London Borough of Haringey
Cabinet, Tuesday 20 October 2026 at 6.30pm

Selby Urban Village - award of contracts for heat supply arrangements

Noted Executive 1 paper

AI summaryHaringey Cabinet approves 40-year heat supply contracts with Energetik for Selby Urban Village, covering 202 new council homes, a community centre, sports pavilion and commercial unit. Two councillors recused themselves.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedHeat Connection Agreements and Framework Supply Agreement approved
MoneyValues in exempt reportTotal contract value not disclosed in public papers
What happens nextFinalise and execute contractsDelegated authority to Corporate Director of Finance and Resources
Who it affects202 new council homes and community buildingsSelby Village, Selby Centre, Sports Pavilion, commercial unit

What was decided

Cabinet approved awarding 40-year Heat Connection Agreements to Lee Valley Heat Network Operating Company Limited (trading as Energetik) for the residential development, commercial unit, Selby Centre and Sports Pavilion. Report P1

Cabinet also approved a 40-year Framework Supply Agreement with Energetik, committing the council to supply costs under subsidiary supply agreements over the contract term. Report 3.2

Delegated authority was granted to the Corporate Director of Finance and Resources, in consultation with the Head of Legal and the Lead Member for Placemaking, to finalise terms and execute the contracts. Report 3.9

Why

Planning approvals and council policy require connection to a district heat network on fair and reasonable commercial terms, and Energetik is the only viable district heat network in the area. Report 4.1, 4.2

Under the Landlord and Tenant Act 1985 the council must provide a working heating system for secure tenants, including the 202 council homes being built, and for the new community and commercial buildings. Report 4.4

Alternative options, including an on-site energy centre or connecting to other heat networks, were considered but discounted as not viable or not cost-effective. Report P15, 5.2, 5.3

What happens next

Finalise contract terms and execute the Heat Connection Agreements and Framework Supply Agreement under delegated authority. Report 3.9

Set up ongoing contract management across Housing Revenue Account and General Fund, with resource and budget for a suitably qualified officer to manage the framework contract. Report 6.31, 6.35

Build works for Phase 1 are scheduled to commence in September 2026, with Phase 2 expected to start in February 2028 and complete by July 2030. Report 6.2

The money

  • £92m in low-cost central government loans secured by Energetik Central government support for Energetik network Report 6.10
  • £500,000 or more Threshold for Cabinet contract approval under CSO 2.01 c) Report 8.13

Options considered

  • Rejected: Do not connect to the Energetik district heat network. Planning policy requires connection unless terms are not fair and reasonable; terms are deemed fair and reasonable Report P15
  • Rejected: Connect to a different district heat network supplier. Capital costs and feasibility of running pipework from other networks (e.g. Stratford, Brent) render it unviable Report 5.2
  • Rejected: Procure connection and supply from Energetik but run residential network management in-house. Technical advice found ongoing high financial, resource and capacity implications; Energetik management is more cost-effective Report 5.3

Implications

  • Financial: Capital connection costs are within the existing approved Selby Urban Village project budget; ongoing revenue costs will fall to the Housing Revenue Account for residential and to the General Fund for commercial voids and units. Report 6.30, 6.31, 8.3, 8.4
  • Legal: The award qualifies as an exempted utilities contract under Schedule 2, paragraph 31 of the Procurement Act 2023, and the Director of Legal and Governance confirmed no legal reasons preventing approval. Report 8.7, 8.11, 8.14
  • Equalities: Annual price increases could disproportionately affect low-income, disabled and older residents; mitigation includes Ofgem regulation, consumer protection provisions, and ongoing contract management. Report 8.18, 8.19
  • Climate: Connection to Energetik aligns with low-carbon targets; 90% of Energetik's heat is expected to come from a low-carbon Energy Recovery Facility by July 2029, though this is dependent on the North London Waste Authority construction programme. Report 6.11, 7.3, 7.4
  • Risk: Risks include reliance on the North London Waste Authority's construction programme for low-carbon heat availability, and the need for clear contract management to avoid revenue responsibilities falling between teams. Report 6.35
  • Staffing: A suitably qualified and experienced officer will likely be needed to manage the Framework Supply Contract, with related resource and budget implications. Report 6.35

Who and where

  • Future residents of the 202 new council homes at Selby Urban Village Report 6.2, 4.4
  • Social housing tenants, who will pay the Tenant's Availability Charge and variable usage charges Report 3.5, 3.6
  • Commercial tenants of the Selby Centre, Sports Pavilion and commercial unit, who will pay availability and variable usage charges Report 3.7
  • The council's Housing Revenue Account and General Fund, which will fund landlord availability charges and void property heat costs Report 3.4, 3.8, 6.31

Timeline

  • September 2026: Phase 1 works scheduled to commence Report 6.2
  • 2026-10-20: Cabinet decision to award heat supply contracts
  • January 2027: Energetik to be fully regulated by Ofgem under the new heat network authorisation regime Report 6.13
  • January 2028: Phase 1 works expected to complete Report 6.2
  • February 2028: Phase 2 works expected to commence Report 6.2
  • July 2029: Classified low-carbon heat expected to be available from the Energy Recovery Facility Report 6.11
  • July 2030: Phase 2 works anticipated to complete Report 6.2
  • 2026 to 2066: 40-year contract term for Connection Agreements and Framework Supply Agreement Report P44, P47

Plain English for the jargon

  • Energetik: Trading name of Lee Valley Heat Network Operating Company Limited, a heat network utility company fully owned by Enfield Council, supplying around 1700 domestic customers.
  • Heat Connection Agreement: 40-year agreement covering connection of buildings to the Energetik heat network, including pipework, technical requirements, ownership, maintenance and payment obligations.
  • Framework Supply Agreement: Overarching 40-year contract governing heat supply, service standards, billing, customer services and subsidiary supply agreements.
  • Availability Charge: Fixed charge paid to secure availability of heat supply, split between Landlord (paid by the council) and Tenant (paid by the resident) for residential units.
  • Landlord and Tenant Act 1985, Section 11: Statutory duty on landlords to provide and maintain a working heating system for secure tenants.
  • NLWA: North London Waste Authority, whose construction programme for the Energy Recovery Facility affects the timing of low-carbon heat availability.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item55

Resolved

DECLARATIONS OF INTEREST MADE FOR THIS ITEM: Cllr Beckford noted that they were appointed by the Council to the membership of the North London Waste Authority in May 2026 by virtue of my Cabinet responsibilities. The North London Waste Authority have a working relationship with the Lee Valley Heat Network referred to in the report and recommendations. It was noted that Councillor Beckford was granted dispensation to vote on matters relating to North London Waste Authority by the Standards Committee in June. Councillor Kuper noted that they were appointed by the Council to the membership of the North London Waste Authority the North London Waste Authority agreed by full Council in July. The North London Waste Authority have a working relationship with the Lee Valley Heat Network .Due to Committee meeting scheduling, the Standards Committee are due to consider a dispensation in relation to my council membership role of North London Waste Association at their November meeting and therefore recused themselves from the meeting at items 15 and 23.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet

Report for: Cabinet, 20 October 2026

Item number: 15

Title: Selby Urban Village – award of contracts for heat supply arrangements

Report authorised by: Jess Crowe, Corporate Director for Culture, Strategy and Communities

Lead Officer: David Sherrington, Head of Estate Renewal

Ward(s) affected: Bruce Castle (LB Haringey), Upper Edmonton (LB Enfield)

Key/Non Key Decision: Key decision

1. Describe the issue under consideration

1.1The Selby Urban Village (SUV) development is a partnership between the Council and the Selby Trust to transform the Selby Centre site and Bull Lane Playing Fields into a new accessible and well-connected neighbourhood, made up of 202 new council homes, new sporting facilities, improved open space, play facilities and a new Community Centre.

1.2The SUV development consists of “Phase One” delivering a new community building, a pavilion building with changing rooms, improved park and sports pitches. “Phase Two” will deliver 202 new Council homes alongside a small commercial unit of 112 sqm.

1.3The development received planning permission in 2025 under two planning approvals as the site comes within both Enfield’s Planning Authority (Phase One - 24/03470/FUL) and Haringey’s Planning Authority (Phase Two - HGY/2024/2851), and was referred to the GLA sue to scale. The planning approvals follow LBH, LBE and GLA energy policy, requiring the SUV development to connect to a district heat network on “fair and reasonable commercial terms” and unless “not possible, practical or viable to connect”.

1.4A main works contractor has been appointed to deliver for Phase One and Phase Two and have been mobilising on site and undertaking preparatory works, aiming to formally commence Phase One in Autumn 2026. This mobilisation period includes RIBA stage 4 detailed design of heat supply infrastructure, based on the tender pack information which included connection to a district heat network.

1.5On 8 January 2026 Cabinet approved a procurement exercise for Selby Urban Village (SUV) heat supply contracts, via direct negotiations with the district heat network, Lee Valley Heat Network Operating Company Limited (company number: 09763702), referred to by their trading name as ‘Energetik’ in this report.

1.6In line with Contract Standing Order (CSO) 2.01 (c), this report seeks approval to award contracts to a third-party heat supplier for the heat connection agreements and supply agreements (including management/ maintenance of residential secondary network) for 40 years for the Selby Urban Village development, to ensure that the construction site, residents, tenants, and building users of the new development are supplied with heat during and upon completion of the build.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Selby Urban Village: award of contracts for heat supply arrangementsMinutes 838 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 20 attended
TE
Taryn EvesCouncil Staff, expected
AD
Andy DonaldOfficer, expected
FA
Fiona AldermanCouncil Staff, expected
AG
Ann GrahamOfficer, expected
BF
Barry FrancisCouncil Staff, expected
JC
Jess CroweOfficer, expected
AS
Ayshe SimsekSecretary, expected
SB
Stephen Bramah-CalvertOfficer, expected
CM
Claire McCarthySecretary, expected
MB
Councillor Mark BlakeChair, expected
TH
Councillor Tammy HymasVice-Chair, expected
GI
Councillor Gio IozziCommittee Member, expected

All 20 on the meeting page

On this subject at Haringey

Search all
  1. Selby Urban Village - award of contracts for heat supply arrangementsThis decision
  2. Selby Urban Village - approval to procure Artificial Grass Pitch works contractorDecided
  3. Selby Urban Village - Procurement strategy for heat supply arrangementsApproved
  4. Award of contract for Employers Agent services for Phase 1 (Selby Centre + Sports Facilities) and Phase 2 (Housing of the Selby Urban Village ProjectApproved
  5. Gateway 0 Report - Phase 2, Selby Urban Village, N17 - Bruce Castle WardNoted
  6. Contract award to KCA for design and architectural services for the Selby Urban Village masterplanApproved

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open
10 Nov 2026 Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies