whose character and appearance the council has a duty to preserve or enhance.
Legal agreement (Section 106): A planning obligation attached to a permission, used here to secure community use, travel planning, and air quality and construction management measures.
Class F1: The use class covering learning and non residential cultural uses, including schools and performing arts venues.
SUDS: Sustainable Drainage Systems, designed to manage surface water runoff and reduce flood risk.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
RESOLVED That the Executive Director of Place be authorised to grant planning permission upon the completion of a satisfactory legal document and subject to the conditions listed in the report as amended by the Addendum. That the Executive Director of Place, after consultation with the Assistant Director, Legal Services and the Chair of the Planning and Development Control Committee be authorised to make any minor changes to the proposed Heads of Terms of the legal document or proposed conditions, which may include the variation, addition, or deletion of conditions, any such changes shall be within their discretion.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
Reg. No: Case Officer: 2021/02737/FUL Neil Egerton
Date Valid: Conservation Area: 20.08.2021 Brook Green Conservation Area - Number 3
Committee Date: 14.04.2026 Applicant: [name removed] Heart High School 212 Hammersmith Road London W6 7DG
Description: Conversion of the Stuart Building (an existing school gymnasium building dating from the 1930's) into a school theatre and performing arts centre; erection of an extension to the east elevation (front) of the building including a mezzanine level outwards into the existing courtyard to provide foyer facilities; erection of an infill extension to the west elevation (rear); and other associated internal and external alterations including associated landscaping.
Drg Nos: See condition 2
Application Type: Full Detailed Planning Application
Officer Recommendation:
1) That the Committee resolve that the Executive Director of Place be authorised to grant planning permission upon the completion of a satisfactory legal document and subject to the conditions listed below.
2) That the Committee resolve that the Executive Director of Place, after consultation with the Assistant Director, Legal Services and the Chair of the Planning and Development Control Committee be authorised to make any minor changes to the proposed Heads of Terms of the legal document or proposed conditions, which may include the variation, addition, or deletion of conditions, any such changes shall be within their discretion.
Conditions:
1) The development hereby permitted shall not commence later than the expiration of 3 years beginning with the date of this planning permission.
Condition required to be imposed by section 91(1)(a) of the Town and Country Planning Act 1990 (as amended by section 51 of the Planning and Compulsory Purchase Act 2004).
2) The development shall be carried out and completed in accordance with the following approved drawings:
In order to ensure full compliance with the planning application hereby approved and to prevent harm arising through deviations from the approved plans, in accordance with Policies DC1, DC4, and DC8 of the Local Plan (2018).
3) Any alterations to the elevations of the existing buildings, including works of making good, shall be carried out in the same materials as the existing elevation to which the alterations relate.
To ensure a satisfactory external appearance of the development, to preserve the special architectural and historic interest of the buildings of merit and their setting, and to preserve the character and appearance of the Conservation Area in accordance with Policies D3 and HC1 of the London Plan (2021), and Policies DC1, DC4 and DC8 of the Local Plan (2018).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning and Development Control Committee at Hammersmith & Fulham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.