AI summaryHammersmith & Fulham Planning Committee authorises grant of planning permission for change of use from former school to 12 self-contained flats at 1-3 Chesilton Road, subject to legal agreement and 41 conditions.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedChange of use to 12 flats with external works
MoneyNo monetary sum stated in decision
What happens nextLegal agreement to be completedBefore permission is issued by Executive Director
Who it affects1-3 Chesilton Road SW6 5AAFulham Town ward, former school site
What was decided
The Executive Director of Place is authorised to grant planning permission once a satisfactory legal agreement is completed and the 41 listed conditions are met. Report P12
The Executive Director of Place, consulting the Assistant Director of Legal Services and the Committee Chair, can make minor changes to the legal agreement heads of terms or conditions. Report P13
The development must begin within 3 years of the permission date, in line with standard planning time limits. Report P15, P16
Why
Officers found nearby schools have capacity for displaced pupils and the scheme meets local housing demand on a currently vacant site. Report P87
The 12 flats meet space standards, the design is compatible with the area, and subject to conditions there would be no unacceptable harm to neighbours' amenity, transport, environment or flood risk. Report P88, P89, P90, P91, P92
Planning obligations are secured covering urban greening, car permit-free restrictions, Section 278 highways works, a Construction Management Plan, an Air Quality Dust Management Plan and monitoring fees. Report P92
What happens next
A legal agreement (likely Section 106) must be finalised before the Executive Director of Place formally issues the permission. Report P12
Pre-commencement conditions require submission of details including 1:20 design details, landscaping, bat roost assessment, Secured by Design statement, contamination reports, demolition method statement, construction management plan and tree protection. Report P19, P22, P25, P39, P74, P78, P79, P84
Pre-occupation conditions require installation of refuse storage, cycle storage, obscure glazing, privacy screening, flood mitigation, ventilation strategy, air source heat pumps, solar PV and battery storage, and a delivery and servicing plan. Report P27, P29, P33, P37, P42, P51, P58, P64, P82
Options considered
Chosen: Grant planning permission subject to legal agreement and conditions (officer recommendation). Scheme complies with land use, housing, design, amenity, transport and environmental policies once conditions are met. Report P11, P12, P86, P87, P88, P89, P90, P91, P92
Implications
Legal: Permission is contingent on completion of a legal agreement; the dwellings must remain single C3 dwellings and not become C4 houses in multiple occupation. Report P12, P80
Environment: Conditions require solar PV panels, air source heat pumps or equivalent electric-only heating, wastewater heat energy recovery, and a ventilation strategy with filtration to address air quality. Report P41, P58, P60, P51, P54
Risk: Extensive contaminated land, flood risk, fire safety, contamination monitoring and demolition/construction management conditions are imposed to manage identified risks. Report P42, P78, P79, P80, P74
Staffing: The previously vacant former school site (last used by Fulham Senior School) will be redeveloped for residential use, ending its educational function. Report 1.2, P9
Who and where
Future residents of the 12 self-contained flats (3 x 1-bed and 9 x 2-bed) Report P9, P88
Neighbouring residents on Chesilton Road and Radipole Road, who raised concerns about privacy, construction noise, dust and impacts on trees Report P110, P125, P126, P127
Applicant FHS Property Ltd, c/o agent at 33 Margaret Street, London W1G 0JD Report P8
Timeline
8th October 2025: Application form and supporting documents (Flood Risk Assessment, Transport Statement, Energy Statement, Fire Safety Statement, etc.) received Report P104
14.10.2025: Application validated by the council Report P6
9.06.2026: Planning and Development Control Committee meeting to decide the application Report P7
Within 3 years of permission: Development must commence, otherwise permission expires Report P15, P16
Plain English for the jargon
PTAL: Public Transport Accessibility Level, a score from 0 to 6b rating access to public transport; the site scores 3 (moderate).
Use Class C3: Dwellinghouses used as single family homes or by up to six residents sharing.
Use Class F1: Learning and non-residential institutions, including schools and other educational facilities.
Article 4 direction: A local planning tool removing permitted development rights; here it covers basement works at the site.
Section 278 agreement: A legal agreement under the Highways Act requiring a developer to carry out works on the public highway, here for crossover removal and kerb reinstatement.
Section 106: A legal agreement under the Town and Country Planning Act 1990 used to secure planning obligations from a developer.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5
Resolved
RESOLVED That the Executive Director of Place be authorised to grant planning permission upon the completion of a satisfactory legal agreement and subject to the conditions listed in the report. That the Executive Director of Place, after consultation with the Assistant Director of Legal Services and the Chair of the Planning and Development Control Committee be authorised to make any minor changes to the proposed Heads of Terms of the legal agreement or proposed conditions, which may include the variation, addition or deletion of conditions, any such changes shall be within their discretion.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
Reg. No: Case Officer: 2025/02767/FUL Christopher May
Date valid: Conservation Area: 14.10.2025
Committee Date: 09.06.2026
Applicant: FHS Property Ltd c/o Agent 33 Margaret Street London W1G 0JD
Description: Change of use from educational (Use Class F1) to residential (Use Class C3) provide 12 self-contained flats (3 x 1-bedroom and 9 x 2-bedroom), with external works including partial demolition and construction of a single-storey side extension, alterations to the roof, windows and doors, creation of external amenity spaces, installation of landscaping and solar panels, reconstruction and increase in height of the north side brick boundary to 3m, along with other associated works.
Application type: Full Detailed Planning Application
Officer Recommendation:
(1) That the Committee resolve that the Executive Director of Place be authorised to grant planning permission upon the completion of a satisfactory legal agreement and subject to the conditions listed below.
(2) That the Committee resolve that the Executive Director of Place, after consultation with the Assistant Director of Legal Services and the Chair of the Planning and Development Control Committee be authorised to make any minor changes to the proposed Heads of Terms of the legal agreement or proposed conditions, which may include the variation, addition or deletion of conditions, any such changes shall be within their discretion.
Conditions:
1) Time Limit The development hereby permitted shall not commence later than the expiration of 3 years beginning with the date of this planning permission.
Condition required to be imposed by section 91(1)(a) of the Town and Country Planning Act 1990 (as amended by section 51 of the Planning and Compulsory Purchase Act 2004).
2) Approved Plans/Drawings The development shall be carried out and completed in accordance with the following drawings hereby approved: P01 Rev.D; P02 Rev.D; P03 Rev.D; P04 Rev.D; P05 Rev.D; P06 Rev.D; P07 Rev.D; P08 Rev.D; P09 Rev.D; Flood Risk Assessment received 8 October 2025; Sustainable Drainage Assessment received 8 October 2025; Outline Construction Logistics Plan received 8 October 2025; Transport Statement received 8 October 2025; Urban Greening Factor Assessment received 8 December 2025; Energy Statement received 8 October 2025; Financial Viability Assessment received 8 October 2025; Fire Safety Statement received 8 October 2025.
To ensure full compliance with the planning permission hereby approved and to prevent harm arising through deviations from the approved plans, in accordance with Policy DC1 and DC4 of the Local Plan (2018).
3) 1:20 Details Prior to commencement of the development hereby permitted (excluding Ground and Enabling Works), details in plan, section and elevation (at a scale of not less than 1:20) of the following matters have been submitted to and approved in writing by the Council. The development shall be carried out in accordance with the approved details; and permanently retained as such.
a) exterior cladding and roofing; b) new and replacement window details; b) gates and railings; d) rooftop plant associated enclosures.
To ensure a satisfactory external appearance of the development, in accordance with Policies D3 and HC1 of the London Plan (2021), and Policies DC1, DC4 and DC6 of the Local Plan (2018).
4) Hard and Soft Landscaping The development hereby permitted shall not be occupied or used before details of the soft and hard landscaping of all private external areas, including planting, planting schedules, paving, boundary walls, fences, gates and other means of enclosure, have been submitted to and approved in writing by the Council.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning and Development Control Committee at Hammersmith & Fulham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.