Agenda item: 11
Alexandra Park and Palace Board 17th November 2015
Report Title: Conservation Report
Report of: Emma Dagnes, Managing Director, Alexandra Park and Palace
1. Purpose 1.1 To provide an update on the Fabric Maintenance Plan and services
2. Recommendations 2.1 That the Board notes the contents of this report
Report Authorised by: Louise Stewart, Chief Executive, Alexandra Park and Palace
Contact Officer: Emma Dagnes, Alexandra Palace & Park, Alexandra Palace Way, Wood Green N22 7AY Tel No. 020 8365 4340
3. Executive Summary 3.1 The budget available for repairs and renewals to the fabric of the buildings is in the region of £158,000 for 2015/16 inclusive of the permitted carry over from 2014/15;
3.2The priority works packages are: Roof Repair Package, Permanent Roof Access, Joinery repairs and redecoration, Great Hall – Clean fabric linings and walkways, Interim Repairs to North Wall, South Elevation/Traitor’s Gate – Brick and render repairs and Conservation Works to Basement Bunkroom
4. Reasons for any change in policy or for new policy development (if applicable) 4.1 N/A
5. Local Government (Access to Information) Act 1985 5.1 N/A
6. FABRIC MAINTENANCE PLAN
The budget available for repairs and renewals to the fabric of the buildings is in the region of £158,000 for 2015/16 inclusive of the permitted carry over from 2014/15. The repair priorities continue to concentrate on making the external envelope weather-tight and safe to access, thereby minimising any further deterioration and unnecessary expense, and adverse impact on event operations and general public.
The priority works packages are as follows:-
6.1Roof Repair Package Urgent glazing repairs and trial abseil access to Palm Court carried out in August, and further glazing repairs in October have addressed the main leaks.
Main Roof Repair Package for the repair of leaking roofs, glazing and abutments to: West Corridor roof; Great Hall main roof and east gutter; Area 7 roof/external wall; East Court dome and atriums, gutters and drainage, has commenced on site. The priority works to the Great Hall, Area 7 and West Corridor shall be completed in October/November 2015 at a value of £44,169 + VAT and remaining works to the East Court in April/May 2016 at a value of £110,712 + VAT. The tender approval report will be presented under the Exempt section of the Board meeting.
6.2Permanent Roof Access
Provision of handrails to Great Hall gutters, recommissioning of existing latch-wires to Great Hall main roof, installation latch-wires and crawl boards to link all access points, as the priority for 2015/16 and additional latch-ways to East and West Lightwells, SW Colonnade, and West Service Yard roofs for early 2016/17. Listed Building Consent has been submitted and a decision is expected in early December, to allow installation in January 2016. The works are being tendered as a single contract to be phased over two years, to suit the budgets available, and should the opportunity arise bring these works forward.
6.3Joinery repairs and redecoration
The extensive external repairs to rotten timber doors, overhaul of windows, and redecoration throughout to Palm Court, Londesborough Room, and Bar & Kitchen, is largely complete. Completion of remaining items was delayed due to the busy events programme and adverse weather, and has been rescheduled for mid- November. The final account is anticipated to be £24,000 + VAT. Alternative paint colours are being trialled on the Bar & Kitchen doors and in the East Court, to inform the selection on the East Wing Restoration and long term redecoration strategy for the whole Palace.
6.4Great Hall – Clean fabric linings and walkways
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CONSERVATION REPORTMinutes | 91 KB | DownloadRead as text |
Follow Alexandra Park and Palace Board at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Oct 2026 | Charitable Trust Progress ReportThe Committee noted the report. | Noted | Open |
| 29 Oct 2026 | FRRAC Chair's Report (Verbal update)The Committee noted the report. | Noted | Open |
| 29 Oct 2026 | Finance ReportThe Committee noted the 2026/27 forecast against revised budget. | Noted | Open |
| 29 Oct 2026 | Panorama Room ReportThe Committee noted the report. | Noted | Open |
| 29 Oct 2026 | Environmental Sustainability UpdateThe Committee noted the contents of this report and approve the Carbon Reduction Plan at Appendix 1. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.