That the River Hamble Harbour Board approves Harbour Works Consent for the proposal set out in paragraph 5 of the report and subject to the following conditions: a. The proposal is to be built in accordance with the details, plans and method set out in paragraph 5. b. A minimum of 7 days advance notice confirming the start of the works must be given to the Harbour Master in order that the Notice to River Users can be issued. c. The applicant should ensure that only coatings and treatments that are suitable for use in the marine environment are used in accordance with best environmental practice. All reasonable precautions will be undertaken to ensure no pollutants enter the waterbody. d. The applicant should ensure that all equipment, temporary structures, waste and/or debris associated with the licensed activities is removed upon completion of the licensed activities. e. The development must be completed within 3 years from the date of the approval granted by the Harbour Board.
Word for word from the decision Hampshire published for this meeting.Source: democracy.hants.gov.uk
2. That the River Hamble Harbour Board approve Harbour Works Consent for the proposal set out in paragraph 5 of this report and subject to the following conditions: a. The proposal is to be built in accordance with the details, plans and method set out in paragraph 5. b. A minimum of 7 days advance notice confirming the start of the works must be given to the Harbour Master in order that the Notice to River Users can be issued. c. The applicant should ensure that only coatings and treatments that are suitable for use in the marine environment are used in accordance with best environmental practice. All reasonable precautions will be undertaken to ensure no pollutants enter the waterbody. d. The applicant should ensure that all equipment, temporary structures, waste and/or debris associated with the licensed activities is removed upon completion of the licensed activities. e. The development must be completed within 3 years from the date of the approval granted by the Harbour Board. Executive Summary
3. This report seeks to:
• Set out an application for Harbour Works Consent made by Royal Southern Yacht Club (via its agent Lymington Technical Services) for the minor rearrangement of a walkway pontoon and the installation of two finger pontoons at the Prince Philip Yacht Haven, Hamble, SO31 4HB.
• Consider the impacts of the proposal on safety and ease of navigation and on the environment of the Hamble Estuary, both during construction and once operational.
Project Description
4. The proposal is for the minor rearrangement of a walkway pontoon and the installation of two finger pontoons within the facility’s existing mooring area. This will require the relocation of one pile and complete removal of another pile. The existing walkway is used to moor vessels, but when relocated as proposed it will provide access only. The two proposed new finger pontoons will replace the lost moorings, resulting in no increase in berth numbers.
5. The following documents have been provided by the applicant to support this application, and reference must be made to these for a full understanding of the proposal (see Appendix 1a, 1b & 1c): • Drawing reference ‘DWG 10907/1A. April 2022, Existing & Proposed Layouts’ • Supporting Document reference ‘10907 Rpt1a June 2022’ • Environmental information document ‘Environmental information to inform any required Habitats Regulations Assessment by the Competent Authority’, reference ‘Document 10907 Rpt 2a June 2022’.
Harbour Authority’s Responsibilities
6. Consent may be granted by the River Hamble Harbour Board permitting harbour works in the River Hamble in accordance with Section 10 of the Southampton Harbour Act 1924 and Section 48 of the Southampton Harbour Act 1949 as amended by the River Hamble Harbour Revision Orders 1969 to 1989. Within the River Hamble Harbour Board’s statutory duties lies the responsibility to ensure that all matters concerning navigational safety and responsibilities under the Habitat Regulations are addressed. This area of responsibility includes the proposed development.
7. Navigational safety issues are addressed through the Port Marine Safety Code and the Harbour’s Safety Management System. Specific issues relevant to this particular application are covered within the Harbour Master’s comments below.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2022-10-07 RHHB HWA Appendix 2 Royal Southern pontoon rearrangement 2022. Habitat Regulations Assessment by Eastleigh Borough Council adopted by RHHAAppendix
56Harbour Works Consent Application - Minor rearrangement of walkway pontoon and installation of two finger pontoons at Prince Philip Yacht HavenThis decision
Harbour Works Consent Application - Minor rearrangement of walkway pontoon and installation of two finger pontoons at Prince Philip Yacht HavenThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.