Alexandra Park and Palace Joint Advisory & Consultative Committee noted this item on Thursday 17 November 2022. Below is the council's own wording, with the papers it was decided on.
RESOLVED The committee are asked to: a. To note the updates, and; b. To consider the proposal to apply to the Local Planning Authority for Planning and Listed Building Consent to extend the use of the shaded wooden structure (the pagoda) on The Beach for two additional months a year (from March to November each year).
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
Report to Alexandra Park and Palace Joint Advisory & Consultative Committee, 3 pages
Recommendations
1.1To note the updates, and;
1.2To consider the proposal to apply to the Local Planning Authority for Planning and Listed Building Consent to extend the use of the shaded wooden structure (the pagoda) on The Beach for two additional months a year (from March to November each year).
Executive summary
2.1In 2019 the Committees were consulted on a proposal to install outdoor shading structures on The Beach area of the Phoenix Bar & Kitchen which was subsequently installed when the Trust was granted the required Listed Building Consent and Planning Permission.
2.2The conditions of consent were that the temporary shaded seating structure with benches would be removed annually outside of the months of March – September.
2.3For the reasons outlined below, the Trust is seeking to apply for an extension to the number of months the structure is permitted to be in place on The Beach, from 7 months (March-September) to 9 months in the year (March-November).
2.4The Advisory and Consultative Committee are invited to provide comments to the Trustee Board and to note the updates on the projects presented to the Committees in June. 3. Update on projects brought to the SAC/CC in June.
3.1Following the SAC/CC meeting in June, where several projects that require consent (planning, LBC or advert, or a combination of) were discussed, the team have progressed several workstreams with some applications now submitted.
3.2The Listed Building Consent application to create a new opening from the East Court into the South East Office Building and the planning and advertisement consent application for the Parking Management System (parking charges) project have been submitted and are in the process of being checked.
3.3On 15 July, a formal pre-application meeting with the Haringey team took place to discuss the skywalk adventure proposal. Representatives from planning, conservation and transport were present. In principle, there was unanimous support for the proposal, as the planning team appreciated how the project aligned with the Trusts objectives and that it was a new, exciting and innovative way for visitors to enjoy the heritage setting of the Park and Palace whilst learning about its eclectic and inspiring past, present and future.
3.4The Planning Authority has advised that to ensure the proposal is acceptable in planning and heritage terms, there needs to be an assessment undertaken on the existing make-up and condition of the Great Hall roof and a clear understanding of how new interventions into the listed fabric will be minimal, and the impact mitigated. It is also fundamental that the proposal does not have a negative impact on the local views of the Palace. These are all matters and considerations that had been previously identified by the APPCT team and therefore we are confident that we address these matters as part of the application which will be submitted Within the next few months.
3.5Work to progress the Beach improvements project and the East Court Café Restaurant will commence in early 2023.
4. Pagoda time limit extension (location in front of the Phoenix Bar & Kitchen)
4.1We will be applying for an extension to the time limit for the temporary pagoda on the Beach which is the area in-front of the Phoenix Bar and Kitchen) currently we are permitted to have the pagoda in place during the months from March to September (inclusive). We are simply applying for an extension to the time limit of 2 months (March – November inclusive).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Alexandra Park and Palace Joint Advisory & Consultative Committee at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.