Resolved

RESOLVED 1. To approve pursuant to the Council’s Contract Standing Orders (CSO) 9.07.01d, the appointment of Contractor A (named in the exempt part of the report) to undertake building works to provide a total of eight Council rented homes at land opposite 16 Park Road/Edith Road for a total contract sum as set out in the exempt part of this report and approves the client contingency sum set out in 1.6 of the exempt part of the report (Appendix 2); 2. To approve the issuance of a letter of intent up to a maximum value of no more than 10% of the contract sum. 3. To approve the appropriation of the land opposite 16 Park Road/Edith Road N11 highlighted in the red line boundary plan attached at Appendix 1 from housing purposes to planning purposes under Section 122 of the Local Government Act 1972 as it is no longer required for the purpose for which it is currently held, and for the purpose of carrying out development as set out in paragraph 6.4 of this report. 4. To approve the use of the Council’s powers under Section 203 of the Housing and Planning Act 2016 to override easements and other rights of neighbouring properties infringed upon by the development of land opposite 16 Park Road/Edith Road N11, under planning permission Ref: HGY/2020/0589; and 5. To approve the appropriation (after practical completion of the development) of the land opposite 16 Park Road/Edith Road N11 (edged red in the boundary plan attached at Appendix 1) from planning purposes back to housing purposes Reasons for decisions On 3 December 2019 Cabinet included the land opposite 16 Park Road/Edith Road N11 into the Council ’s housing delivery programme. This scheme has subsequently been granted planning consent and is ready to progress to construction. This report therefore marks the third, ... view the full minutes text for item 535.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet, 8 pages

Report for: Cabinet 15 June 2021

Title: Approval of construction contract and land appropriation at land opposite 16 Park Road Report Authorised by: David Joyce, Director of Housing, Regeneration and Planning

Lead Officer: Robbie Erbmann, Assistant Director for Housing

Ward(s) affected: Bounds Green

Report for Key/ Non Key Decision: Key Decision

1. Describe the issue under consideration 1.1 This report seeks Cabinet’s approval, in light of engagement with local residents, to deliver eight new Council homes for Council rent on Council land opposite 16 Park Road/Edith Road N11. These new homes will consist of two three-bedroom town houses, one of which is fully adaptable, five two-bedroom flats, one of which is fully accessible for wheelchair-users, and one four-bedroom duplex apartment. The scheme was given detailed planning permission on 3 July 2020. If approved, the scheme will improve the existing public realm and the deliver the first true zero carbon homes for the Council.

1.2In order to facilitate this, Cabinet is being asked to approve use of the Council’s powers to appropriate the land for planning purposes and to override any easements.

1.3Cabinet is asked in light of a formal procurement exercise to approve the appointment of contractor A (exempt - further details in exempt report), to deliver these new Council homes on a vacant former car park site at Land opposite 16 Park Road/Edith Road N11 (See Appendix 1).

2. Cabinet Member Introduction 2.1 This Council remains committed to delivering the new era of Council homes that Haringey’s communities need.

2.2I’m proud to recommend building eight new Council homes for social rent on the council-owned brownfield site in Park Road, Bounds Green. The homes will be made up of: two three-bedroom houses, one of which is fully adaptable; five two- bedroom flats, one of which is fully accessible for wheelchair-users, and one four- bedroom duplex apartment. These homes will give eight families a new start and the opportunity for a secure future in Haringey.

2.3If approved, they will be the Council’s first zero carbon homes, achieving the GLA target of zero carbon through onsite means. The scheme makes use of state-of- the art thermal insulation, energy-efficient fittings, solar panels and air source heat pumps. Wildflower green roofs and generous outdoor space will increase the area’s biodiversity, transforming a vacant site currently occupied by derelict garages.

3. Recommendation 3.1 It is recommended that Cabinet: 3.1.1. Approves pursuant to the Council’s Contract Standing Orders (CSO) 9.07.01d, the appointment of Contractor A (named in the exempt part of the report) to undertake building works to provide a total of eight Council rented homes at land opposite 16 Park Road/Edith Road for a total contract sum as set out in the exempt part of this report and approves the client contingency sum set out in 1.6 of the exempt part of the report (Appendix 2);

3.1.2. Approves the issuance of a letter of intent up to a maximum value of no more than 10% of the contract sum;

3.1.3. Approves the appropriation of the land opposite 16 Park Road/Edith Road N11 highlighted in the red line boundary plan attached at Appendix 1 from housing purposes to planning purposes under Section 122 of the Local Government Act 1972 as it is no longer required for the purpose for which it is currently held, and for the purpose of carrying out development as set out in paragraph 6.4 of this report.;

3.1.4. Approves the use of the Council’s powers under Section 203 of the Housing and Planning Act 2016 to override easements and other rights of neighbouring properties infringed upon by the development of land opposite 16 Park Road/Edith Road N11, under planning permission Ref: HGY/2020/0589; and

3.1.5. Approves the appropriation (after practical completion of the development) of the land opposite 16 Park Road/Edith Road N11 (edged red in the boundary plan attached at Appendix 1) from planning purposes back to housing purposes

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Red Line PlanAppendix 1 1 pages Download
PDF
Approval of construction contract and land appropriation at land opposite 16 Park RoadMinutes 8 pages DownloadRead as text

At this meeting

Whole meeting
521MinutesOn the agenda 524To consider the Scrutiny Panel Review on Noel Park Major Works Programme and further consider the response to the Scrutiny recommendations.On the agenda 525London Borough of Haringey Gambling Act PolicyApproved 526Community Carbon Offset Fund Spending StrategyApproved 527The Regulation of Investigatory Powers Act 2000 (RIPA) and Investigatory Powers Act 2016: Use of powers by the Council in 2020Noted 528Permanent Recruitment Agency Supply Chain to support the insource recruitment serviceApproved 529Wavier Contract to Citizen's Advice Bureaux for the Information, Advice and Guidance service for 9 monthsApproved 530Stroud Green Primary School - Phase 1 External Envelope and Building Services Improvement Works – Award of Construction ContractApproved 531Approve the Appointment of Contractor for Seven Sisters Primary School Building Services and External Envelope Works Phase 1Approved 532Approve the Appointment of Contractor for Campsbourne Primary School Building Services and External Envelope Works Phase 1Approved 533Bruce Grove Primary School - External Envelope and Building Services Improvement Works – Award of Construction ContractApproved 534Approval to develop 57 White Hart Lane into supported accommodation for young people with complex learning disabilities and autismApproved
535Approval of construction contract and land appropriation at land opposite 16 Park RoadThis decision
536Award of contract for Automatic Opening Ventilation worksApproved 537Award of Contract for a Social Care SystemApproved 538Establishment of the Corporate Parenting Committee and Appointment of Cabinet Members to Committees and Partnerships 2021-22 & Confirmation of their Terms of Reference.Noted 539Minutes of Other BodiesNoted 540Significant and Delegated ActionsNoted 542Exclusion of the Press and PublicDecided 550Exempt MinutesPrivate

On this subject at Haringey

Search all
  1. Approval of construction contract and land appropriation at land opposite 16 Park RoadThis decision
  2. Approval to deliver Council homes and let construction contract within Tiverton Estate boundary N15 6RRDecided
  3. Approval to deliver Council homes and let construction contract within Sir Frederick Messer Estate boundary N15Decided
  4. Jansons Road - Approval of Housing Construction ContractApproved
  5. Grasmere Court, N22 - Approval of housing construction contract and land appropriationApproved
  6. Approval of housing construction contract at land adjacent Wat Tyler House Boyton Road .Approved

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open
10 Nov 2026 Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies