RESOLVED To approve a variation of contract to Kind Diamond Build Consortium to increase their contract value to £1,098,872. Reasons for Decision During the course of construction there have been instructions issued by the Contract Administrator to address issues discovered on site, consequently the construction value has increased from that of tender award. All instructions have been approved under strict change control procedures. The key instructions involve structural works to the roof, removal of the chimney stack, rebuilding the bay at the front of the property, provision of structural uPVC windows in lieu of timber windows and the supply of alternative fire doors. Alternative Options Considered The option of doing nothing would mean that future invoices received for work already carried out would not be able to be paid. Initiating a new procurement activity to undertake the varied works would not have been cost efficient for the Council having a well-established contractor on site and would have severely impacted on the completion of this project which was considered a particular priority project during the current Covid-19 pandemic. Furthermore, to have seen two contractors on site would have created risks around co-ordination and safety and likely have invalidated certain warranties.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
3.1For Cabinet to approve a variation of contract to Kind Diamond Build Consortium to increase their contract value to £1,098,872. 4. Reasons for Decision
4.1During the course of construction there have been instructions issued by the Contract Administrator to address issues discovered on site, consequently the construction value has increased from that of tender award. All instructions have been approved under strict change control procedures.
4.2The key instructions involve structural works to the roof, removal of the chimney stack, rebuilding the bay at the front of the property, provision of structural uPVC windows in lieu of timber windows and the supply of alternative fire doors. 5. Alternative Options Considered
5.1The option of doing nothing would mean that future invoices received for work already carried out would not be able to be paid.
5.2Initiating a new procurement activity to undertake the varied works would not have been cost efficient for the Council having a well-established contractor on site and would have severely impacted on the completion of this project which was considered a particular priority project during the current Covid-19 pandemic.
5.3Furthermore, to have seen two contractors on site would have created risks around co- ordination and safety and likely have invalidated certain warranties.
6. Background information
6.1Linden House used to be an 8 bedded residential care home and has now been refurbished and converted into supported living accommodation consisting of 4 self- contained flat units.
6.2Kind Diamond Build Consortium Ltd were appointed as the contractor for the Linden Road project through competitive tender process.
6.3Their appointment was approved by Cabinet in July 2019.
6.4The project started on site on 14th October 2019 with a completion date of 28th April 2020. However, during the strip out phase of the project several structural issues related to the roof and the chimney stack structure within the building were uncovered along with some previously unknown asbestos leading the Contract Administrator to award an extension of time. This extension of time and all variations to date have been approved under change control procedures.
6.5The project continued through the current Covid pandemic and was identified an ‘essential project’ because the assisted living accommodation would provide for adults with autism on completion.
6.6Further structural issues were identified when it was discovered that the windows on the front elevation of the building were in fact structural elements, as there were no lintels to their openings. it was also found that the bay frontage was not tied back to the main building. Rectification of these two issues resulted in a further extension of time being granted.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.