London Borough of Haringey
Cabinet, Tuesday 15 June 2021 at 6.30pm

Approval to develop 57 White Hart Lane into supported accommodation for young people with complex learning disabilities and autism

Approved Executive 3 papers

Cabinet approved this item on Tuesday 15 June 2021. Below is the council's own wording, with the papers it was decided on.

Item534

Resolved

RESOLVED That the 57 White Hart Lane site is approved for redevelopment into supported accommodation for young people with complex learning disabilities and autism with a capital value of £3.650m, to support them to remain living in their local area. That £2.665m of capital funding from the supported living capital programme allocation is committed to develop this scheme. That the Council enters into a capital grant agreement with NHS England to accept the award of £985,000 for the development of this project. ... view the full minutes text for item 534.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet, 10 pages

Recommendations

3.1Cabinet is asked to approve that:

a) The 57 White Hart Lane site is approved for redevelopment into supported accommodation for young people with complex learning disabilities and autism with a capital value of £3.650m, to support them to remain living in their local area.

b) £2.665m of capital funding from the supported living capital programme allocation is committed to develop this scheme.

c) The Council enters into a capital grant agreement with NHS England to accept the award of £985,000 for the development of this project.

d) The Council commissions and procures design and construction partners to develop the 57 White Hart Lane site into supported accommodation.

e) Following a period of design development, procurement and operational planning, a further report will be brought back to Cabinet for approval of the operational strategy, final scheme design and procurement of the chosen construction partner.

Reasons for decision

4.1This development project seeks to utilise a soon-to-be vacant property, to address the need for local supported housing for young people with complex learning disabilities and autism.

4.2This cohort are often placed in costly, out-of-area residential colleges if they are unable to live with their family. The development of an in-borough service to support this cohort, will generate savings in comparison to the use of high-cost out of borough placements. This will contribute to the People Priority’s Medium Term Financial Strategy (MTFS) savings.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
. 57 White Hart Lane Site planAppendix A 1 pages Download
PDF
. EqIA: 57 White Hart Lane signedAppendix B 12 pages Download
PDF
Approval to develop 57 White Hart Lane into supported accommodation for young people with complex learning disabilities and autismMinutes 10 pages DownloadRead as text

At this meeting

Whole meeting
521MinutesOn the agenda 524To consider the Scrutiny Panel Review on Noel Park Major Works Programme and further consider the response to the Scrutiny recommendations.On the agenda 525London Borough of Haringey Gambling Act PolicyApproved 526Community Carbon Offset Fund Spending StrategyApproved 527The Regulation of Investigatory Powers Act 2000 (RIPA) and Investigatory Powers Act 2016: Use of powers by the Council in 2020Noted 528Permanent Recruitment Agency Supply Chain to support the insource recruitment serviceApproved 529Wavier Contract to Citizen's Advice Bureaux for the Information, Advice and Guidance service for 9 monthsApproved 530Stroud Green Primary School - Phase 1 External Envelope and Building Services Improvement Works – Award of Construction ContractApproved 531Approve the Appointment of Contractor for Seven Sisters Primary School Building Services and External Envelope Works Phase 1Approved 532Approve the Appointment of Contractor for Campsbourne Primary School Building Services and External Envelope Works Phase 1Approved 533Bruce Grove Primary School - External Envelope and Building Services Improvement Works – Award of Construction ContractApproved
534Approval to develop 57 White Hart Lane into supported accommodation for young people with complex learning disabilities and autismThis decision
535Approval of construction contract and land appropriation at land opposite 16 Park RoadApproved 536Award of contract for Automatic Opening Ventilation worksApproved 537Award of Contract for a Social Care SystemApproved 538Establishment of the Corporate Parenting Committee and Appointment of Cabinet Members to Committees and Partnerships 2021-22 & Confirmation of their Terms of Reference.Noted 539Minutes of Other BodiesNoted 540Significant and Delegated ActionsNoted 542Exclusion of the Press and PublicDecided 550Exempt MinutesPrivate

On this subject at Haringey

Search all
  1. Approval to develop 57 White Hart Lane into supported accommodation for young people with complex learning disabilities and autismThis decision
  2. Approval to enter into grant funding agreement (Memorandum of Understanding - MOU) to support delivery of phase one of the Selby Urban Village Redevelopment ProposalsAgreed

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open
10 Nov 2026 Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies