Award of Contract for Alexandra House and 48 Station Road Refurbishment Works

Approved Executive 1 paper

Cabinet Member Signing approved this item on Friday 18 March 2022. Below is the council's own wording, with the papers it was decided on.

Item3

Resolved

RESOLVED 1. Pursuant to Contract Standing Order 16.02, to approve an award of contract to Alcema Ltd for the sum of £3,665,316 to deliver the part refurbishment and redecoration of Alexandra House and the full refurbishment of office floors in 48 Station Road. 2. Pursuant to Contract Standing Order 16.02, to approve the issuance of a letter of intent for up to 10% of the contract value, totalling £366,531. 3. To approve the contingency sum as set out in the exempt part of this report (Part B). 4. To approve the delegation as set out in the exempt part of this report (Part B). Reasons for decision The report “Station Road Refurbishment Works” approved at Cabinet on 9 th November 2021 gave three reasons for programme. Firstly, to deliver office accommodation improvements, noting the poor standard of existing office accommodation, and the need for essential maintenance as well as interior redecoration. Secondly, to enable the continued adoption of flexible working, so that officers can work in and for the borough, whilst maintaining a good work-life balance through the adoption of Hybrid working. The plans will modernise audio-visual equipment, office layouts and furniture to provide a variety of work settings to enable greater cross-service collaboration and partnership working. Thirdly, it supports short-term goals in the Accommodation Strategy, such as the release of 40 Cumberland Road to be repurposed as an Enterprise Hub. This aligns with the overall aim of relocating core office and civic functions to the refurbished Civic Centre in 2025, by ensuring the buildings the Council occupies in the interim are maintained in suitable condition. The proposed contract enables the Council to meet these objectives and achieve value for money and delivery of the works within an acceptable timeframe. The letter of intent is required to enable the preferred contractor to begin mobilisation at an early stage, thereby expediting delivery of the programme. The rationale for the additional recommendation is also set out in the exempt part of the report. Alternative options considered Do Nothing This option, which is not to appoint Alcema Ltd to undertake the proposed works, is not recommended as the Council would fail to achieve the agreed Accommodation objectives as set out it the November cabinet report. This would mean the Council would be left without suitable office workspace for its staff, and significant operational difficulties in achieving plans for more flexible working. Further information on why this is not recommended is set out in the Exempt Part B. Other redecoration / refurbishment options Other options for proceeding with a different scope of works were considered and rejected at an earlier stage ... view the full minutes text for item 3.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Recommendations

The Cabinet Member for Finance and Transformation is asked:

3.1Pursuant to Contract Standing Order 16.02, to approve an award of contract to Alcema Ltd for the sum of £3,665,316 to deliver the part refurbishment and redecoration of Alexandra House and the full refurbishment of office floors in 48 Station Road.

3.2Pursuant to Contract Standing Order 16.02, to approve the issuance of a letter of intent for up to 10% of the contract value, totalling £366,531.

3.3To approve the contingency sum as set out in the exempt part of this report (Part B).

3.4To approve the delegation as set out in the exempt part of this report (Part B)

Reasons for decision

4.1The report “Station Road Refurbishment Works” approved at Cabinet on 9th November 2021 gave three reasons for programme. 4.2 Firstly, to deliver office accommodation improvements, noting the poor standard of existing office accommodation, and the need for essential maintenance as well as interior redecoration. 4.3 Secondly, to enable the continued adoption of flexible working, so that officers can work in and for the borough, whilst maintaining a good work-life balance through the adoption of Hybrid working. The plans will modernise audio-visual equipment, office layouts and furniture to provide a variety of work settings to enable greater cross- service collaboration and partnership working. 4.4 Thirdly, it supports short-term goals in the Accommodation Strategy, such as the release of 40 Cumberland Road to be repurposed as an Enterprise Hub. This aligns with the overall aim of relocating core office and civic functions to the refurbished Civic Centre in 2025, by ensuring the buildings the Council occupies in the interim are maintained in suitable condition. 4.5 The proposed contract enables the Council to meet these objectives and achieve value for money and delivery of the works within an acceptable timeframe. 4.6 The letter of intent is required to enable the preferred contractor to begin mobilisation at an early stage, thereby expediting delivery of the programme. 4.7 The rationale for the additional recommendation is also set out in the exempt part of the report.

Alternative options considered

5.1Do Nothing 5.5.1 This option, which is not to appoint Alcema Ltd to undertake the proposed works, is not recommended as the Council would fail to achieve the agreed Accommodation objectives as set out it the November cabinet report. 5.5.2 This would mean the Council would be left without suitable office workspace for its staff, and significant operational difficulties in achieving plans for more flexible working. 5.5.3 Further information on why this is not recommended is set out in the Exempt Part B.

5.2Other redecoration / refurbishment options 5.5.2 Other options for proceeding with a different scope of works were considered and rejected at an earlier stage and are set out in the November Cabinet Report.

6. Background Information

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Award of Contract for Alexandra House and 48 Station Road Refurbishment WorksMinutes 156 KB DownloadRead as text

At this meeting

Whole meeting
3Award of Contract for Alexandra House and 48 Station Road Refurbishment WorksThis decision
4Exclusion of the Press and PublicDecided

Who was there

1 of 2 attended
ID
Councillor Isidoros DiakidesCommittee Member, present
FR
Fiona RaeSecretary, expected

On this subject at Haringey

Search all
  1. Award of Contract for Alexandra House and 48 Station Road Refurbishment WorksThis decision
  2. Contract Award - Procurement of Enforcement Agency Services via the YPO Framework to collect PCN related debt for the AuthorityDecided
  3. Direct Award and of Residential and Nursing Care Block Contracts with OurrisDecided
  4. Selby Urban Village - award of contracts for heat supply arrangementsNoted
  5. Woodridings Court N22 Award of Construction ContractApproved
  6. Approval to Award Contract, Kings Road Car Park, N17Approved

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies