117 - 123 King Street, London W6 9JT, Hammersmith Broadway, 2022/03727/FUL
AgreedPlanning1 paper
AI summaryHammersmith & Fulham planning committee authorises the Executive Director of Place to grant full planning permission for seven new flats at 117-123 King Street, subject to a legal agreement and 47 conditions.
Who it affects117-123 King Street, Hammersmith BroadwaySite in Hammersmith Town Hall Conservation Area
What was decided
The committee authorised the Executive Director of Place to grant full planning permission once a satisfactory legal agreement is completed and the listed conditions are met. Report P9
The Executive Director of Place was authorised, after consulting the Assistant Director for Legal Services and the committee Chair, to make minor changes to the legal agreement heads of terms or conditions. Report P10
The development provides seven self-contained flats (two studios, two one-bed, three two-bed) alongside retention of the existing five ground floor commercial units and Class E offices and leisure floorspace above. Report P6, 2.1, 2.2, 2.3
Why
Officers judged the principle of development acceptable, noting the proposal would contribute to the borough's housing stock in a highly accessible town centre location with PTAL 6b. Report P147, 1.2
The design was considered high quality, with no harmful impact on heritage assets or neighbouring residential amenity, subject to conditions covering noise, privacy, contamination, air quality and construction management. Report P147, 5.0
Eleven objections and a petition signed by all 18 flats at Federal House, 2 Down Place were received, raising concerns on conservation, density, traffic, construction and operational nuisance, amenity and impact on a yoga studio. Report 3.2, P167
What happens next
A satisfactory legal agreement must be completed and 47 planning conditions discharged before the development can commence or be occupied, including a three-year time limit, approved plans, materials, Construction Logistics Plan, Construction Management Plan, accessibility, sound insulation, air quality, contamination, drainage, fire strategy and Thames Water piling conditions. Report P12, P13, P14, P28, P29, P48, P141, P143
No development may commence until conditions covering land contamination assessment, remediation and verification, plus a piling method statement and a 5 metre buffer from the water main, have been approved in writing by the council, in consultation with Thames Water where required. Report P97, P98, P100, P102, P104, P106, P108, P141, P144
Prior to occupation, conditions require delivery of a ventilation strategy, mechanical filtration, electric induction cooking, zero emission heating, waste water heat recovery, solar battery storage, a solar private network microgrid, a delivery and servicing plan, cycle and refuse storage. Report P86, P89, P92, P115, P121, P127, P130, P132, P135
Options considered
Chosen: Grant full planning permission subject to legal agreement and conditions (officer recommendation). Acceptable in principle, design and amenity terms; contributes to housing supply; subject to conditions and legal agreement on highways, transport and environmental matters. Report P8, P9, P147
Rejected: Refuse the application. Officers found the proposal compliant with relevant policies; objections on amenity, conservation, density, traffic and nuisance are addressed by conditions. Report 3.2, P147, P167
Implications
Equalities: Condition 11 requires 90% of dwellings to meet Building Regulations M4(2) accessible and adaptable standard, with 10% to M4(3) wheelchair user standard. Report P48, P49, P50
Climate: The site is in the borough wide Air Quality Management Area; conditions require zero emission heating, electric cooking, mechanical ventilation filtration, NRMM Stage V compliance, a dust management plan, solar panels, solar battery storage and a solar private network microgrid. Report P110, P113, P115, P121, P127, P132, P135, P112, P118
Risk: Conditions 29-34 require land contamination risk assessment, site investigation, remediation and verification before development commences, because potentially contaminative uses are understood to occur at or near the site. Report P97, P98, P100, P102, P104, P106, P108, P99
Legal: A satisfactory legal agreement must be completed before permission is granted; the Executive Director can make minor changes after consulting Legal and the committee Chair. Report P10
Other: Condition 19 requires a Secure by Design statement including site wide public realm CCTV and feasibility of linking to the council's borough wide CCTV system; condition 45 ties the development to the approved Fire Statement. Report P70, P71, P138, P139
Who and where
Future residents of seven new flats (2 studios, 2 one-bed, 3 two-bed) at 117-123 King Street Report P6, 2.2
Existing occupiers of the five ground floor commercial units and Class E office and leisure floorspace on the site, which are retained Report 1.1, 2.3
Residents of Federal House, 2 Down Place, who submitted 10 objections and an 18-flat petition against the scheme Report 3.2, P167
Occupiers of 105 surrounding properties notified as part of statutory consultation Report 3.1
Adjoining locally listed Art Deco building at 111-115 King Street (Building of Merit) and the Hammersmith Town Hall and Brackenbury Conservation Areas Report 1.2
09/06/2026: Planning and Development Control Committee considers and resolves to authorise grant Report P4
Within 3 years of permission: Development must commence, per standard time limit condition 1 Report P12, P13, P14
Plain English for the jargon
Class C3: Planning use class for dwellinghouses used as a single home; condition 10 prevents use as houses in multiple occupation (Class C4).
Class E: Planning use class covering commercial, business and service uses including retail, offices and leisure, which are retained on the site.
PTAL 6b: Public Transport Accessibility Level rating on a 0-6b scale; 6b is the highest, indicating excellent access to public transport.
AQMA: Air Quality Management Area; the site lies within the borough wide AQMA, triggering several conditions on plant, dust, NRMM, ventilation and zero emission heating.
Secure by Design: Police crime prevention accreditation scheme; condition 19 requires a statement on how its requirements will be met.
NRMM: Non-Road Mobile Machinery; condition 36 requires Stage V NOx and PM10 emissions compliance and registration on the GLA NRMM register.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
RESOLVED That the Executive Director of Place be authorised to grant permission upon the completion of a satisfactory legal agreement and subject to the conditions listed in the report and changes in the Addendum. That the Executive Director of Place, after consultation with the Assistant Director for Legal Services and the Chair of the Planning and Development Control Committee be authorised to make any minor changes to the proposed Head of Terms of the legal agreement or conditions, which may include the variation, addition or deletion of conditions, any such changes shall be within their discretion.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
Applicant: New Hill Limited C/o Latitude Architects 15 Weller Street, London, SE1 1QU
Description: Erection of an additional floor at roof level, and erection of rear extensions at first, second and third floor level in connection with the creation of 2 x studios, 2 x 1 bedroom and 3 x 2 bedroom self-contained flats (Class C3); formation of roof terraces at second and third floor level; erec- tion of external staircases from first to second floor level at the rear of the building; installation of solar panels, rooflights and formation of a roof plant enclosure at roof level; formation of com- mercial bin and cycle stores at the rear of the building and conversion of rear part of the com- mercial property at ground floor level to provide residential bin and cycle stores; installation of a lift overrun; alterations to part of the shopfront to form a new residential entrance comprising of new door and window glazing; replacement of 1no door and window with new at second floor level to the rear elevation.
Drg. Nos: Refer to condition 2.
Application type: Full Planning Application Officer Recommendation:
1) That the Committee resolve that the Executive Director of Place be authorised to grant per- mission upon the completion of a satisfactory legal agreement and subject to the conditions listed below;
2) That the Committee resolve that the Executive Director of Place, after consultation with the Head of Law and the Chair of the Planning and Development Control Committee be author- ised to make any minor changes to the proposed Head of Terms of the legal agreement or conditions, which may include the variation, addition or deletion of conditions, any such changes shall be within their discretion.
Conditions:
1 Time Limit
The development hereby permitted shall not commence later than the expiration of 3 years beginning with the date of this planning permission.
Condition required to be imposed by section 91(1)(a) of the Town and Country Planning Act 1990 (as amended by section 51 of the Planning and Compulsory Purchase Act 2004).
2 Approved Plans
The development hereby permitted shall be carried out in complete accordance with the following approved drawing numbers, other than where those details are altered pursu- ant to the conditions of this planning permission:
+ Approved Documents: • Flood Risk Assessment, Issue 2 Revision 1 dated 20th December 2022 • Fire Statement, Issue 1 dated 11th June 2025 To ensure full compliance with the planning application hereby approved and to prevent harm arising through deviations from the approved plans.
3 Hoarding
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning and Development Control Committee at Hammersmith & Fulham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.